Haringey Council Audio Visual Supply, Installation, Configuration & Support Contract

Decided Executive 1 paper

AI summaryHaringey Cabinet Member for Finance and Corporate Services approves a four year audio visual contract for the new Civic Centre, worth £1,571,384.61, to be awarded to Supplier B from 13 April 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to a backup award to Supplier E
Money£1,571,384.61Plus letter of intent of £157,138.46
What happens nextContract starts 13 April 2026Ends 12 April 2030
Who it affectsCivic Centre and other council buildingsCouncil staff, members and event users

What was decided

To award a four year audio visual supply, installation, configuration and support contract to Supplier B for an estimated value of £1,571,384.61, covering the Civic Centre and other Council buildings from 13 April 2026 to 12 April 2030. Report 3.1

To approve a letter of intent for up to 10% of the tendered contract value, totalling £157,138.46, so the preferred contractor can begin mobilisation ahead of the formal contract. Report 3.2

If the Council cannot award to Supplier B, to award the contract instead to Supplier E, the next highest scored bidder. Report 3.3, P50

Why

The Civic Centre Programme is building the Council's new offices and needs reliable audio visual equipment to support new ways of working, including activity based working, with the chamber and event spaces also requiring specialist equipment. Report 4.1, 4.2, 4.3, 6.4

The recommended supplier submitted a strong tender that aligned with discovery phase cost estimates and showed a strong understanding of the Council's requirements, scoring highest overall in the price and quality evaluation. Report 4.9, 4.10, 7.2, P50

A procurement through the NEUPC Audio Visual framework offered a compliant route to market and a robust mini competition, with six compliant tenders received and evaluated on 60% price, 30% quality and 10% social value. Report P42, P44, P46, P47

What happens next

The contract will be funded from the existing Civic Centre AV Hardware Install and Commissioning project budget, Scheme 330, in the Medium Term Financial Strategy capital programme. Report 7.5, P55, 10.1

Digital Services and Facilities Management will work with Supplier B on a support model beyond April 2028, with any new requirement to be included in the Digital Services 2027/2028 Service Plan. Report 7.5, P56

The contract will be awarded under Contract Standing Orders 2.01(c), 0.08, 7.02 and 16.04, with the Director of Legal and Governance confirming no legal reasons preventing approval. Report 10.2, 10.3, P71, P78

The money

  • £1,571,384.61 Estimated contract value to Supplier B for audio visual supply, installation, configuration and support, excluding contingency Report 3.1, P50
  • £157,138.46 Letter of intent at up to 10% of the tendered contract value, as set out in the decision Report 3.2
  • £500,000 Contract Standing Order threshold above which Cabinet or Cabinet Member approval is required for contract awards Report 3.1, P75
  • £3.15m Provisional total budget set for all IT and AV elements of the Civic Centre programme Report 6.9
  • £1.56m Concept level peer and market estimate for the audio visual elements within that total IT/AV budget Report 6.9
  • £50k per year Revenue stream cited in the original business case, expected to be supported by event, welcome, courtyard and chamber hire in the Civic Centre Report 4.4
  • £1,511,940.75 Tendered price for Bidder A, with overall score 82.86 Report P50
  • £1,603,934.99 Tendered price for Bidder C, with overall score 86.91 Report P50

Options considered

  • Chosen: Award contract to Supplier B, the highest scoring bidder at £1,571,384.61. Strongest combined price and quality score of 89.23, tender aligned to discovery phase estimates, and clear understanding of Council requirements Report 4.9, 4.10, 7.2, P50
  • Chosen as fallback: If Supplier B cannot be awarded, award the contract to Supplier E at £1,596,826.75. Supplier E submitted the next highest scored bid of 87.47 Report 3.3, P50
  • Rejected: Do nothing and not award a contract for new audio visual equipment. Would leave staff and visitors without the digital tools to work collaboratively or enable the Council chamber, event and community spaces, and create significant operational difficulties for new ways of working Report 5.1, P19
  • Rejected: Lift and shift all existing audio visual equipment into the new buildings. Existing equipment is near refresh point and not an exact fit, the fitout would take around three months, the chamber and event spaces have no current viable provision, and the option would risk the occupation timeline Report 5.1, P21, P22

Implications

  • Financial: The contract will be funded from the existing Civic Centre AV Hardware Install and Commissioning project budget, Scheme 330, in the MTFS capital programme, and the Director of Finance confirms the recommendation can be funded from the approved budget. Report 7.5, P55, 10.1, P65
  • Legal: Award is permitted under Contract Standing Orders 2.01(c), 0.08, 7.02 and 16.04, using a call-off from the NEUPC framework procured under PCR 2015, and the Director of Legal and Governance raises no legal reasons preventing approval. Report 10.2, 10.3, P42, P68, P71, P78
  • Equalities: The Council has had due regard to its Public Sector Equality Duty; displays will be visible from all seated positions, controls will be at seated height, hearing loops will be installed where required, and the Disability and Illness Network will be involved in user experience trials. Report P79, P80, P83, P84
  • Climate: The Council will seek to reuse existing audio visual equipment where suitable, redistribute other equipment to smaller sites on a case by case basis, and align the procurement with its BREEAM Outstanding target for the Civic Centre. Report 4.6, 4.7, 6.8, P60, P61, P62
  • Risk: Existing equipment will be nearing recommended refresh thresholds at the point of Civic Centre occupancy in 2027, so a supply and support contract is needed to avoid spaces being out of action for long periods. Report 4.5, 6.8
  • Staffing: The internal audio visual support team will continue to deliver day to day support, with the new contract providing additional specialist technical support and continuous improvement. Report 4.8
  • Other: The decision is being taken by the Cabinet Member for Finance and Corporate Services with the agreement of the Leader, under CSO 0.08, instead of by full Cabinet. Report P1, P76

Who and where

  • Council staff who will use the Civic Centre, including those based elsewhere who will have access to the building Report 4.1, 6.4
  • Members and participants in Council and statutory meetings, including those using the chamber beyond its statutory obligations Report 4.3, 6.4
  • Community groups and event hirers who will use the Civic Centre's event, welcome, courtyard and chamber spaces Report 4.3, 4.4, 6.4
  • Visitors to the Civic Centre, including those requiring accessible audio visual provision Report P83, P84
  • The internal audio visual support team, whose day to day role is retained and supplemented by the new contract Report 4.8
  • Residents of the borough, as the Civic Centre is described as the civic heart of the borough and supports wider community, cultural and public art activity Report 6.2, P26, P27

Timeline

  • 23 April 2023: Cabinet approved the redevelopment of the Civic Centre in Wood Green as the Council's new headquarters Report 6.1
  • 12 November 2024: Cabinet approved the appointment of John Sisk Ltd as the main contractor for the new Civic Centre Report 6.1
  • 31st October 2025: Tender opened to all framework suppliers in the relevant lots on the Haringey Procurement and Contract System Portal Report P44
  • 23 January 2026: Moderation meeting led by Strategic Procurement to discuss and finalise quality scores Report P47
  • 5th February: Price evaluation panel returned final scores for the bidders Report 7.2
  • 19 March 2026: Cabinet Member for Finance and Corporate Services took the decision to award the contract Report 3.1, 3.2, 3.3
  • 13th of April 2026: Contract is due to commence Report 3.1
  • 2027: Existing equipment will be nearing recommended refresh thresholds at the point of Civic Centre occupancy Report 4.5, 6.8
  • beyond April 2028: Support model arrangements to be reviewed and may be included in the Digital Services 2027/2028 Service Plan Report 7.5, P56
  • 12 April 2030: Contract is due to end Report 3.1

Plain English for the jargon

  • NEUPC: North Eastern Universities Purchasing Consortium, whose Audio Visual Supplies, System Design Integration and Maintenance Framework (AVI2007 NE) was used for this procurement
  • FF and E: Furniture, Fixtures and Equipment, the wider category of items being procured for the Civic Centre, of which audio visual is one element
  • CSO: Contract Standing Order, the Council's internal rules for procurement, with specific rules cited including 0.08, 2.01(c), 7.02 and 16.04
  • BREEAM: Building Research Establishment Environmental Assessment Method, the sustainability rating the Council is targeting as Outstanding for the Civic Centre
  • MTFS: Medium Term Financial Strategy, the Council's capital and revenue planning document, from which Scheme 330 funds this contract
  • Category A, B and C+ fit-out: Stages of office fit-out, where John Sisk Ltd is delivering shell and core and Category A, and the Council will deliver Category B and C+ client fit-out
  • PCR 2015: Public Contracts Regulations 2015, the procurement legislation under which the NEUPC framework was established
  • RIBA Stage 3+: A stage of design development under the Royal Institute of British Architects' plan of work, used as the basis for the Civic Centre design
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

The Cabinet Member for Finance and Corporate Services

3.1Pursuant to Contract Standing Order (CSO) 2.01( c) and CSO 0.08 (approve award of contract valued at £500,000 (five hundred thousand pounds) or more) to approve the award of a contract to Supplier B in paragraph 7.2.1 of the report and named in paragraph 2.1 of the Exempt portion of the report (Part B) for an estimated contract value of £1,571,384.61 (one million, five hundred and seventy one thousand, three hundred and eighty four pounds, sixty one pence) (excluding contingency as set out in the Part B report).for Audio-Visual equipment supply, installation and support in the Civic Centre and other Council buildings subject to the further details set out in section 3.1 of Appendix 1 - Part B (exempt information) of this report). The contract is for a period of 4 years commencing 13th of April 2026 to 12th April 2030.

3.2To approve, the issuance of a letter of intent for up to 10% of the tendered contract value, totalling £157,138.46 (one hundred and fifty-seven thousand, one hundred and thirty eighty pounds, forty sixty pence).

3.3In the event of the Council being unable to award the contract to supplier B to agree the award of the contract to supplier E (named in paragraph 6.2.1 of the Exempt portion of the report (Part B)) who submitted the next highest scored bid.

Reasons for decision

4.1The Civic Centre Programme is building the Councils’ new offices, AV needs to enable, support and be dependable to support the new ways of working. The reliability of the AV offering has repeatedly topped staff surveys as a key element to carry out day to day tasks effectively. Having a supply and support contract in place will ensure reliability for staff.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Haringey Council Audio Visual Supply, Installation, Configuration & Support ContractMinutes 569 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
DC
Councillor Dana CarlinCommittee Member, present

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies