Cabinet Member Signing, Tuesday 7 April 2026 at 11.30am

Contract uplift in respect of contract for the provision of refurbishment works at Void Properties in the area of Haringey.

Decided Executive 1 paper

AI summaryHaringey Cabinet Member approves a contract uplift to refurbish more void properties for use as homeless accommodation in the borough.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedVariation to void works contract
MoneyNot stated in open reportAmount set out in exempt appendix
What happens nextVary the existing contractTo deliver additional HCBS void works
Who it affectsHCBS acquired homes and homeless households370 homes acquired since 2019

What was decided

The Cabinet Member for Housing and Planning, with the agreement of the Leader, approved a variation to the existing void works contract under Contract Standing Order 0.08, on the basis that the variation is £500,000 or more but below the public procurement threshold.

Strategic Procurement supported the variation under Contract Standing Orders 18.03.1, 18.03.3 and 2.01(d), and the Director of Legal and Governance saw no legal reasons preventing approval.

No declarations of interest were made for the item.

Why

The council is acquiring more properties for the Homelessness and Community Based Services and forecasts a significant increase in the number of voids needing rapid, specialist refurbishment work over the next two years. Report 4.2, 5.1

Bringing more council properties into use is intended to reduce reliance on expensive private rented sector accommodation for homeless households and to keep families in the borough. Report 5.3

Existing council services need additional short term contractor capacity to deliver the time dependent void works at the required pace. Report 4.3

What happens next

The contract is to be varied so the existing contractor can carry out additional refurbishment works on recently acquired HCBS properties to bring them up to the decent home standard for letting. Report 5.4

Works will include measures to enhance water consumption and energy efficiency in the void properties, supporting the council's climate change emergency commitments. Report 7.3, 8.1

The contractor will deliver social value through apprenticeships and, where possible, use of the local supply chain for labour and materials.

Options considered

  • Rejected: Do not uplift the contract or reduce its scope to recently acquired HCBS properties. Would leave acquired properties uninhabitable, leave the council holding vacant deteriorating stock at additional cost, and keep homeless households in more expensive private rented sector homes Report 4.1
  • Rejected: Use the council inhouse team to deliver the additional works. Inhouse capacity is insufficient to handle the forecast increase in void properties requiring rapid, specialist work Report 4.2
  • Chosen: Uplift the existing short term void works contract. Provides the additional capacity needed to deliver time dependent void works and bring more homes into use Report 4.3

Implications

  • Financial: Bringing more council properties into use is intended to reduce spending on private rented sector homes used for homeless households. Report 5.3
  • Legal: The contract is below the public procurement threshold, so the Public Contracts Regulations 2015 and the Procurement Regulations 2024 do not apply, and the variation is governed by the council's Contract Standing Orders.
  • Equalities: There is no change to the equality implications set out in the original decision paper; the council has had due regard to its Public Sector Equality Duty under the Equality Act 2010.
  • Climate: Works include provisions to enhance water consumption and energy efficiency in the void properties, supporting the climate change emergency theme of the Corporate Delivery Plan. Report 7.3, 8.1
  • Staffing: Existing council services will receive additional short term contractor support to manage the increased void workload. Report 4.3
  • Other: The contractor is committed to social value through apprenticeships and use of the local supply chain for labour and materials where possible.

Who and where

  • Homeless households in Haringey needing accommodation Report 4.2, 5.1, 5.3
  • Properties acquired for the Homelessness and Community Based Services (HCBS) Report 5.1, 5.4
  • Homes for Haringey, the council's housing company Report 5.1
  • Local supply chain businesses and apprenticeship candidates

Timeline

  • Since 2019: 370 homes have been acquired for the HCBS to provide accommodation to homeless households Report 5.1
  • Ongoing: Haringey Council and Homes for Haringey are targeting acquisitions of 250 new properties per year Report 5.1
  • Next two years: A significant increase in the number of properties requiring void works is forecast Report 4.2

Plain English for the jargon

  • HCBS: Used in the report for the council's homelessness and community based housing service, through which properties are acquired to house homeless households
  • PSL: Used in the contract title alongside HCBS, referring to void property work in the leasing programme
  • Void: A council property that has become empty between lettings and needs refurbishment before being re-let
  • CSO: Contract Standing Orders, the council's rules on how contracts are awarded and varied
  • CDP: Corporate Delivery Plan 2022-2024, the council's high level strategy document
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Alternative options considered

4.1The primary alternative to the proposed contract uplift would be for the contract to not deliver the required works or reduce the number of void properties within the scope of the contract specifically in relation to recently acquired HCBS properties. This is judged to be unviable as to not carry out these required, essential works would leave these properties uninhabitable and vacant. This would result in the council incurring significant costs, with prospective households continuing to reside in more expensive, private sector accommodation. It would also leave Haringey Council in possession of vacant properties in a deteriorating condition. Additional expenditure would be incurred from the need to secure these properties and prevent squatting or other damage.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract uplift in respect of contract for the provision of refurbishment works at Void Properties in the area of Haringey.Minutes 157 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies