Resolved
that Cabinet supports the Governors’ project to provide a new school building for 70 pupils in Staunton on Wye.
Cabinet decided this item on Thursday 27 March 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
that Cabinet supports the Governors’ project to provide a new school building for 70 pupils in Staunton on Wye.
STAUNTON ON WYE PRIMARY SCHOOL: REPLACEMENT AIDED SCHOOL PROJECT PORTFOLIO RESPONSIBILITY: CHILDREN’S SERVICES CABINET 27 MARCH 2008
Wards Affected Wormsley Ridge
Castle
Purpose Cabinet to approve the provision of a new build replacement school for Staunton on Wye.
Key Decision This is a Key Decision because it is likely to be significant in terms of its effect on communities living or working in Herefordshire in an area comprising one or more wards.
It was included in the Forward Plan.
Recommendations THAT Cabinet supports the Governors’ project to provide a new school building for 70 pupils in Staunton on Wye.
Reasons In 2000 the Department for Children, Schools and Families (then DfES) made a grant available to the Trustee Governors of this aided school to meet 90% of the net costs of new accommodation. This grant is dependent on the Local Authority supporting the scheme. The Department for Children, Schools and Families require an explicit expression of support from the Local Authority before 31 March 2008. Otherwise they will withdraw their offer, and place the resources back into the national fund used to fund aided schools across the country.
Considerations 1. Staunton on Wye Primary School is a 3 class school accommodated in a 3 storey Victorian Gothic Listed Building within a complex built and managed by the Jarvis Trust. Although this provides a fascinating local history, the 19th Century school accommodation is not appropriate to meeting the needs of all children in the 21st Century. There is no disabled access to the upper floors, which also rely on the adjoining but empty building as a means of emergency fire exit.
2. In terms of physical condition and suitability of teaching spaces it is one of the worst Primary Schools in the County, requiring over £177,000 to repair the building fabric. In
Further information on the subject of this report is available from George Salmon – Head of Commissioning & Improvement (Schools & Services) Tel: 01432 260802
EStauntononWyePSReplacementAidedSchoolProject270320.doc the past roof materials have fallen into playground areas, and a ceiling in the hall has collapsed. It remains an expensive building for the Governors to maintain.
3. In December 2000 the DCSF recognised this, and offered 90% funding towards the net cost of a new school. Since then there have been difficulties in identifying a site and obtaining outline planning permission. The latter was achieved in January 2004 when outline permission was granted. This was valid for 5 years, subject to 3 reserved matters (approval of the details of the siting, design and external appearance of the buildings, the means of access thereto and the landscaping of the site) being resolved before January 2007.
4. In this period pupil numbers in the County and in the Weobley Pyramid of schools declined, and questions were raised about the wisdom of proceeding with this scheme. The reserved matters were not resolved, and planning permission has now lapsed. The Planning Service Officer has advised that he is unaware of any changed circumstances. However, the outcome of any further application cannot be pre-judged. Governors would have to reapply and the application should be resolved within 3 months.
5. The site has been purchased. The original owners or their successors are entitled to recover possession if the site is not used for a school within a specified period.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STAUNTON ON WYE REPLACEMENT AIDED SCHOOL PROJECTReport | 105 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.