Southern Area Planning Sub-Committee approved this item on Wednesday 23 November 2005. Below is the council's own wording, with the papers it was decided on.
That subject to there being no new relevant representations during the consultation period, the Officers named in the Scheme of Delegation to Officers be authorised to approve the application subject to the following conditions and any further conditions considered necessary by Officers: 1. A01 (Time limit for commencement (full permission)) Reason: Required to be imposed by Section 91 of the Town and Country Planning Act 1990. 2. G04 (Landscaping scheme (general)) Reason: In order to protect the visual amenities of the area. 3. G05 (Implementation of landscaping scheme (general)) Reason: In order to protect the visual amenities of the area. 4. No development within the application area shall be undertaken unless technical approval (including foundations) has been applied for and agreed by the local planning authority after consultation with the Highways Agency (required in accordance with HA BD2/05 “Technical Approval of Highway Structures” [section 3.4.2 (i)]) Reason: As directed by the Highways Agency in order to ensure the safe and free flow of traffic on the M50 motorway. 5. As soon as it is no longer required for telecommunications purposes, the development approved under the terms of this application shall be removed from the land and the land restored to its condition before the development took place. Reason: In the interests of visual amenity. Informative(s): 1. N15 - Reason(s) for the Grant of Planning Permission
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
For: Hutchinson 3G UK LTD per White Young Green Planning, Ropemaker Court, 12, Lower Park Row, Bristol, BS1 5BN
Date Received: 6th October, 2005 Ward: Penyard Grid Ref: 66639, 26112 Expiry Date: 1st December, 2005 Local Member: Councillor H. Bramer
1. Site Description and Proposal
1.1The application site is close to the south-eastern side of the M50 motorway and about 250m south-west of Junction 3 at Gorsley. The nearest road on the south side of the motorway is an unclassified road linking the junction with one of the main housing areas in Gorsley and on the north side another unclassified road runs parallel with the motorway. It is proposed to erect a 18.3m lattice mast on top of which would be 3 antennae, making a total height of just over 20m. In addition, 60cm and 30cm transmission dishes would be attached near the top of the mast. A compound of 8.45m x 5m would be constructed around the mast's base with chain link fencing and barbed wire (2.1m high). A meter cabinet and other equipment would be installed within the compound. Vehicular access would be via an existing field gate off the road linking Junction 3 and Linton, about 400m west of the application site.
1.2There are houses and a gypsy caravan site to the north side of the motorway. To the east of the application site there is a cluster of farm buildings, with a bungalow and large detached house within half a kilometre of the site but the main housing area is further away. A 30m telecommunications mast is sited about 120m south-west of the application site.
2. Policies
2.1Planning Policy Guidance PPS.7 - Sustainable Development in Rural Areas PPG.8 - Telecommunications
2.2Hereford and Worcester County Structure Plan Policy CTC.6 - Development and Significant Landscape Features
2.3South Herefordshire District Local Plan Policy C.1 - Development within Open Countryside Policy C.41 - Telecommunications Development Policy C.42 - Criteria to Guide Telecommunication Development Policy GD.1 - General Development Criteria
Further information on the subject of this report is available from [name removed] on 01432 260479 SOUTHERN AREA PLANNING SUB-COMMITTEE 23RD NOVEMBER, 2005
2.4Unitary Development Plan (Revised Deposit Draft) Policy CF.3 - Telecommunications
3. Planning History 3.1 There have not been any previous applications for development of this site.
4. Consultation Summary Statutory Consultations
4.1Highways Agency directs that a condition be attached to any planning permission in order to address their main concern that were the structure to fall this could have a detrimental impact to the safe and free flow of traffic upon the M50 motorway.
Internal Council Advice
4.2Traffic Manager has no objection to the grant of permission.
4.3Head of Environmental Health has no comment to make on the proposals.
5. Representations
5.1The applicant's agent has submitted a detailed explanation of the proposal, including maps showing a gap in coverage and the improved coverage resulting from the current proposal. In summary, the following points are made:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Southern Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.