Resolved
That the Capital Budget monitoring report be noted.
Environment Scrutiny Committee noted this item on Monday 25 September 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Capital Budget monitoring report be noted.
ENVIRONMENT SCRUTINY COMMITTEE 25TH SEPTEMBER, 2006
CAPITAL BUDGET MONITORING Report By: DIRECTOR OF ENVIRONMENT
Purpose 1. To advise Members on the progress of the 2006/07 Capital Programme for Environment Areas within the overall context of the Herefordshire Council Capital Programme.
Financial Implications 2. Capital Budgets for the Environment Programme Areas for 2005/06 are shown in Appendix 1, on an individual basis, with funding arrangements indicated in overall terms.
3. The total of the Capital Programme has been increased to £13,216,000 from £12,554,000 notified to the previous meeting (see Appendix 1). This is a net increase of £662,000 and relates to:
• LPSA 2 grant for Street scene and Road Safety totalling £310,000;
• An increase in budget on Public Toilet improvements made available through the receipt generated from the sale of old sites of £161,000;
• A reduction in budget in relation to Hereford Crematorium of £147,000 due to delays in land acquisition resulting in two months slippage in the programme.
• Slippage in the 2005/06 Capital Programme in relation to Leominster Closed Landfill Monitoring Infrastructure and Pembridge and Grafton Travellers’ Sites totalling £324,000.
Considerations 5 The report has been largely based on the latest round of capital monitoring, which involved an examination of all schemes at the end of July 2006. Care is being taken to ensure the forecast spend accurately reflects the expected spend in 2006/07. The Environment General Capital Working Group is keeping the overall spending position under careful review.
6. The actual spend against each scheme is shown as at 31st July 2006.
7. The total spent or committed to 31st July is £5.438 million or 41.1% of the Revised Forecast. The actual amount spent is £1.320 million.
RECOMMENDATION THAT the report be noted.
BACKGROUND PAPERS • None identified.
Further information on the subject of this report is available from Cathy Stokes on 01432 261849
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL BUDGET MONITORINGReport | 23 KB | DownloadRead as text |
PDF |
envt sct Capital: Appendix 1 25.09.06 geAppendix | 37 KB | Download |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.