What was decided
Cabinet agreed that the Council would make a CPO to acquire all property and other proprietary interests shown in the CPO Order Plan, including new rights where appropriate, to secure comprehensive regeneration of Bridge Close. Report P12
The Strategic Director of Place, after consultation with the Leader, Strategic Director of Resources and Deputy Director of Legal Services, was authorised to make and promote the CPO, appoint specialists, settle documents, serve notices, address objections, negotiate agreements and amend the Order Land if needed. Report P13, P14, P15, P16, P17, P18, P19, P20, P22
After Secretary of State confirmation, the Strategic Director of Place was authorised to secure vacant possession through a General Vesting Declaration or Notices to Treat and Entry, use acquired land for planning or housing purposes, and transfer or license the acquired interests to a development or contractor partner. The Deputy Director of Legal Services may affix the Council's seal after checking further information and the Equalities Impact Assessment recommendations, if no further Cabinet referral is required. Report P23, P24, P25, P26, P27, P28
Why
Cabinet must be satisfied that the acquisition facilitates development and is likely to improve economic, social and environmental wellbeing. It must also find a compelling public interest case, proportionality, public benefit that outweighs interference with rights, and no reliable alternative. Report 1.17, 8.1, 8.2, 8.5
Planning permission was granted on 28th August 2025. The scheme follows planning policy for Bridge Close and Romford and is intended to provide homes, a school, health facilities, community and cultural space, a pedestrian and cycle bridge and improvements to the River Rom. Consultation recorded approximately 70.9% support for the plans. Report 3.4, 3.5, 3.6, P9, 4.4
The CPO is a last resort after extensive negotiations, and officers consider agreement alone unlikely to secure the whole site. Acquired, exchanged or contracted interests cover 70% of the total area, and offers are in place on all other known interests. Financial modelling finds a positive return, with funding in place for full delivery without third party financing. Report 1.10, 5.18, P64, P66, 5.15, 5.10, 5.11, 7.1
What happens next
Continue negotiations with owners and occupiers and progress relocations. Make the CPO if the required land and proprietary interests still cannot be secured by agreement. Report P18, P19, 5.21
If the CPO is made, serve and advertise statutory notices with the Statement of Reasons and allow a 28 day period for representations. Unresolved objections may lead to a public inquiry, after which an inspector is likely to recommend whether the CPO should be confirmed. Report 5.22, 5.23, 5.24, 5.25
The Secretary of State decision was anticipated early Quarter 1 2027. After confirmation, the Council has 3 years to exercise the powers and acquire the required interests. Start on site is currently expected in Quarter 2 of 2027. Report 5.25
The money
- 90% Possible advance payment against the Council's property valuation, at Council discretion or the owner's request Report 5.26
Options considered
- Chosen: Make the CPO if required interests cannot be secured by agreement. The CPO is the last resort route for assembling the site and securing the regeneration scheme. Report 1.10, 5.21, P12
- Rejected: Continue acquisition by agreement without a CPO. Officers consider it unlikely that all required interests can be secured by negotiation. Report 5.18, 6.3, 6.4
Implications
- Financial: Funding is in place to deliver the full development without recourse to third party financing, predominantly through the Housing Revenue Account. Financial modelling finds a positive return and says the funding envelope is sufficient. Report 7.1, 5.9, 5.10, 5.11
- Legal: The CPO requires confirmation by the Secretary of State. The Council must show a compelling public interest case, proportionality, planning fit, public benefit, no reliable alternative, funding and deliverability. Report 1.17, 5.25, 8.5, 8.7
- Equalities: An Equalities Impact Assessment was completed in October 2024 and updated in October 2025 to understand and mitigate differential impacts on people with protected characteristics. Report 2.19
- Climate: Homes are to meet high energy efficiency standards, reducing energy consumption and carbon emissions. The scheme is also intended to revitalise the River Rom and provide open space. Report P122
- Risk: If the HICC cannot be relocated, there is a risk that compulsory purchase powers will not be granted, or conditions will be imposed. This could prevent the development continuing in the proposed form and scale. Without a CPO, housing and social infrastructure delivery could be delayed, possibly indefinitely. Report 2.21, 6.6
- Risk: Owners and occupiers may claim more than the estimated land acquisition costs. Valuation advice, approved budgets and the Compensation Code provide controls, while disputed final prices may be resolved at the Upper Tribunal (Lands Chamber). Report 5.31, 5.26
- Other: Relocation is planned for businesses, residents, statutory undertakers' apparatus and Communication Code Operators. The Council says ambulance operations and HICC services will be maintained. Report P19, 2.11, 2.20
- Staffing: A dedicated project team will use experienced external practitioners and contractors. Atkins Realis and Gardiner & Theobald advise on procurement. Report 5.12
Who and where
- Landowners, occupiers and third party interest holders within the Order Land Report P18, 2.3
- Owners of 22 commercial and 37 residential properties Report 1.1
- Businesses Report 1.13
- Residents Report 1.16
- Havering Islamic Cultural Centre Report 1.14, 2.14
- London Ambulance Service Report 1.15, 2.8
- Statutory undertakers and Communication Code Operators Report P19
- Objectors and other stakeholders Report P18, P19
Timeline
- 5th February 2025: Cabinet approved the Bridge Close Regeneration LLP Business Plan. Report 1.5
- 28th August 2025: Strategic Planning Committee granted planning permission for the scheme. Report 1.4, 3.6
- 10th December, 2025: Cabinet agreed the proposed CPO and related powers. Report P10
- Shortly after the CPO is made: Statutory notices would be served and advertised, and documents deposited for inspection. Report 5.22
- 28 days after service of notices: Those affected and the public could make representations or object to the CPO. Report 5.23
- early Quarter 1 2027: The Secretary of State decision on confirmation was anticipated. Report 5.25
- Quarter 2 of 2027: Start on site was currently expected. Report 5.25
- After confirmation, within the statutory period of 3 years: The Council must exercise its powers and acquire the required land and interests. Report 5.25
Plain English for the jargon
- CPO: Statutory order allowing compulsory acquisition of land needed for regeneration [1.10] [P12].
- BCR LLP: Bridge Close Regeneration LLP, the Council owned company leading the scheme [1.3] [1.6].
- Order Land: Land outlined for acquisition on the CPO Order Plan at Appendix B [P8] [P12].
- GVD: General Vesting Declaration used after CPO confirmation to establish the vesting and purchase process [P24] [5.26].
- HICC: Havering Islamic Cultural Centre, providing worship, cultural and charitable services [2.13] [2.14].
- LAS: London Ambulance Service, which owns and occupies Romford Ambulance Station [2.8].
- HRA: Housing Revenue Account, the main stated source of scheme funding [1.4] [5.9].
- Crichel Down Rules: Guidance on the factors for deciding whether a CPO should be confirmed [5.6].