London Borough of Havering
Cabinet, Wednesday 28 January 2026 at 7.00pm

Rainham and Beam Park Business Plan Update 20206/27

Noted Executive 1 paper

AI summaryHavering Cabinet approved management and placemaking strategies for Council owned Rainham and Beam Park sites, with financial support, and authorised officers to appoint specialists and instruct legal officers. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFurther investment schemes will return through further reports. [D]
MoneyCabinet approved financial support, with details in Exempt Appendix C. [D] [P15]
What happens nextFurther reports and officer action [D]Officers may appoint specialists and instruct legal officers. [D]
Who it affectsRainham and Beam Park [D]Commercial and residential properties now owned by the Council. [D]

What was decided

Cabinet noted the LLP's new membership arrangement, with the retiring partner's interest sold to the Council and Nominee Co as the second member, and approved the management strategy for the Council's commercial and residential sites. Report 10.12, 10.14, 10.15

Cabinet approved the placemaking strategy and noted that schemes needing further investment, design and planning will return through further reports. Report P13, P14

Cabinet approved financial support for the management strategy, placemaking strategy and possible further investment work, and authorised the Strategic Director of Place and the Assistant Director of Regeneration & Place Shaping to implement the strategies, give legal instructions and appoint specialists. Report P15, P16

Why

The original plan assumed Beam Park Station would be confirmed and delivered, but delay led to the CPO's withdrawal and suspension of development activity. Report 10.8, 10.10, 10.11

The short and medium term plan seeks to improve site use, rental income and key frontages while the station decision is pending. Report 1.0, 4.0, 7.0

A new school and health centre are complete and in use, but residential development remains stalled while the station decision is made. Eight homes have been repaired and occupied, and one additional home will be presented in the first quarter of 2026. Further schemes require planning consent, finance, current market information and some land assembly. Report 11.2, 11.7, 11.9, 11.10

What happens next

The Strategic Director of Place and the Assistant Director of Regeneration & Place Shaping may instruct legal officers and appoint architects, surveyors, engineers, planning advisers and agents. Report P16

The GLA will report its due diligence work to the Mayor and ministers in the first quarter of 2026, with a final review before a decision. The LLP will also present an additional home. Report 11.5, 11.7

The Council and LLP will bring further recommendations on investment, design, planning, land assembly and possible commercial or enabling development. Temporary modular homes and early development phases also remain under review. Report 11.8, 11.10, 11.11, 14.1

Options considered

  • Chosen: Management and placemaking strategies for Council owned sites. They aim to improve site use, rental income and frontages while the station decision is pending. Report 4.0, 7.0
  • Rejected: Leave the sites unimproved. Properties could continue to deteriorate, putting the Council's reputation and credibility as a landlord at risk. Report 12.1, P61
  • Rejected: Do not seek to improve revenue income. The Council is committed to improving revenue to help its financial position. Report 12.2, P64
  • Rejected: Stop reviewing development options. Reviewing design, delivery and funding improves readiness to act when economic conditions allow. Report 12.3, P66
  • Rejected: Stop exploring land assembly opportunities. Other ownership could dilute the Council's sites and compromise comprehensive development and high quality placemaking. Report 12.4, P68

Implications

  • Financial: Cabinet approved financial support for the management, placemaking and future investment work. The funding envelope and financial risks are in Exempt Appendix C. Report 8.0, P15, 13.0, P72
  • Financial: Service charges are being introduced at sites in multiple occupancy, while better rents and appearance are intended to optimise the portfolio. Report 11.13, 11.14, 11.15
  • Legal: The Council may acquire land by agreement under section 120 of the Local Government Act 1972 and use section 111 for action connected to its functions. It may also use section 1 of the Localism Act 2011, subject to rationality and public law constraints. Report 14.2, 14.3
  • Legal: The Council and Nominee Co have agreed the Conformed Members Agreement, which sets the LLP's governance, and future reports must identify legal implications and risks. Report 14.1, 14.4
  • Risk: Development requires comprehensive planning consent, finance, deliverability and viability, current survey and cost information, and further land assembly in places. Programme delays create continuing issues for review, although the decision itself is not expected to cause negative wellbeing effects. Partnership delivery models can contain the Council's financial involvement and delivery risk. Report 11.9, 11.10, 11.16, 17.1, 17.2
  • Staffing: The programme requires continued input from Regeneration Directorate officers, other Council services and external resources. Report 15.1
  • Equalities: No adverse Public Sector Equality Duty implications were identified. If a negative impact is possible, a full Equality Impact Assessment will be undertaken, along with a Health Impact Assessment. Report 16.3, 17.6
  • Climate: No environmental or climate change implications or risks arise from the report. Report 17.8

Who and where

  • People in the Council's emergency housing programme, including tenants previously housed in high cost private accommodation Report 5.0, 11.7
  • Residents of Rainham and South Hornchurch Report 17.3
  • Disabled people and carers Report 17.6
  • People needing affordable, lifetime or disabled housing Report 17.3, 17.4
  • Existing and prospective commercial occupiers Report 6.0, 11.12
  • Local community, employers and residents near Beam Park Station Report 11.3
  • Local landowners and developers Report 11.17
  • The Council as property owner and landlord Report 5.0, 6.0, 11.15

Timeline

  • December 2021: The CPO was withdrawn after delays to the anticipated confirmation of Beam Park Station. Report 10.5, 10.10
  • 19th July 2023: Cabinet made the decision underpinning the Council's acquisition of assets from the original regeneration partner, Notting Hill Genesis. Report 1.0
  • this academic year: A new primary school opened. Report 11.17
  • 28th January 2026: Cabinet approved the management and placemaking strategies and financial support. Report P9, P15
  • first quarter of 2026: The GLA's station work will report to the Mayor and ministers for final review before a decision. Report 11.5
  • first quarter of 2026: The LLP will present an opportunity for one additional home. Report 11.7

Plain English for the jargon

  • RBPR LLP: Rainham and Beam Park Regeneration LLP, the partnership tasked with residential led regeneration across nine sites. Its Members are the Council and Nominee Co. [10.1] [10.15]
  • CPO: The Council's land assembly measure for the Rainham and Beam Park sites, withdrawn in December 2021. [10.5] [10.10]
  • Comprehensive development: Development of an assembled site as a whole rather than in fragmented pieces. [10.4]
  • Placemaking: Improving the use and appearance of sites while influencing wider development. [4.0] [7.0]
  • Nominee Co: A company wholly owned by the Council that acts as the LLP's second Member. [10.14] [10.15]
  • GLA: The body delivering Beam Park Station and reporting to the Mayor and ministers. [11.3] [11.5]
  • Public Sector Equality Duty: The Council duty to eliminate discrimination, advance equality of opportunity and foster good relations. [16.1] [P84] [P85]
  • Service charges: Charges introduced for sites in multiple occupancy to reduce the Council's contribution to running and maintenance costs. [11.14]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item77

Resolved

Report Title: Rainham and Beam Park Business Plan Update 20206/27 Presented by: Councillor Graham Williamson, Cabinet Member for Development & Regeneration Cabinet : 1. Noted the current status of Rainham and Beam Park Regeneration LLP in the context of the delayed regeneration plans for Rainham and Beam Park. 2. Noted and approved the management strategy for the commercial and residential sites now owned by the Council as detailed in this report and in Exempt Appendix A. 3. Noted and approved the placemaking strategy as detailed in this report and Exempt Appendix A, so as to allow Rainham and Beam Park Regeneration LLP and the Council to influence the development plan for Rainham and Beam Park. 4. Noted that schemes that might be considered suitable for further investment, including detailed design and planning, will be the subject of further reports and recommendations. 5. Approved the proposed financial support necessary to deliver recommendations 2, 3 and 4 above, details of which are contained within Exempt Appendix C. 6. Authorised the Strategic Director of Place and the Assistant Director of Regeneration & Place Shaping to take any action necessary to bring into effect recommendations 2-3 above including, but not limited to, instructions to legal officers and the appointment of architects, surveyors, engineers, planning advisors and agents.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 13 pages

Summary

1.0This Business Plan considers short and medium term measures appropriate for managing the assets acquired by Havering Council from its original regeneration partner, Notting Hill Genesis, in accordance with the Cabinet decision granted on 19th July 2023.

2.0The long-term aim remains to facilitate delivery of a scheme of residential led regeneration across 9 comprehensive development sites along the A1306 New Road corridor in Rainham. The sites, largely in industrial use, are in multiple ownerships and often in poor environmental condition; residential development values in the area are very challenging.

3.0The Business Plan considers scope to prepare specific sites for potential development pending approval of the new Beam Park Station by the Mayor of London. The investment in this station, and subsequent improvement in rapid transport options for the neighbourhood is expected to make a positive contribution to the local area and its economy, helping to stimulate demand for new homes and an improvement in the market for new homes.

4.0In the meantime, the Plan seeks to improve utilisation and revenue income from existing sites and to improve the appearance of key frontages as part of the Council’s place-making role.

5.0The sites are in varying states of condition. The majority have occupiers in situ and generate an ongoing rental stream. Nine of the properties are residential and have now been repaired or will soon be repaired and brought into use in support of the Councils emergency housing programme.

6.0The remaining properties are commercial. The majority are occupied and generating rental income for the council. Some commercial properties are vacant but being marketed for new occupiers or are being considered for interim uses, including short term residential.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rainham and Beam Park Business Plan Update 20206/27Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. Rainham and Beam Park Business Plan Update 20206/27This decision
  2. Options for the Rainham and Beam Park Joint VentureApproved
  3. Rainham and Beam Park Regeneration LLP Business Plan 2019/2020Approved
  4. Rainham and Beam Park, Land Acquisition Strategy, making of CPO(s)Agreed
  5. Rainham and Beam Park Housing Zone - Appointment of a Joint Venture Development Partner.Noted
  6. P1901.11 - beam reach 8, former murex site, rainham - extension of time limit of application u0011.06 - (variation of the conditions precedent in outline planning permission p2078.03 to enable the discharge of conditions separately on a phaAgreed

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies