Approval to tender, Land rear of Woodridings Court N22

Decided Executive 1 paper

AI summaryHaringey Cabinet Member approves competitive tender to appoint a contractor for 37 new council homes on derelict land behind Woodridings Court, using volumetric construction next to a Network Rail line.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedApproval to start competitive procurement for contractor
MoneyCosts in exempt Appendix 2, not published
What happens nextTender via DPS or FrameworkLCP DPS and Framework under CSO 7.02 and 8.01
Who it affectsWoodridings Court residents and new tenantsExisting block of 56 flats and future homes

What was decided

The Cabinet Member for Housing and Planning, with the Leader's agreement, approved the start of a competitive tender exercise for a contractor to build 37 new council homes on the Woodridings Court site, under Contract Standing Orders 2.01(b) and 0.08. Report 9.2, 9.3, 9.5, 9.9, 6.1

Procurement will run on a price and quality basis, with quality scored 0 to 5 by the project team, moderated by Strategic Procurement, and cost assessed independently by the Council's Cost Consultant. Report 6.2, 6.3, 6.4

A further Cabinet report at Gateway 3 will be brought forward to award the construction contract if the tender succeeds. Report 6.5

Why

The Council wants to deliver 37 new council homes, including three wheelchair adaptable homes, on a derelict, Council-owned site held in the Housing Revenue Account, contributing to its target of 3,000 homes by 2031. Report 5.1, 5.5, 5.6, 9.11

The site sits very close to an active Network Rail line, and the design and construction must be carefully coordinated with Network Rail on safety and operational grounds. Report 5.4, 8.2

A category 1 volumetric approach, with most components factory-built and delivered for installation, is judged the best route to value for money and least disruption for existing residents. Report 5.3, 5.5

What happens next

Strategic Procurement will work with the service to pick the route to market, starting with the LCP DPS and Framework, and seek Chief Procurement Officer approval if neither is usable. Report 6.1, 9.7

A comprehensive tender report covering quality and cost evaluations will be produced at the end of the process. Report 6.4

Subject to a successful tender, a Gateway 3 paper will go to Cabinet to seek approval to award the construction contract. Report 6.5

Options considered

  • Rejected: Not proceed with a competitive tender or develop the site for housing. Does not align with the Council's strategic objective to deliver a new generation of Council homes Report 4.1

Implications

  • Legal: The Director of Legal and Governance sees no legal reasons preventing the recommendation, and using a Framework or Dynamic Purchasing System under CSO 7.02, 8.01 or 8.02 is a compliant route. Report 9.4, 9.5
  • Financial: Finance confirms the scheme is in the Housing Revenue Account financial plan within the recently approved Medium Term Financial Plan, with further finance detail in the exempt Appendix 2. Report 9.10, 9.12
  • Equalities: A full Equality Impact Assessment concludes the decision will have a positive impact, helping women, young people, lower socio-economic groups and Black, Asian and Minority Ethnic residents over-represented in temporary accommodation, and providing three parking spaces for the three wheelchair homes. Report 9.17, 9.18, 9.19, 9.20
  • Climate: The scheme is designed to Passivhaus principles, uses sustainable technologies to cut carbon emissions against the Building Regulations baseline, and all homes are dual aspect for cross-ventilation and daylight. Report 7.2, 8.1, 8.3
  • Risk: The site's proximity to an active Network Rail line imposes strict limits on design, construction and maintenance and needs ongoing coordination with Network Rail. Report 5.4, 8.2
  • Other: The appointed contractor will carry out a public function and must have due regard to the Public Sector Equality Duty throughout delivery. Report 9.21

Who and where

  • Existing residents of Woodridings Court, 56 flats in the current block Report 5.1, 5.3
  • Future council tenants of the 37 new homes, including three wheelchair adaptable homes Report 5.1, 9.20
  • Households in Haringey on the housing register and in temporary accommodation Report 9.17, 9.19
  • Residents in the Alexandra ward area, including 973 local addresses contacted during engagement Report 5.10, 9.16
  • Forty secure tenants and sixteen leaseholders consulted under section 105 Report 5.14

Timeline

  • 2nd August 2021 until 2nd September 2021: Section 105 consultation on changes to amenities of secure tenants Report 5.13, 5.14
  • September 2021 to 17th October 2021: Pre-application community engagement events Report 5.11
  • 2026-04-07: Cabinet Member decision to approve competitive tender
  • Gateway 3 (future): Further Cabinet report to award the construction contract Report 6.5

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account for council housing income and spending
  • CSO: Contract Standing Order, the Council's rules for procurement
  • DPS: Dynamic Purchasing System, a list of pre-approved suppliers for ongoing tenders
  • LCP: London Construction Programme framework used for procuring construction works
  • Passivhaus: A high energy efficiency building standard that significantly cuts heating demand
  • Volumetric construction: Factory-built three-dimensional units craned into place on site
  • Section 105 consultation: Consultation required by section 105 of the Housing Act 1985 with secure tenants on changes to their housing
  • EQiA: Equality Impact Assessment, an analysis of how a decision affects protected and other groups
  • ASB: Anti-social behaviour
  • MTFP: Medium Term Financial Plan covering several years of council budgets
  • Gateway 3: Haringey's stage in its project approval process before awarding a construction contract
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Report for: Cabinet Member Signing – 7 April 2026

Title: Approval to Tender, Woodridings Court N22 Report Authorised by: Taryn Eves, Corporate Director of Finance and Resources

Lead Officer: Robbie Erbmann, Delivery Director of Capital Projects & Property

Ward(s) affected: Alexandra Ward

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration

1.1Cabinet Member for Housing and Planning (Deputy Leader) is requested to approve, as required under Contract Standing Order 2.01b and CSO 0.08 the commencement of a tender process for the selection of a contractor to deliver a new-build housing development comprising thirty-seven Council homes.

1.2The development will be situated on Council-owned land to the rear of Woodridings Court (N22 7RX). The location of the proposed homes is illustrated in the ‘Proposed Site Plan’ provided in Appendix 1.

1.3All thirty-seven homes will be delivered as Council housing and let at Social Rent levels.

2 Cabinet Member Introduction

2.1This report seeks Cabinet Member approval to progress the development of the Woodridings disused under croft car park and podiums site (land to the rear of Woodridings Court N22 7RX) as part of the Council’s Housing Delivery Programme.

2.2The Council has committed to delivering 3,000 new council homes by 2031 in response to the significant and growing demand for genuinely affordable housing in the borough. This commitment forms a central part of our strategy to address the housing crisis and improve outcomes for residents in housing need.

2.3Woodridings Court scheme will contribute to this target by delivering thirty-seven new council homes for affordable rent. The scheme has been designed to make efficient use of underutilised council-owned land while enhancing the surrounding environment and supporting inclusive neighbourhood development.

2.4This project reflects the Council’s wider approach to placemaking, delivering high- quality, sustainable homes that meet local needs and contribute positively to the character and functionality of the area. 2. Recommendations It is recommended that Cabinet Member for Housing and Planning (Deputy Leader):

2.1Approves the initiation of a tender process for the selection of a contractor to deliver the new-build development of thirty-seven Council homes at land to the rear of Woodridings Court N22 7RX. This approval includes the anticipated total scheme cost as detailed in the exempt section of this report.

Cabinet Member for Housing and Planning (Deputy Leader) to note:

2.2The new build construction costs presented in the part B exempt report have been supported by the Council’s appointed Quantity Surveyor (QS) based on the current stage of the scheme’s design development (RIBA Stage 3b). As such, they reflect the best available information at this point in time but remain subject to change once suppliers submit their bids.

2.3These cost estimates are indicative and intended to support decision-making at this stage. They do not represent a final budget. The total scheme cost will be confirmed following completion of the competitive procurement process and will be reported through the appropriate governance channels for approval, in accordance with CSO 2.01.(c) and CSO 0.08.

3. Reasons for decisions

3.1The Council’s Contract Standing Order item 2.01.b requires Cabinet approval to commence a procurement exercise for proposed contracts valued £500k or above.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to tender, Land rear of Woodridings Court N22Minutes 482 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Approval to tender, Land rear of Woodridings Court N22This decision
  2. Pre-tender approval to commence procurement for Housing-Related Support – Single Adults Complex Needs Supported HousingDecided
  3. Approval to tender valuation and survey services relating to the acquisitions programmeDecided
  4. Pre-approval to proceed to tender for Adult Social Care Home Care and Reablement ServicesDecided
  5. Approval to tender a JCT Design and Build Contract for the Kings Road Car Park site, N17Decided
  6. Approval to tender for a works contractor to build 17 homes at Tiverton EstateDecided

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies