Cabinet Member Signing, Monday 9 March 2026 at 4.00pm

Hornsey Library

Decided Executive 1 paper

AI summaryHaringey Cabinet Member for Culture and Leisure to approve procurement of a contractor for RAAC roof remediation at Hornsey Library, ahead of the London Borough of Culture 2027 deadline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFor RAAC roof remediation contractor at Hornsey Library
MoneyNot stated in open reportCosts held in exempt Appendix 1, Part B
What happens nextTender exercise to beginUsing LCP Education Framework or DPS
Who it affectsHornsey Library users and staffMain library space faces temporary 14 week closure

What was decided

The Cabinet Member for Culture and Leisure is recommended to approve the commencement of a procurement exercise for a construction works contractor to deliver roof remediation works at Hornsey Library. Report 3.1, 3.2

Why

Structural surveys confirmed Reinforced Autoclaved Aerated Concrete in the ceiling and roof of the double-height atrium on the western side, which is the main library space, with significant safety concerns. Report 4.1, 4.2, 6.3, 6.4

What happens next

A single-stage JCT traditional tender will be run via the London Construction Programme Education Framework or DPS, with a further report to be brought back to award the contract. Report 4.3, 6.16

Options considered

  • Rejected: Do nothing. Council would be responsible for an unsound roof and ongoing scaffold hire costs Report 5.1
  • Rejected: Deliver in-house. No in-house capacity, specialist expertise or qualifications available Report 5.2
  • Rejected: Open tenders via Contracts Finder. Would prolong the tender period and delay delivery Report 5.3
  • Rejected: Use an alternative public sector DPS. Would not comply with Contract Standing Order 8.02 Report 5.4
  • Chosen: Use LCP Education Framework or DPS. Compliant with standing orders, positive soft market testing feedback Report 4.3
  • Chosen: Brace the RAAC with a Metsec system (Option 1). Cheaper than replacement, no visible change to roof, foundations can bear the load, avoids decommissioning solar panels Report 6.9, 6.10, 6.11, 8.2
  • Rejected: Remove and replace RAAC with timber joists (Option 2). More expensive than Option 1; risk of reverting to it now removed Report 6.10, P21
  • Rejected: Remove and replace RAAC with timber panel system (Option 3). More expensive than Option 1; risk of reverting to it now removed Report 6.10, P21

Implications

  • Financial: Total projected costs are not published, being held in the exempt Part B appendix. Report 6.17
  • Legal: Procurement must comply with the Procurement Act 2023 and the Council's Contract Standing Orders; no legal obstacles identified.
  • Equalities: The Public Sector Equality Duty applies; the aim is to make the library interior safe for all users, and the contractor will also be bound by the duty.
  • Climate: Existing solar PV panels installed in 2018 will be preserved and continue to generate electricity; Option 1 upgrades the structure rather than replacing it, avoiding unnecessary waste. Report 8.2, 8.3
  • Risk: A scaffold crash deck is in place to protect the public and staff while the area beneath the RAAC panels remains out of use. Report 4.2, 6.5

Who and where

  • Users of the main library space in the western double-height atrium Report 4.2, 6.3
  • Library staff and visitors in the Adults section Report 4.2, 6.5
  • Friends of Hornsey Library, engaged on site compound arrangements Report 6.13
  • Haringey residents, through the Resident Experience strand of the Corporate Delivery Plan Report 7.2, P33, P34, P35, P36

Timeline

  • September 2023: Original structural report by Bryan Packman Marcel found no visual defects but recommended further intrusive surveys Report 6.4
  • 28th October 2024: Multi-Disciplinary Design Team appointments approved under delegated decisions
  • 23rd April 2025: Option 1 (Metsec bracing of RAAC) approved at RIBA Stage 1 Gateway Report 6.9
  • 2026-03-09: Cabinet Member for Culture and Leisure decision to approve commencement of procurement Report 3.1, 3.2
  • 14 weeks: Anticipated temporary closure of the library under the main roof during the works
  • April 2027: Completion deadline, linked to Hornsey Library's role in London Borough of Culture 2027 Report 6.14

Plain English for the jargon

  • RAAC: Reinforced Autoclaved Aerated Concrete, a lightweight building material with known structural risks
  • DPS: Dynamic Purchasing System, a list of approved suppliers used for public sector procurement
  • CSO: Contract Standing Orders, the Council's rules for procuring and contracting
  • LCP: London Construction Programme, a public sector construction framework
  • MDDT: Multi-Disciplinary Design Team appointed to develop the project
  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
  • PSED: Public Sector Equality Duty under the Equality Act 2010
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: None That the Cabinet Member for Culture and Leisure
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1For the Cabinet Member for Culture and Leisure, pursuant to Contract Standing Orders 0.08 and 2.01(b) to:

3.2Approve the commencement of a procurement exercise for a construction works contractor to deliver remediation works to the roof at Hornsey Library.

Reasons for decision

4.1Structural surveys have confirmed the presence of Reinforced Autoclaved Aerated Concrete (RAAC) within the ceiling/roof areas of double-height atrium located in the western side of Hornsey Library.

4.2This area comprises the main library space for the building. After completing these further surveys, it was recommended that the area below the RAAC panels should be taken out of use immediately, due to significant safety concerns. To enable continued use a scaffold crash deck has been installed to protect members of the public and staff.

4.3It is proposed to procure a contractor to undertake remediation works as outlined in 6.9 of this report on a single-stage, JCT traditional form of contract using the London Construction Programme Education Framework or DPS. Soft market engagement has been undertaken to ascertain interest and availability within the market, with positive feedback of the proposed approach. 5. Alternative options considered

5.1Do nothing - The Council could decide to not tender the scheme. This option has been discounted as it is not in the Council’s interest to be responsible for a structurally unsound roof. Neither is it financially responsible for the Council to carry the ongoing weekly hire cost of the scaffold which forms the crash deck.

5.2In-house – There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.3Invite open tenders via Contracts Finder. This would result in a protracted tender period and would delay delivery of the project.

5.4Use an alternative public sector DPS. This would not be compliant with CSO 8.02, given the LCP Framework or DPS has been deemed suitable for the requirements being sought.

6. Background information

6.1Hornsey Library is one of the busiest libraries in the borough.

6.2The premises comprise a three-storey Public Library building with flat roof areas over. The library was refurbished in 2018, during which new Bauder felt roof coverings were installed, together with solar photo voltaic (PV) panels. PVs making a significant difference to the building’s sustainability.

6.3Structural surveys by Bryan Packman Marcel (BPM) confirmed the presence of Reinforced Autoclaved Aerated Concrete (RAAC) within the ceiling/roof areas of double-height atrium located in the western side of the building. This area comprises the main library space for the building.

6.4The original report completed in September 2023 identified no visual defects but recommended further intrusive surveys. After completing these further surveys, BPM advised that the area below the RAAC panels should be taken out of use immediately, due to significant safety concerns. They further recommended that remedial works should be considered for this area before it could be brought back into use.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hornsey LibraryMinutes 309 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
EA
Councillor Emily ArkellCommittee Member, present

On this subject at Haringey

Search all
  1. Hornsey LibraryThis decision
  2. Variation of Contract Award and associated Purchase Order on Hornsey Library Refurbishment ProjectApproved
  3. Award of Contract for Hornsey LibraryApproved
  4. Hornsey Library refurbishment and Essential MaintenanceDecided

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open