Resolved
That the Environment Capital Programme 2004/05 monitoring report be noted.
Environment Scrutiny Committee noted this item on Friday 17 September 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Environment Capital Programme 2004/05 monitoring report be noted.
ENVIRONMENT SCRUTINY COMMITTEE 17 SEPTEMBER 2004
CAPITAL BUDGET MONITORING Report By: DIRECTOR OF THE ENVIRONMENT
Purpose 1. To advise Members on the progress of the 2004/05 Capital Programme for Environment Areas within the overall context of the Herefordshire Council Capital Programme.
Financial Implications 2. Capital Budgets for the Environment Programme Areas for 2004/05 are shown in Appendix 1, on an individual basis, with funding arrangements indicated in overall terms.
3. The total of the Capital Programme has been reduced from £12,643,720 notified to the previous meeting (see Appendix 1) to £12,009,519. The variations are as follows; -
(a) Approval of four schemes as part of the Prudential Borrowing arrangement
£000 Hereford Crematorium 100 Leominster Closed Landfil 45 Site Monitoring Infrastructure Extension to Hereford Cemetery 100 Improvements to Public Conveniences 150 395
(b) The Urban Bus challenge of £774,000 was incorrectly included as an expenditure item with funding. The Challenge finished in 2003/04.
(c) Completing the Jigsaw capital grant £68,385 and Safety Camera installation are funding brought forward from 2003/04.
(d) New contributions are anticipated for Legion Way Bus Stops (£6,000) and Cycle Network (£20,000).
(e) The amount of Objective 2 funding available for addition to the Roman Road scheme in 2004/5 has been confirmed at £170,000. This represents a transfer of planned funding from the Rotherwas Access Road scheme.
(f) The amount shown for the Friar Street scheme is now included as part of the traffic calming scheme budget.
Further information on the subject of this report is available from David Keetch on 01432 260227 CAPITALBUDGETMONITORINGreport0.doc ENVIRONMENT SCRUTINY COMMITTEE 17 SEPTEMBER 2004
Considerations 4. The report has been largely based on the third round of capital monitoring, which involved an examination of all schemes at the end of July 2004. Care is being taken to ensure the forecast spend accurately reflects the expected spend in 2004/05. The overall spending position is being kept under careful review by the Environment General capital-working Group.
5. The actual spend against each scheme is shown as at 31st July 2004.
6. The total spent or committed to 31st July date is £4.812 million or 39% of the Revised Forecast.
Notes on individual schemes.
7. It is anticipated that because of the need to obtain a compulsory purchase order spending on the Rotherwas Access Road will be significantly less than forecast in 2004/5. The spending forecasts will need to be reviewed to take account of this situation.
RECOMMENDATION THAT the report be noted.
BACKGROUND PAPERS • None identified.
Further information on the subject of this report is available from David Keetch on 01432 260227 CAPITALBUDGETMONITORINGreport0.doc
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL BUDGET MONITORINGReport | 59 KB | DownloadRead as text |
PDF |
env cap append 1Report | 74 KB | Download |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.