that (i) the draft Outline Business Case for the creation of an Academy at Wyebridge Sports College be approved for submission to the Secretary of State, on the strict understanding that all capital costs associated with the project are met from within DCSF grant (£21,939,195) and that the Academy will be funded after the initial start up period on the same basis of other schools in the county; ... view the full minutes text for item 56.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
WYEBRIDGE ACADEMY – OUTLINE BUSINESS CASE PORTFOLIO RESPONSIBILITY: CHILDREN’S SERVICES CABINET 27TH MARCH 2008
Wards Affected St Martins & Hinton Belmont Hollington
Purpose To approve, for submission to the Secretary of State, the Outline Business Case for Wyebridge Sports College to become an Academy; and to authorise other necessary steps including the appointment of consultants to implement the project.
Key Decision This is a Key Decision because it is likely to be significant in terms of its effect on communities living or working in Herefordshire in an area comprising of one or more wards.
It was included in the Forward Plan.
Recommendations THAT (a) the draft Outline Business Case for the creation of an Academy at Wyebridge Sports College be approved for submission to the Secretary of State, on the strict understanding that all capital costs associated with the project are met from within DCSF grant (£21,939,195) and that the Academy will be funded after the initial start up period on the same basis of other schools in the county;
(b) the relocation of a temporary unit on the Wyebridge site as an alternative provision for Redhill Residents Association be approved in principle, subject to a successful bid being made to the capital programme to secure the necessary funding, estimated at £80,000;
(c) the signing of the Memorandum of Understanding between the Council & Partnership for Schools be authorised, thereby agreeing the use of the National Academy Framework for the procurement of the construction of the buildings be approved; and
(d) the engagement of Navigant Consultants to implement the next stage of the project at the cost of £107,000 be approved.
Further information on the subject of this report is available from George Salmon – Head of Commissioning and Improvement Tel – 01432 260802
1MAINREPORTOutlineBusinessCase270308FINALCXApprovedon20Mar080.doc Reasons (a) To make progress with the academy project, the Local Authority has to submit the Outline Business Case to the Secretary of State for his approval;
(b) Sole use space has not been offered to any third party user within the new academy building. Alternative solutions are therefore proposed.
(c) The Memorandum of Understanding commits the authority to use the National Consultants and Contractors Framework for the procurement of the new building. The Head of Asset Management and Property Services and the Strategic Procurement & Efficiency Review Manager judge this to be the most sensible way forward. The alternative requires dispensation from Partnerships for Schools, and the Council publishing OJEU notices in a separate procurement process which would incur additional cost and add to the timeframe;
(d) As part of the National Framework there is an approved list of consultants, as well as contractors, with agreed rates of engagement. Navigant Consultants is on this list, and was selected in the light of their experience locally.
Considerations 1. The complete, albeit final draft, version of the Outline Business Case is attached as Appendix 1. The completion of the Outline Business Case is dependant on the Cabinet’s decisions of today e.g. third party use and procurement process. There is also a Funding Agreement which is a contract between the Sponsors (Hereford Diocese) and the DCSF setting out what the Sponsors will do in return for ongoing revenue funding, which will be received direct from DCSF. The DCSF ensures that the arrangements, including governance, admissions and Special Education Need (SEN) provision comply with statutory requirements. The sections relating to Governance, Admissions, SEN Provision and Exclusions are attached in Appendices 3, 4, 5 and 6 respectively. The Governors will have to comply with the statutory requirement in these areas, and manage within the budget allocated to them.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.