London Borough of Haringey
Cabinet Member Signing, Thursday 19 March 2026 at 3.30pm

Enterprise Resource Planning (ERP) Programme - Phase 1

Decided Executive 1 paper

AI summaryHaringey Cabinet Member approves £1,922,653.19 to start discovery phase of council-wide ERP replacement, split across 2025/26 and 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedDiscovery and initiation phase funding for ERP replacement
Money£1,922,653.19Across 2025/26 and 2026/27, from contingency and capital receipts
What happens nextDiscovery and initiation phase workGovernance, requirements, market testing, procurement strategy
Who it affectsHR, Finance and Procurement functionsPlus council-wide services supported by the ERP system

What was decided

The Cabinet Member for Finance and Corporate Services approved an initial budget of £1,922,653.19 to fund the discovery and initiation phase of the ERP replacement programme. Report 3.1

No declarations of interest were made for this item.

Members noted the programme is moving from a foundational phase into a structured discovery and initiation stage, and that an independent assessment confirmed the strategic direction remains sound. Report 3.2, 3.3, 3.4

Why

The current ERP platform is reaching the end of support and is no longer a reliable basis for the council's operational, security and statutory needs over the medium to long term, so doing nothing is not viable. Report P26

The existing 2025/26 budget of £150k was wholly insufficient to cover what has been done to date or the next, more detailed discovery phase needed to produce a robust, fully costed business case. Report 4.1, 4.3

Without the additional investment, the council risks slow decision-making, weak or over-specified requirements, supplier-led design, late data and change planning, and procurement without an evidence base. Report 4.7

What happens next

Phase 1 activities will formalise governance, complete and prioritise requirements, prepare for market testing, develop the procurement strategy, start data discovery, and refresh costed options and the 10-year total cost of ownership. Report P10, P11, P12, P13, P14, P15, P19

Phase 2 delivery funding will be subject to a future Cabinet decision after Phase 1, based on a refreshed business case with evidenced scope, costs, benefits, risks and delivery confidence. Report 4.5, P19

A fully costed ERP business case is to be produced by summer 2026 to support full programme approval. Report 9.3

The money

  • £1,922,653.19 Total initial budget approved for ERP Phase 1 discovery and initiation Report 3.1, P25
  • £679,374.10 Sub-total for 2025/26 after deducting existing £150,000 budget Report P25
  • £1,243,279.10 Sub-total for 2026/27 Report P25
  • £150,000 Existing approved 2025/26 ERP programme budget (FCR) Report 4.1, P25
  • £425,393.85 2025/26 existing project resource Report P25
  • £212,696.93 2026/27 existing project resource Report P25
  • £32,845.00 HR SME resource (2025/26) Report P25
  • £237,570.00 External consultancy (2026/27) Report P25
  • £660,000.00 Additional project resource (2026/27) Report P25
  • £180,000.00 Required data migration resources (2026/27) Report P25
  • £58,167.60 SME recharges 2025/26 Report P25
  • £77,556.80 SME recharges 2026/27 Report P25
  • £75,397.65 Contingency at 10% for 2025/26 Report P25
  • £113,025.37 Contingency at 10% for 2026/27 Report P25
  • £150,000 Existing 25/26 budget deducted Report P25
  • £4m Proposed 2026/27 use of capital receipts for invest to save, including ERP Report 9.2
  • £829,374 Forecast spend at Period 10 2025/26 Report 9.3
  • c£1.92m Total stabilisation and option-assessment funding cited by Finance Report 9.2
  • £0.68m Finance-cited 2025/26 requirement Report 9.2
  • £1.24m Finance-cited 2026/27 requirement Report 9.2

Options considered

  • Chosen: Approve the £1,922,653.19 Phase 1 budget for ERP discovery and initiation. Needed to evidence best value for a very substantial future investment, manage risks, and produce a fully costed business case for Cabinet. Report 3.1, 4.3, 4.8
  • Rejected: Do nothing. Current ERP is reaching end of support, raising operational, security and statutory risk; delay would increase risk and reduce ability to maintain business continuity. Report P26

Implications

  • Financial: Phase 1 funding will be met from corporate contingency in 2025/26 and capital receipts flexibility in 2026/27, with a £4m capital receipts use for invest to save (including ERP) considered by Council on 10 March 2026. Report 9.2
  • Risk: Identified risks include business continuity on ageing systems, programme delivery complexity, financial control without staged funding, premature procurement exposure, change and adoption risk, and data quality and migration risk. Report P43, P44, P45, P46, P47, P48
  • Legal: Director of Legal and Governance (Monitoring Officer) was consulted and confirmed no contractual and procurement issues require legal comments. Report P79, P80
  • Equalities: Report sets out how a modern ERP could support the Public Sector Equality Duty through better data, fairer HR processes, accessibility features and resource allocation; Haringey also treats socio-economic status as a locally protected characteristic. Report 9.10, 9.11, 9.13, 9.15, 9.17
  • Climate: A modern, often cloud-based ERP is expected to lower energy use, reduce hardware and electronic waste, and improve reporting on environmental performance, though no quantified local carbon saving is given. Report 8.2, 8.5, 8.10
  • Staffing: Phase 1 will supplement in-house capability with ERP-experienced SMEs, appoint a Data Lead, and stand up a small Programme Management Office to manage plan, RAID log and escalation. Report P10, P15, P16

Who and where

  • HR, Finance and Procurement functions across Haringey Council Report 4.1, 6.8
  • Council services reliant on the ERP for payments, HR processes, procurement and contract management Report 7.1
  • Members of the Senior Leadership Team and Corporate Leadership Team through structured engagement Report 6.10
  • Strategic Procurement team, currently constrained by manual processes and lack of supporting technology Report 9.5

Timeline

  • 2025/26: Existing £150k budget for foundational ERP work; £679,374.10 of new Phase 1 spend required Report 4.1, P25
  • 2026/27: Further £1,243,279.10 of Phase 1 spend required Report P25
  • 10 March 2026: Council considered 2026/27 Budget/MTFS including £4m capital receipts use for invest to save Report 9.2
  • 19 March 2026: Cabinet Member for Finance and Corporate Services approves Phase 1 ERP budget
  • Summer 2026: Target for completion of a fully costed ERP business case to support full programme approval Report 9.3
  • 18 to 24 months from system selection (indicative): Indicative sector benchmark for full ERP implementation; precise timing subject to replanning Report 6.1
  • Future Cabinet decision: Phase 2 delivery funding to be sought after Phase 1, based on refreshed business case Report 4.5, P19

Plain English for the jargon

  • ERP: Enterprise Resource Planning, the integrated software system used for finance, HR and procurement functions
  • PMO: Programme Management Office, a small team that owns the plan, RAID log, dependencies and escalation
  • RAID: Risks, Assumptions, Issues and Dependencies, a standard programme control log
  • SME: Subject Matter Expert, used here for external specialists with ERP experience
  • MTFS: Medium Term Financial Strategy, the council's multi-year budget planning framework
  • CSO: Contract Standing Orders, the council's rules governing procurement and contracts
  • FCR: Existing 2025/26 budget reference cited in the financial table
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

The Cabinet Member for Finance and Corporate Services is asked to:

3.1To approve an initial budget to fund a defined discovery and initiation phase of £1,922,653.19.

3.2Note that Haringey Council’s ERP replacement programme is now moving from an initial foundational phase into a discovery and initiation stage.

3.3Note that the next phase is essential to ensure the programme is positioned to proceed in a controlled, evidence-based and deliverable manner, with clear governance, mature requirements, and a robust understanding of cost, risk and delivery approach.

3.4Note an independent assessment has confirmed that the strategic direction to replace the Council’s current ERP remains sound and necessary. The next step is to build on this foundation through a structured discovery and initiation phase that will strengthen decision-making, validate options, refine scope, test our approach with the market and ensure the programme is ready to proceed at pace in a way that is affordable, compliant and defensible.

Reasons for decision

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enterprise Resource Planning (ERP) Programme: Phase 1Minutes 203 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
DC
Councillor Dana CarlinCommittee Member, present

On this subject at Haringey

Search all
  1. Enterprise Resource Planning (ERP) Programme - Phase 1This decision
  2. Enterprise Resource Planning Programme - Phase 2Decided

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies