Cabinet, Wednesday 28 January 2026 at 7.00pm

Havering Wates Regeneration Joint Venture Business Plan

Approved Executive 1 paper

AI summaryHavering Cabinet approved the 2026/27 joint venture business plan and delegated contracts, land acquisition, grant bids and adjustments within approved budgets. Later phases are likely to remain paused over the next 12 months. [D] [P22]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThe plan covers 2026/27 and delegates programme delivery powers. [D] [P12]
MoneyNot stated
What happens nextOfficers can begin delivery work [D]Contracts, land and grants may progress within approved budgets. [D] [P13] [P21]
Who it affectsNot stated

What was decided

Cabinet approved the Havering and Wates Regeneration Joint Venture Business Plan for 2026/27. Cabinet also noted that work beyond Work Package 2 is paused and likely to remain so over the next 12 months. Report P12, P22

The Strategic Director of Place may, with Cabinet Member consultation, enter pre construction services agreements, an overarching framework contract, and a Phase 1 Farnham and Hilldene demolition contract where appropriate. The demolition contract must remain within the approved budget and follow completion of land assembly. Report P13, P14, P15

Cabinet noted updated viability and financial implications and delegated land appropriation, including between the Housing Revenue Account and General Fund for planning purposes. It also delegated property acquisition by private treaty or an approved Compulsory Purchase Order, and legal steps to secure vacant possession. Grant bids, related funding agreements and budget adjustments were delegated within approved budgets, with material variances returning to Cabinet. Report P16, P17, P18, P20, P21

Why

The plan increases affordable housing purchased through the joint venture on appropriate terms, to help sustain the Housing Revenue Account over the long term. Report P140

It increases family housing and retirement provision in the borough. Report P140

It replenishes social homes lost through right to buy sales in recent years. Report P140

What happens next

Officers may enter pre construction services agreements once necessary land, funding and planning requirements are met, allowing design development, surveys and contractor pricing within approved budgets before main contract awards. Report P13

Officers may progress the proposed St Andrew’s Church Hall land swap, outstanding property acquisitions and the Farnham and Hilldene demolition contract, subject to the stated conditions. Report P15, P17, P36

Officers may prepare, submit, accept and use external grant bids, enter related funding agreements and make adjustments within approved budgets to maintain programme viability. Report P18, P20, P21

Options considered

  • Chosen: Approve the 2026/27 business plan and delegate delivery powers. To sustain the Housing Revenue Account, increase family housing and retirement provision, and replenish social homes. Report P140
  • Rejected: Reduce affordable housing and convert some units to private sale. This would conflict with policy aims, increase housing waiting lists and raise homelessness prevention costs. Report P140

Implications

  • Financial: Financial returns secured by the Council from the joint venture will be reinvested in future regeneration. Vacant acquired units used for temporary accommodation support homelessness pressures and reduce General Fund costs. Report P25, 5.2
  • Financial: Farnham and Hilldene will be implemented in phases to manage financial risk. Later phases require detailed business cases, and commercial relocations will be sequenced. Report 8.6
  • Risk: Current economic volatility has significantly affected Work Packages 3 and 4, whose viability and delivery timelines remain under review. Report 8.7
  • Legal: The Council is contractually committed to progress the project under its agreements with Wates and the joint venture unless variations are agreed. Report 12.3
  • Equalities: The Council is maintaining early resident engagement, support for vulnerable residents, accessible communications and equality reviews at key decision stages. Report P149
  • Climate: There are no adverse environmental or climate implications directly from the decision. The programme targets high energy performance, and where possible includes green roofs, green spaces, electric vehicle charging and cycle storage. Later phases of Waterloo and Queen Street are planned to use 95% air source heat pumps and 5% electric supply. Report 16.0, P162, P164
  • Staffing: No direct Human Resources implications or risks affecting the Council workforce were identified. Report P145
  • Other: Good quality affordable housing is expected to improve health and wellbeing. The proposals give rise to no health and wellbeing risks. Report 15.4, 15.7

Who and where

  • People on the Housing Register, people on low incomes and households in greatest need Report P26, 15.4
  • Residents across the 12 estates, including vulnerable residents and people with protected characteristics Report P149, P154
  • Council tenants, leaseholders and freeholders affected by redevelopment Report P113
  • Existing commercial occupiers, local businesses and small and medium enterprises Report P52, P121
  • Local residents seeking training, jobs, apprenticeships and work placements Report P120, P121, 15.6
  • St Andrew’s Church and the Church of England, through the proposed land swap Report P36, 8.0
  • The Council’s Housing Revenue Account and General Fund Report P16, P25, 5.2
  • The Greater London Authority as a key funding partner Report P53

Timeline

  • end of January 2024: Park Rise reached practical completion. Report 8.3
  • February 2025: Cabinet received and approved the sixth review of the joint venture business plan. Report P28
  • 28th January 2026: Cabinet approved the 2026/27 business plan and delegated delivery powers. Report P10
  • early 2026: Final terms and required approvals for the St Andrew’s Church land swap will be presented to Cabinet through an Executive Decision. Report P36
  • March 2026: A planned grant draw-down will maintain programme viability and align with funding milestones. Report P29
  • March 2026: Chippenham Road is on track to enter contract. Report P47, 8.4
  • over the next 12 months: Work on later phases is likely to remain paused. Report P22
  • 2026: Students are planned to visit the delivery of modular units. Report P123

Plain English for the jargon

  • HWR: Havering and Wates Regeneration Joint Venture, the development company through which the Council and Wates deliver the programme. [P25] [P27]
  • PCSA: Pre Construction Services Agreement used for design development, surveys and contractor pricing before main contract awards. [P13]
  • HRA: Housing Revenue Account, which the plan is intended to sustain over the long term. [P16] [P140]
  • EqIA: Equality Impact Assessment for the 12 Estates Programme. [P149]
  • GLA: Greater London Authority, a key funding partner in the Farnham and Hilldene scheme. [P53]
  • LAR: London Affordable Rent. [P44]
  • SO: Shared Ownership. [P44]
  • 12 Estates Regeneration Programme: The Council programme to renew town centres and estates while providing affordable homes. [P25]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item80

Resolved

Report Title: Havering Wates Regeneration Joint Venture Business Plan Presented by: Councillor Graham Williamson, Cabinet Member for Development and Regeneration Cabinet : 1. Approved the Havering/Wates JV LLP Business Plan for 2026/27 2. Delegated authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter into Pre-Construction Services Agreements (PCSAs), where appropriate, for relevant regeneration schemes once the necessary land, funding and planning requirements are in place. This will enable design development, surveys and contractor pricing to progress within approved budgets ahead of subsequent main contract awards 3. Delegated authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter an overarching framework contract to facilitate early contractual arrangements necessary to support programme delivery. 4. Delegated authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter a demolition contract for Phase 1 of the Farnham and Hilldene regeneration, where appropriate, within the approved budget and subject to completion of land assembly. 5. Delegated authority to the Strategic Director of Place, in consultation with the Strategic Director of Resources and Cabinet Member for Development & Regeneration, to progress any land appropriation required to support delivery of the regeneration programme, including appropriation between the Housing Revenue Account and the General Fund for planning purposes, where appropriate. This delegation builds on prior Cabinet authority for land appropriation under the Havering and Wates Regeneration LLP Business Plan (Cabinet 12 February 2020 and Cabinet 8 February 2023). 6. Delegated authority to the Strategic Director of Place, in consultation with the Deputy Director of Legal Services, Strategic Director of Resources and Cabinet Member for Development & Regeneration, to agree terms and acquire all outstanding property interests required for the scheme, including progression of the proposed land swap with St Andrew’s Church Hall as set out in paragraph 2.3. This authority extends to acquisition by private treaty or, where necessary, through the approved Compulsory Purchase Order, and to taking all legal and procedural steps needed to secure vacant possession. 7. Delegated authority to the Strategic Director of Place, in consultation with the Strategic Director of Resources and Cabinet Member for Development & Regeneration, to prepare, submit, accept, and utilise external grant-funding bids, and to enter into any related funding or forward-funding agreements required to support delivery of the Havering and Wates Regeneration LLP programme and the wider 12 Sites regeneration programme, provided such agreements remain within previously approved budgets. 8. Noted the updated viability assessments and financial implications set out within the Havering and Wates Regeneration LLP Business Plan 2026/27, and delegate authority to the Strategic Director of Place, in consultation with the Strategic Director of Resources, to make adjustments within approved Cabinet budgets as required to maintain programme viability, with any material variances brought back to Cabinet for consideration. 9. Noted that work on the later phases (i.e. beyond Work Package 2) is currently paused and likely to remain so over the next 12 ...
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 21 pages

Summary

This report provides an update on the 12 Estates Regeneration Programme. Financial data within this paper utilises the most current information available, for the purpose of informing the HRA Business Plan refresh.

This update outlines the latest position on:

Work Package One

 Park Rise - Completion, sales, and marketing.  Waterloo & Queen Street – update on scheme phasing and viability.

Work Package Two

 Chippenham Road – design development, planning submission and demolition of Phase 1  Farnham & Hilldene – Planning update, design development and consultation

Later Phases

It is noted that work is currently paused on the following sites:

1. Oldchurch Gardens 2. Maygreen Crescent 3. Delderfield House 4. Dell Court 5. Brunswick Court 6. Royal Jubilee Court

3 Cabinet 28th January 2026

Recommendations

Cabinet approval is sought to:

1. Approve the Havering/Wates JV LLP Business Plan for 2026/27

2. Delegate authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter into Pre- Construction Services Agreements (PCSAs), where appropriate, for relevant regeneration schemes once the necessary land, funding and planning requirements are in place. This will enable design development, surveys and contractor pricing to progress within approved budgets ahead of subsequent main contract awards

3. Delegate authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter an overarching framework contract to facilitate early contractual arrangements necessary to support programme delivery.

4. Delegate authority to the Strategic Director of Place, in consultation with the Cabinet Member for Development and Regeneration, to enter a demolition contract for Phase 1 of the Farnham and Hilldene regeneration, where appropriate, within the approved budget and subject to completion of land assembly.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Havering Wates Regeneration Joint Venture Business PlanReport 21 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. Havering Wates Regeneration Joint Venture Business PlanThis decision
  2. Havering Wates Regeneration LLP - In-Year Review of 2023/24 Business PlanNoted
  3. Havering and Wates Regeneration LLP - 2023/24 Business PlanAgreed
  4. Havering & Wates Joint Venture Business Plan Update - 2021/22Agreed
  5. Havering and Wates Regeneration LLP - Business Plan 2019/2020Approved

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies