Cabinet 1. Noted The Strategic Director of Place will bring forward a report proposing the use of Compulsory Purchase Order (CPO) powers for the Chippenham Road development. This report will detail the necessity of invoking CPO powers to acquire outstanding land interests. 2. Delegated authority for the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to agree on and thereafter submit, accept and utilise grant funding bids to support the 12 Sites regeneration programme. 3. Approved the revised approach to proceed with a Council-led scheme prioritising the development of Blocks 9, and 10, along with a temporary energy centre, as part of Phase 1 of the Waterloo and Queen Street programme. 4. Delegated authority to the Strategic Director of Place to make variations to any of the joint venture agreements, as necessary, to implement the recommendations contained in this report. 5. Noted that the HWR JV Business Plan document will be presented to Cabinet in Q1 2025/26.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This report provides an update on the 12 Estates Programme. Financial data within this paper utilises the most current information available, for the purpose of informing the HRA Business Plan refresh. The HWR JV Business Plan will be presented to Cabinet once it comes forward in Q1 2025/26.
This update outlines the latest position on:
Work Package One
New Green - progress on completion and sale receipts. Park Rise - progress on completion, sales, and marketing. Waterloo & Queen Street – update on scheme phasing and viability.
2 5th February 2025
Work Package Two
Chippenham Road – design development, planning submission and planned demolition Farnham & Hilldene - design development and consultation.
Later Phases
It is noted that work is currently paused on the following sites:
1. Note The Strategic Director of Place will bring forward a report proposing the use of Compulsory Purchase Order (CPO) powers for the Chippenham Road development. This report will detail the necessity of invoking CPO powers to acquire outstanding land interests.
2. Delegate authority for the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to agree on and thereafter submit, accept and utilise grant funding bids to support the 12 Sites regeneration programme.
3. Approve the revised approach to proceed with a Council-led scheme prioritising the development of Blocks 9, and 10, along with a temporary energy centre, as part of Phase 1 of the Waterloo and Queen Street programme.
4. Delegate authority to the Strategic Director of Place to make variations to any of the joint venture agreements, as necessary, to implement the recommendations contained in this report.
5. Note that the HWR JV Business Plan document will be presented to Cabinet in Q1 2025/26.
3 5th February 2025
REPORT DETAIL
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.