London Borough of Haringey
Cabinet Member Signing, Monday 5 January 2026 at 3.00pm

To award a new asbestos contract and appoint a UKAS accredited asbestos contractor.

Decided Executive 1 paper

AI summaryHaringey Cabinet Member awards asbestos services contract worth £1,815,540 to Tenderer A for up to four years, with a £181,554 letter of intent to bridge mobilisation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedAsbestos surveying, bulk sampling and air monitoring
Money£1,815,540.00 plus project specific sumsUp to four years, plus £181,554 letter of intent
What happens nextLetter of intent to be issuedTo enable mobilisation before formal contract signed
Who it affectsCouncil tenants, leaseholders, staff, visitorsAll users of properties managed by the Council

What was decided

The Cabinet Member for Housing & Planning and Deputy Leader approved awarding the asbestos services contract to Tenderer A for £1,815,540.00, plus additional project specific costs, for up to four years. Report 3.1

Delegation of additional expenditure under the contract was approved to the Assistant Director of Repairs & Compliance in consultation with the Head of Finance. Report 3.2

Approval was given to issue a letter of intent to the preferred contractor for up to £181,554.00, equal to 10% of the surveying contract sum, to enable mobilisation. Report 3.3

Why

The Council must comply with the Health and Safety at Work Act 1974 and the Control of Asbestos Regulations 2012, and cannot allow a break in asbestos service provision that would put residents and building users at risk. Report 4.1, 6.1, 6.2

A seamless changeover between the old and new contracts was required by the end of December 2025, making the letter of intent necessary. Report 4.2, 3.3

Tenderer A scored 95.50 against Tenderer B's 66.40 on a 50% quality, 40% price and 10% social value basis, and offered a social value commitment of £297,063. Report 6.8, 6.9

What happens next

Issue a letter of intent for up to £181,554.00 to Tenderer A so mobilisation can start while the formal contract is finalised. Report 3.3, 6.2

Finalise the formal contract for asbestos surveying, bulk sampling and air monitoring for up to four years. Report 3.1, 6.3

Monitor the contractor's social value commitment through monthly reports from the Project Manager.

The money

  • £1,815,540.00 Sum awarded to Tenderer A for asbestos surveying, bulk sampling and air monitoring, plus additional project specific sums, for up to four years Report 3.1
  • £181,554.00 Letter of intent to the preferred contractor, up to 10% of the surveying contract sum, to enable mobilisation Report 3.3
  • £297,063 Social value commitment from Tenderer A covering job creation, training, local skills and local business support
  • £1,476,631 over 3.5 years Revenue element of the contract, met from the Fire Risk and Asbestos revenue budget (J19720) Report P32
  • £411k Original 2025/26 revenue allocation, now estimated at £102k due to the delayed contract start Report P32

Options considered

  • Chosen: Award the contract to Tenderer A as recommended. Highest score at 95.50, with strong quality, favourable pricing and a £297,063 social value commitment Report 3.1, 6.8, 6.9
  • Rejected: Do nothing. Would prevent the Council from delivering statutory services under Health and Safety legislation Report 5.1
  • Rejected: Carry out the work through in-house resources. Lack of suitably trained and certified operatives, recruitment timescales and insurance premiums make this unviable Report 5.2
  • Rejected: Use existing contracts or contractors. Current contracts have expired or reached extension limits, so a new contract is needed for compliance and current pricing Report 5.3

Implications

  • Legal: Award is made under Contract Standing Orders 2.01(c), 8.01 and 16.04, using the London Construction Programme Dynamic Purchasing System, and the Director of Legal and Governance raises no legal objection. Report P36, P40, P41, P42, P45, P46
  • Financial: The contract is contained within the approved budget envelope with no requirement for additional funding; capital comes from the HRA Major Works Capital Programme and revenue from budget J19720, with uplifts and indexation built in. Report P32, P33
  • Equalities: No foreseeable negative impacts on protected characteristic groups are identified, and managing properties safely under asbestos regulations is expected to have a positive impact on residents, with contract management arrangements in place. Report 11.3, 11.4
  • Legal: Because costs to individual leaseholders will not exceed £100 in any service charge year, no formal consultation is required under the Landlord and Tenant Act 1985 for this Qualifying Long-Term Agreement. Report 7.1, 7.2, 7.3

Who and where

  • Residents, staff, visitors and contractors using Council managed properties Report 6.1, 4.1
  • The preferred contractor (Tenderer A, named in the exempt appendix) Report 3.1, P54
  • Council leaseholders, who may contribute a small proportion of costs via service charges Report 7.1, 7.3
  • Assistant Director of Repairs & Compliance and Head of Finance, who will oversee delegated additional expenditure Report 3.2, P44

Timeline

  • Up to four years from commencement of the contract: Duration of the awarded asbestos services contract to Tenderer A Report 3.1
  • End of December 2025: Target for seamless changeover between old and new asbestos contracts Report 4.2
  • 5 January 2026: Date of the Cabinet Member Signing decision

Plain English for the jargon

  • UKAS: United Kingdom Accreditation Service, the national accreditation body for conformity assessment.
  • DPS: Dynamic Purchasing System, an electronic purchasing system used to procure works, goods or services, here the London Construction Programme's Asbestos category.
  • CSO: Contract Standing Order, the Council's internal rules governing how contracts are procured and awarded.
  • HRA Major Works Capital Programme: The Housing Revenue Account capital funding for major works to Council housing stock.
  • Social Value: The wider non-financial benefits a contractor commits to deliver, such as local jobs, training and support for local businesses.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1That the Cabinet Member for Housing & Planning and Deputy Leader, Pursuant to Council’s Contract Standing order (CSO) 8.01 (use of Council Dynamic Purchasing system), CSO 2.01(C) (Cabinet approve awards of Contract valued at £500,000 or more), approves the award of a contract to Tenderer A (identified in the Exempt portion of the report – Appendix [insert]) for Asbestos Services including asbestos surveying, bulk sampling and air monitoring for the sum of £1,815,540.00, plus additional costs in relation to project specific services in relation to surveying, sampling and air monitoring services, for a duration of up to four years from the commencement of the contract.

3.2That the Cabinet Member for Housing & Planning and Deputy Leader is also asked to approve the delegation of expenditure of the additional sums in relation to project specific work under the contract, identified through

Page 1 of 7 surveys, to the Assistant Director of Repairs & Compliance in consultation with the Head of Finance as set out in the exempt part of the report.

3.3Pursuant to Council’s CSO 16.04, the report also requests Cabinet Member’s approval for the issue of a letter of intent to the preferred contractor. This will be for an amount up to, but not exceeding, £181,554.00. This represents 10% of the surveying contract sum. This will enable mobilisation of the contract to be completed, whilst the contract particulars are finalised.

Reasons for decision

4.1Haringey Council has an obligation to comply with the Health and Safety at Work Act 1974, and all regulations that sit beneath it, such as The Control of Asbestos Regulation 2012. Due to these obligations, it is not possible accommodate a break in the service provision for asbestos surveying and associated services. This is to ensure residents and other building users or visitors remain safe in relation to the existence and risks regarding asbestos.

4.2It is therefore crucial this contract is awarded to facilitate a seamless changeover between the old and new contracts by the end of December 2025.

Alternative options considered

5.1Do-nothing – This is not an option as it would mean the Council is not able to deliver statutory services in accordance with current Health and Safety legislation.

5.2Carry out the work through in-house resources - We are unable to deliver these works in-house due to a lack on suitably trained and certified operatives. We do not have enough operatives, and the timescales required to recruit and train them would result in the same outcome as set out in 5.1 above. Haringey council do not carry out asbestos works in-house due to the insurance premiums included with carrying out such works. Given the resourcing, necessary accreditations, training, consumables and general overheads involved in such a division, we do not see this as a viable option.

5.3Use our existing contracts or contractors - Current contracts have expired or reached extension limits. A new contract ensures compliance and up-to-date pricing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
To award a new asbestos contract and appoint a UKAS accredited asbestos contractor.Minutes 439 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. To award a new asbestos contract and appoint a UKAS accredited asbestos contractor.This decision
  2. Approval for Haringey to directly award a new contract for the Integrated Community Equipment Service to a new providerApproved
  3. Approval for Haringey to enter into a Partnership agreement and for Haringey Council to directly award a new contract for the Integrated Community Equipment Service to a new provider.Decided
  4. Award of contract for the delivery of a maintence, repairs and defect service to domestic and commercial units relative to new builds and haringey community benefit society (hcbs)Approved
  5. Award of Consultancy Contracts for Broadwater Farm New Homes Design TeamApproved
  6. Award microsoft unified support 3 year renewalDecided

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies