London Borough of Haringey
Cabinet Member Signing, Monday 9 February 2026 at 3.00pm

Approval to Procure Contractor for Henrietta House and Carlton Lodge

Approved Executive 1 paper

AI summaryHaringey's Cabinet Member for Housing and Planning approved starting procurement for £1.2m of urgent external structural repairs at Carlton Lodge and Henrietta House, with tenders in February/March 2026 and works starting after April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedessential external structural repairs at both blocks
Money£1.2m pre-tender estimatefunded from existing capital budget
What happens nextTenders February/March 2026works start on-site after April 2026
Who it affectsResidents of two housing blocksCarlton Lodge and Henrietta House

What was decided

Approval was granted to commence procurement of essential external structural repairs at Carlton Lodge and Henrietta House, with a pre-tender estimate of £1.2m. Report 3.1

The choice of procurement route was delegated to the Chief Procurement Officer under Contract Standing Order 12. Report 3.2

Tenders will be invited through an appropriate Lot on the London Construction Programme (LCP) Framework. Report 4.2, 6.4

Why

In July and October 2024 both blocks suffered significant structural deterioration to concrete windowsills and the reinforced concrete beams supporting balconies, communal walkways and landings. Report 4.1

The defects have caused spalling concrete, exposed reinforcement bars, progressive corrosion, and a risk of collapse or falling debris. Report 4.1

Because the pre-tender estimate exceeds £500,000, Cabinet Member approval is required before tendering. Report 4.2, P35

What happens next

Procurement will run in February/March 2026 using a single-stage JCT Intermediate Building Contract 2024 with contractor design. Report 8.1, 8.2

Bids will be scored 60 per cent on price and 40 per cent on quality, with Ridge and Partners supporting the evaluation. Report 8.3, 8.4, 8.5

Subject to a successful tender, the scheme will return to Cabinet for approval to award. Report 8.6

The money

  • £1.2m pre-tender estimate for the essential external structural repairs Report 3.1
  • £1.2m annualised cost in 2026/27 reflected in the service's MTFS forecasts
  • £500,000 threshold above which Cabinet or Cabinet Member approval to invite tenders is required Report P35, 4.2

Options considered

  • Rejected: Take no action. Would pose an unacceptable risk to health and safety of residents and visitors, and would accelerate deterioration, leading to significantly higher future repair costs. Report 5.1

Implications

  • Risk: Urgent works are needed to stabilise the structures and prevent further collapse or falling debris, protecting residents, visitors and the public. Report 4.1, 5.1, 6.1
  • Financial: The contract is capital funded from the Asset Management Capital Works Programme; no additional funding outside the approved capital budget envelope is required.
  • Legal: The Director of Legal and Governance confirmed there are no legal reasons preventing approval, and the route complies with Contract Standing Orders 2.01(b), 0.08, 7.02 and 12. Report P38
  • Equalities: The works are expected to have a positive impact on leaseholders and tenants, advancing the council's Public Sector Equality Duty, and the appointed contractor will also be required to have due regard to that duty.
  • Climate: Sustainable materials, recycled waste and sustainable working practices will be required of the contractor and form part of the tender selection. Report 9.2, 10.1, 10.2
  • Other: The procurement will seek social value through jobs and training opportunities during construction. Report 9.3

Who and where

  • Residents and leaseholders at Carlton Lodge and Henrietta House Report 4.1, 7.1, 7.2
  • Visitors and members of the public near the two blocks Report 5.1, 6.1

Timeline

  • July 2024: Scaffolding and safety netting erected at Carlton Lodge after reports of falling concrete. Report 4.1, 6.1
  • October 2024: Scaffolding and safety netting erected at Henrietta House; Ridge and Partners appointed to investigate and prepare a tender package. Report 4.1, 6.1, 6.2
  • June 2025: First letter issued to all residents providing an update on the council's proposals. Report 7.3
  • October 2025: Further letter issued to all residents outlining the proposal to appoint a specialist contractor. Report 7.3, 7.4
  • February/March 2026: Procurement timetable for competitively tendering the works. Report 8.1
  • After April 2026: Works expected to start on site. Report 8.1
  • 2026/27: Annualised cost of approximately £1.2m reflected in the service's MTFS forecasts.

Plain English for the jargon

  • LCP Framework: London Construction Programme Framework, an approved framework used to invite tenders for construction works.
  • Spalling: Flaking or breaking away of the surface of concrete, often caused by corrosion of embedded steel reinforcement.
  • Concrete carbonation: Chemical reaction between concrete and carbon dioxide that reduces its protective alkalinity, leading to corrosion of embedded steel.
  • JCT Intermediate Building Contract 2024: A standard form of building contract used for intermediate-scale construction projects, here used with contractor-designed elements.
  • Contract Standing Orders (CSOs): The council's internal rules governing how contracts must be procured and awarded.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None RESOLVED It was recommended that: 3.1. In accordance with Contract Standing Order 2.01. b) and 0.08, the Cabinet Member for Housing and Planning (Deputy Leader) granted approval to commence the procurement of essential external structural repairs at Carlton Lodge and Henrietta House. The pre-tender estimate for these works is set at £1.2m. 3.2. Delegate the appropriate procurement route to the Chief Procurement Officer in compliance with Contract Standing Order 12. Reasons for decisions In July and October 2024 - Carlton Lodge and Henrietta House experienced significant structural deterioration affecting the concrete windowsills and the reinforced concrete beams supporting the Item 6 balconies and communal walkway and landing areas. The defects have resulted in spalling concrete, which has exposed the reinforcement bars and led to progressive corrosion. Urgent remedial works are required to both blocks to stabilise these elements to prevent further degradation and mitigate the risk of collapse and/or falling debris. As the pre-tender estimate for the remedial works were above £500k, approval wa required from the Cabinet Member for Housing and Planning (Deputy Leader) to invite tenders via the LCP (London Construction Programme) Framework. 5. Alternative options considered The option of taking no action had been reviewed and formally discounted. Given the urgent nature of the structural defects and the risk of falling masonry, inaction would pose an unacceptable risk to the health and safety of residents and visitors. Furthermore, failure to address the issues promptly would accelerate the deterioration of critical concrete components within the blocks, leading to more extensive damage and significantly higher repair costs in the future.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that:

3.1In accordance with Contract Standing Order 2.01. b) and 0.08, the Cabinet Member for Housing and Planning (Deputy Leader) grants approval to commence the procurement of essential external structural repairs at Carlton Lodge and Henrietta House. The pre-tender estimate for these works is set at £1.2m.

3.2Delegate the appropriate procurement route to the Chief Procurement Officer in compliance with Contract Standing Order 12.

4. Reasons for decisions

4.1In July and October 2024 - Carlton Lodge and Henrietta House experienced significant structural deterioration affecting the concrete windowsills and the reinforced concrete beams supporting the balconies and communal walkway and landing areas. The defects have resulted in spalling concrete, which has exposed the reinforcement bars and led to progressive corrosion. Urgent remedial works are required to both blocks to stabilise these elements to prevent further degradation and mitigate the risk of collapse and/or falling debris.

4.2As the pre-tender estimate for the remedial works are above £500k, approval is required from the Cabinet Member for Housing and Planning (Deputy Leader) to invite tenders via the LCP (London Construction Programme) Framework.

Alternative options considered

5.1The option of taking no action has been reviewed and formally discounted. Given the urgent nature of the structural defects and the risk of falling masonry, inaction would pose an unacceptable risk to the health and safety of residents and visitors. Furthermore, failure to address the issues promptly would accelerate the deterioration of critical concrete components within the blocks, leading to more extensive damage and significantly higher repair costs in the future.

6. Background information

6.1Carlton Lodge and Henrietta House sites Following reports of falling concrete at Carlton Lodge and Henrietta House, Haringey’s Repairs Service (HRS) erected scaffolding and safety netting in July and October 2024 respectively. These works were introduced as protective measures to safeguard residents, visitors, and the public from potential hazards while permanent structural repairs are planned and undertaken.

6.2Ridge and Partners were appointed in October 2024 to carry out an investigation into the reasons why the masonry was deteriorating and to produce a comprehensive specification and tender package for the procurement of a contractor to undertake the necessary urgent remedial works.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Procure Contractor for Henrietta House and Carlton LodgeMinutes 250 KB DownloadRead as text

At this meeting

Whole meeting
6Approval to Procure Contractor for Henrietta House and Carlton LodgeThis decision
7Award of Housing Asset Management Partnering ContractsApproved 8Exclusion of the Press and PublicOn the agenda

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Approval to Procure Contractor for Henrietta House and Carlton LodgeThis decision
  2. Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDecided
  3. Approval to procure Enhanced Environmental Enforcement ContractDecided
  4. Selby Urban Village - approval to procure Artificial Grass Pitch works contractorDecided
  5. Pre-tender approval to commence procurement for Housing-Related Support – Single Adults Complex Needs Supported HousingDecided
  6. Approval of the Procurement of Integrated Drug and Alcohol Treatment and Recovery Services for HaringeyApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies