What was decided
Cabinet approved the draft Bridge Close Regeneration LLP Business Plan 2026/27. It agreed a budget to fund delivery, for inclusion in the proposed Housing Revenue Account Capital Programme. Report P8, P9
Cabinet gave the Leader authority to approve detailed business cases, funding arrangements and legal agreements after consultation with the Strategic Director of Place, the Strategic Director of Resources and the Deputy Director of Legal and Governance. The Strategic Director of Place may negotiate, finalise and enter agreements with the Strategic Director of Resources and the Deputy Director of Legal and Governance. Report P10, P13
Cabinet noted continued discussions to relocate the HICC to a suitable alternative site and to acquire a minor part of Romford Ambulance Station land. The land is needed for the school and an emergency fire access route at the rear. Report P11, P12
Why
Under the Members’ Agreement, the Bridge Close Regeneration LLP Board must send the Council a draft plan for approval. Approval would replace the previous formal plan. Report 1.4, 5.2, 8.2
The refreshed plan brings together policies, delivery processes, a budget, forecasts, risk controls and governance. It gives the Council a framework for direct delivery of the scheme. Report 1.3, 5.3, 5.4
The plan supports approximately 35% affordable homes, subject to viability and future review, plus a school, health building, bridge, public realm and River Rom improvements. It also seeks an acceptable payback, funding certainty and certainty for affected business and resident communities. Report 5.1, 5.4, P139, P140, P141, P142
What happens next
The Bridge Close Regeneration LLP Board is to formally adopt the agreed plan. The delivery budget is to be included in the proposed Housing Revenue Account Capital Programme for the Housing Revenue Account Business Plan update. Report 8.2, P9
The Leader will approve detailed business cases, funding arrangements and legal agreements after consultation with the relevant officers. The Strategic Director of Place will negotiate, finalise and enter the necessary agreements. Report P10, P13
Land assembly, design work, compulsory purchase preparation and contractor selection will continue. The report identifies a South Street site for HICC relocation and approximately 303 sqm of ambulance station land for the school and emergency access. Report 3.31, 3.40, 3.44, 4.3, 4.5, P125
Options considered
- Chosen: Approve the draft business plan. It supports the Council’s regeneration aims, affordable housing, funding certainty and an acceptable payback. The report says the scheme should return more than the Council’s cost of capital. Report 5.4, 5.5, P138, P139, P140, P141
- Rejected: Do not approve the draft business plan. The previous plan would remain, but it would not reflect the latest planning, land, market, cost and financial advice. The Council said this could delay or lose the scheme, harm its reputation and impede key work streams. Report 6.1
- Rejected: Approve the draft business plan and pause the scheme. A pause would create uncertainty, impede planning and any compulsory purchase process, and make contractor and land agreement engagement harder. The Council also cited reputational risk and adverse effects on owners and occupiers. Report 6.2
Implications
- Financial: The budget has a minor downward adjustment. This mainly reflects lower construction and land assembly costs and fees following a reduced forecast scope. Report 7.2, P153
- Financial: The report expects an acceptable payback from the Council’s investment. It also describes the scheme’s financial return as exceeding the Council’s cost of capital. Report P141, 5.5
- Risk: Risks include planning, ground conditions, construction, cost price inflation, sales price inflation and programme risk. A rise in borrowing costs is another continuing risk. Report 7.4, 7.5, 7.6
- Legal: The Council may use statutory powers to fund the scheme and acquire land. Compulsory purchase is a last resort where an agreement cannot be reached. Report 8.4, 8.5, 8.7, 3.40, 4.5
- Legal: The Council must reimburse the HICC’s reasonable planning application costs. It is also negotiating compensation for its existing land and accommodation, and any funding shortfall for a new facility. Report 3.41
- Equalities: An Equalities Impact Assessment was completed in October 2024 and updated in October 2025 to understand and mitigate differential impacts on people with protected characteristics. Report 3.42
- Climate: The design work targets net zero compliance and at least a 35% on site reduction against the Building Regulations Part L 2013 baseline. Air source heat pumps and possible future connections to wider heating networks are also under consideration. Report P44, P45
- Staffing: Unity Trust Partnerships is due to operate and maintain the new school. Separate operators will be procured for the estate and heat network. Report 7.4
Who and where
- Existing and future residents of Havering and Romford Report P20, P21, P25, P27
- Businesses, staff, residents and families affected by displacement or disruption Report 3.23
- Property owners and occupiers still involved in land assembly Report 3.21, 3.26
- The HICC and people using its worship, cultural and charitable services Report 3.37, 3.43
- The London Ambulance Service and people relying on Romford Ambulance Station Report 3.31, 3.34, 3.35
- Primary school pupils, families and education partners Report 3.10, P56
- People using primary, social care, community and specialist health services Report P57
- People sharing one or more protected characteristics Report 3.42
Timeline
- August 2025: The Strategic Planning Committee granted planning permission for the scheme. Report P49
- 28th January 2026: Cabinet approved the refreshed business plan and delivery budget. Report P6, P8, P9
- Quarter 2 ’26: Cabinet is due to make the compulsory purchase order and begin main contractor selection. Report P125
- Quarter 1 ’27: The compulsory purchase public inquiry is due to take place. Report P125
- Quarter 2 ’27: The compulsory purchase order is expected to be confirmed by the Secretary of State. Report 4.5, P125
- Quarter 3 ’27: Vacant possession and the start on site are anticipated. Report P125, P127
- early 2031: First completions of Phase 1 are anticipated. Report P132
- 2034: Phased delivery is expected to reach completion. Report P132
Plain English for the jargon
- BCR LLP: Council controlled joint venture used as the delivery vehicle for Bridge Close regeneration. [1.1] [8.8] [8.9]
- HRA: Housing Revenue Account, used to fund the Council’s direct delivery of the scheme. [1.2] [5.2]
- CPO: Compulsory purchase order, a possible route to acquire land where agreement cannot be reached. [3.40] [4.5]
- HICC: Havering Islamic Cultural Centre, which the Council is discussing relocating from Bridge Close. [3.36] [3.39]
- LAS: London Ambulance Service, the owner and occupier of Romford Ambulance Station. [3.31]
- DfE: Department for Education, whose grant funding for the school was confirmed in December 2025. [P56]
- ICB: NHS North East London Integrated Care Board, working with the Council on health space, services and funding. [P57] [P59] [P60]