Rainham and Beam Park Regeneration LLP Business Plan 2019/2020

Approved Executive 1 paper

Cabinet approved this item on Wednesday 13 February 2019. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

Cabinet: Approved the draft Rainham and Beam Park Regeneration Joint Venture LLP Overarching Business Plan 2019-20, full details of which are contained within the Exempt Agenda Report . Agreed that the Leader of the Council and Cabinet Member for Housing after consultation with the s151 Officer, the Chief Executive Officer and the Director of Legal and Governance, approve the finalised Overarching Business Plan 2019-20, and possible later incorporation of an additional site known as the ‘Rainham Opportunity Site’ as may be presented during the Business Plan 2019-20 period. Agreed to Endorse and Recommend to Council the budget allocation set out in this report to include the related site known as ‘Rainham Opportunity Site’ with the Rainham and Beam Park Regeneration Scheme. Agreed that the s151 Officer, after consultation with the Cabinet Member for Housing, responds to the service of any notice as described in Section 8.4 of this report, served by the Rainham and Beam Park Regeneration Joint Venture LLP, indicating a willingness or otherwise to participate in making third party debt available from the Council, subject to contract and due diligence. Agreed that the s151 Officer, after consultation with the Chief Executive and The Leader of the Council, may enter into funding agreements consistent with the Treasury Management Strategy and Council’s Scheme of Delegation. Agreed the revised capital profile which brings forward £1.5m capital expenditure from 2019/20 to 2018/19.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 13 pages

Summary

The Council’s over-arching vision for setting up the Joint Venture (JV) was to stimulate the regeneration of a key area in the south of the borough characterised as the ‘Rainham and Beam Park Housing Zone’. In March 2018 this Council entered into a joint venture Limited Liability Partnership (known as Rainham and Beam Park Regeneration LLP – “RBPR”) with Notting Hill Commercial Properties (a subsidiary of Notting Hill Genesis) to deliver this vision.

Nine strategic sites along the A1306 have been identified that will require direct intervention to enable development that accords with the Council’s overall Housing Zone objectives. With the Council’s support, the LLP has now embarked on a programme to assemble these sites and to deliver their redevelopment.

To compliment this redevelopment the Council is delivering a programme to reconfigure the A1306 New Road and is supporting the GLA to deliver the new ‘Beam Park’ rail station. The adjacent scheme to transform New Plymouth and Napier Estates as part of the HRA 12 Estates housing transformation programme will also benefit from this activity.

Together these opportunities create a major opportunity to build a new strong sustainable community with its own identity and improved transport infrastructure.

Any returns to the Council are being committed to fund future regeneration programmes across the borough and help fund renewal of our cherished town centres across the borough at a time when the traditional high streets are under significant threat from changing consumer habits.

When the initial Overarching Business Plan (OABP) was agreed by Cabinet, this was on the basis that there would be regular (annual) reviews and Cabinet would be asked to agree material changes to the OABP on an annual basis. This is the first of those reviews.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rainham and Beam Park Regeneration LLP Business Plan 2019/2020Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. Rainham and Beam Park Regeneration LLP Business Plan 2019/2020This decision
  2. Rainham and Beam Park Business Plan Update 20206/27Noted
  3. Options for the Rainham and Beam Park Joint VentureApproved
  4. Rainham and Beam Park, Land Acquisition Strategy, making of CPO(s)Agreed
  5. Rainham and Beam Park Housing Zone - Appointment of a Joint Venture Development Partner.Noted
  6. P1901.11 - beam reach 8, former murex site, rainham - extension of time limit of application u0011.06 - (variation of the conditions precedent in outline planning permission p2078.03 to enable the discharge of conditions separately on a phaAgreed

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies