London Borough of Havering
Cabinet, Wednesday 14 January 2026 at 7.00pm

Arnold's Field Works- Contracts Award (Phase 1)

Agreed Executive 1 paper

AI summaryHavering Cabinet approved Phase 1 works at Arnold’s Field in principle, capped at £300,000, and delegated officers to award contracts or support equivalent landowner proposals. The work targets the southern area before the 2026 summer fire season, without accepting wider site responsibility. [D] [P29] [P1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedTemporary work targets the southern area [P29] [P3]
MoneyMaximum £300,000 [D]Includes first year inspection and maintenance [P61]
What happens nextOfficers procure and award [D]Landowner alternatives may be supported [D] [P45]
Who it affectsResidents and site [P27] [P71]Aims to reduce fires and smoke [P17]

What was decided

Cabinet agreed in principle to the Phase 1 proposals, with a maximum value of £300,000. This does not accept responsibility for clearing or other works across the wider site.

The Strategic Director of Place, together with the Strategic Director for Resources, may procure and award a Phase 1 contract, consider the landowner’s alternative proposals, and enter into related contracts and arrangements.

Cabinet agreed not to follow the Contracts Procedure Rules for these recommendations.

Why

The site was formally identified as contaminated land on 16 October 2025. Urgent action was needed to stop or reduce harmful smoke before the 2026 summer fire season. Report P1, P16

Only one of three explored options appeared economically viable and able to meet the required timescale. Cement polymer covering was the lowest cost and quickest option, but gives temporary relief rather than a permanent solution. Report P3, P14, P21

The landowner has ultimate responsibility, although they did not own the site during the unlawful dumping. A voluntary temporary solution was seen as an effective use of public resources to provide interim relief. Report P72, P73

What happens next

Officers will assess final quotations, select the best option and award a contract directly, with the landowner’s permission. They may instead support a developed landowner proposal with an equivalent or greater effect. Report P39, P45, P53, P56

Drone and topographical survey findings will identify the Phase 1 work area and inform EPG’s detailed specification. Report P31

Works should start in February 2026 to target completion by 30 April 2026. Monitoring will check the effectiveness of the works from May 2026 onwards. Report P2, P6, P57

The money

  • £300,000 Maximum value approved for the Phase 1 works, with no wider site liability
  • £200,000 Lower end of the expected Phase 1 cost Report P61
  • £300,000 Upper end of the expected Phase 1 cost Report P61
  • £85,000 Lower end of the landowner’s initial alternative estimate Report P62
  • £215,000 Upper end of the landowner’s initial alternative estimate Report P62
  • £5m Lower end of the estimated permanent solution cost Report P79
  • £10m Upper end of the estimated permanent solution cost Report P79

Options considered

  • Chosen: Cement polymer covering focused on the southern stretch. It was the Council’s preferred option because it was the lowest cost and quickest to implement, providing temporary relief. Report P21, P29
  • Chosen: A developed landowner alternative with equivalent or greater effect. Officers may support it if it can be completed by 30 April 2026. Report P43, P45, P56
  • Rejected: Do nothing. The Council would be in breach of its duties to seek remediation and reduce the effects on residents. Report P74
  • Rejected: Immediately pursue enforcement. A Remediation Notice and pursuit of polluters would take too long for the 2026 summer fire season. Report P74
  • Rejected: Treat the whole 17 hectare site by April 2026. It was not possible in the time available, so Phase 1 targets areas with a higher perceived risk of fire. Report P27, P79
  • Rejected: Rely on a planning application for the 2026 response. It could take seven years and would not provide a solution for next summer. Report P40, P86

Implications

  • Financial: The cost is contained up to £300,000. Further funding is likely for a temporary covering across the whole site and would require a separate key decision. The funding is earmarked from the Corporate Contingency Fund while potential support is sought from MHCLG, DEFRA and the GLA. Report P80, P81
  • Legal: The Council says the action is within its legal powers and duties. It does not accept liability for future costs, wider site works or ongoing maintenance of the temporary measures. Report P82, P89, P90
  • Legal: The preventative covering would not change the site's planning status. Enforcement against the wider site remains possible. Report P33, P36
  • Risk: The landowner may not agree the final approach, allow access or accept responsibility for completed works. Report P84, P90
  • Risk: A legal challenge to the contaminated land determination would not itself prevent voluntary works, but would likely signal unwillingness to continue with them. Report P69
  • Equalities: Poor air quality and restricted access to outdoor spaces disproportionately affect older adults, children, disabled residents, pregnant individuals and lower income households. Communication and support should be inclusive of digitally excluded residents and those with limited English proficiency. Report P94, P98, P99
  • Other: Fire related particulate pollution increases the risk of heart attack, stroke and respiratory conditions. Fires at the site are associated with GP attendances among people with existing respiratory conditions. Report P102
  • Climate: Drought and heat waves are likely to increase fires. Repeated fires add carbon emissions, while firefighting water and polluted runoff may affect the wider ecosystem. Report P105, P108

Who and where

  • Local residents exposed to smoke and fire related pollution Report P17, P71
  • Older adults and people with underlying health conditions Report P94
  • Children, including young children Report P94, P97
  • Disabled residents, pregnant individuals and lower income households Report P98
  • Residents with poorer mental health or resilience Report P95
  • Residents without private gardens who rely on public outdoor space Report P97
  • Digitally excluded residents and residents with limited English proficiency Report P99
  • The site landowner, potential main contractors and specialist subcontractors Report P23, P38, P52

Timeline

  • 16 October 2025: The Council formally determines the site as contaminated land. Report P16
  • early January 2026: Preliminary drone survey results are due. Report P6, P31
  • late January 2026: The confirmed approach is informed by the drone survey review. Report P78
  • 14 January 2026: Cabinet approves the Phase 1 approach and officer delegations. Report P9
  • February 2026: Works should begin to allow completion in April. Report P6
  • 30 April 2026: Initial works are targeted to finish. Report P2, P43
  • May 2026 onwards: Monitoring checks the effectiveness of the works. Report P57
  • 2026 summer fire season: The Council aims to stop or significantly reduce fires and smoke before the season. Report P1, P17

Plain English for the jargon

  • Arnold’s Field: A privately owned former legal landfill on Launders Lane, Rainham, RM13 9FL. [P12]
  • Contaminated land: The Council’s formal designation under Part 2A of the Environmental Protection Act 1990, which triggered the duty to seek remediation. [P16] [P89]
  • Phase 1: Temporary initial works focused on the southern stretch and intended to reduce fires in 2026. [P3] [P29]
  • Cement polymer covering: A surface treatment that clears vegetation, lightly compacts and levels the ground, then applies a thin sprayed cement and polymer layer. [P20]
  • PosiShell: The commercial polymer used in the covering. The supplier says it could last up to five years in appropriate conditions, but it has not been used in these circumstances in the UK before. [P22]
  • EPG: Environmental Protection Group, which advised the Council on capping options and the detailed specification. [P18] [P31] [P109]
  • Main contractor: A general earthworks contractor for clearance and compaction, with spraying work given to a specialist subcontractor. [P23] [P52]
  • Corporate Contingency Fund: The Council fund earmarked for this work while potential support is sought from other public bodies. [P80]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item68

Resolved

Report Title: Arnold’s Field Works – Contracts Award (Phase 1) Presented by: Councillor Ray Morgon, Leader of the Council Cabinet Members Agreed 1. In principle, to the proposals for the Phase 1 works for Arnold’s Field (as set out in this report) (without prejudice and with no acknowledgement of responsibility for works across the wider site) to be a maximum value of £300,000. 2. To delegate, to the Strategic Director of Place in conjunction with the Strategic Director for Resources, authority to: a. procure and award a contract for Phase 1 remedial works at Arnold’s Field as set out in this report; and/or b. Consider alternative arrangements on required works from the owner c. negotiate and enter into any contracts and ancillary arrangements required to give effect to the recommendations in this report 3. To waive the Contracts Procedure Rules, as required, to give effect to the recommendations in this report.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 13 pages

Summary

Due to the determination, on 16 October 2025, that the Arnold’s Field site is now formally identified as “contaminated land”, it became urgent and necessary to seek to stop (or significantly reduce) the cause of the adverse effects on human health before the next annual cycle of fires/smoke (likely to start in the approach to the summer of 2026).

As reported to residents at the public meeting on 25 November 2025, the Council has been in dialogue with the site landowner with a view to having initial works carried out at the site – aiming to be completed by 30 April 2026. These works will focus on the areas which were either responsible for most of the fires in the 2025 summer fire season and/or are most likely to be the seat of fires in 2026.

These initial works (known as “Phase 1”) are regarded as a temporary means to halting or reducing the fires to provide some interim relief to residents and do not constitute a permanent solution or full coverage of the site. The success, or otherwise, of Phase 1 will be reviewed to provide learning for any further works.

Due to the impact on public health and the need to take all necessary reasonable steps to facilitate the achievement of the works, consideration has been given to the Council providing funds, without prejudice and with no acknowledgement of responsibility for clearing up the wider site, of up to £300,000 for the Phase 1 works. This was noted in the Cabinet report (17 September 2025) on “Launders Lane (Arnold’s Field)” to achieve a “voluntary temporary solution” (at least in part) in 2026.

Whilst, at the time of drafting this report, the Council and the landowner have differing views as to the best way forward to achieve the desired result, there exists (at this time) a common commitment to meet the required works timeline.

The Phase 1 works are estimated to take up to three months and, in order to finish in April, they should begin in February. However, the preliminary drone surveys (currently being procured), will not bear results until the start of January and the detailed specifications and any alternative proposals for works cannot be developed until after those results are available.

Consequently, the timeline is tight – particularly in the context of the timescales required for the Council’s governance and procurement processes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Arnold's Field Works- Contracts Award (Phase 1)Report 13 pages DownloadRead as text

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies