Resolved
RESOLVED That planning permission be granted subject to the following conditions: Commencement of works 1 A01 (Time limit for commencement (full permission)) Reason: Required to be imposed by Section 91 of the Town and Country Planning Act 1990. Approved plans 2 B01 (Development in accordance with the approved plans) Reason: To ensure adherence to the approved plans and details in the interests of a satisfactory form of development and to comply with policy DR1 of the Herefordshire Unitary Development Plan 2007. Working Method Statement 3 No development shall take place until a working method statement for the project has been submitted to and approved in writing by the local planning authority. The statement shall include in particular: i) Details of the type, source and estimated quantity of stone to be used; ii) A plan showing the indicative locations for stockpiles of stone and parking of construction vehicles plant and equipment; iii) Details of, arrangements for the public rights of way, including fencing, signage, and the use of a banksman for the crossing point; iv) Details of all preparatory work necessary, including vegetation trimming the ground preparation, excavations, working area and stone movements; v) Indicative provision for a watching brief to identify, record and protect archaeological remains; vi) Details, and a large scale plan, of the design, construction method and materials to be used for the proposed access ramp on the riverbank and the haul route at the river's edge; vii) Full methodology for the in-river working, groyne construction and all other works; viii) Measures to prevent pollution to ground and surface waters; ix) Health and safety details and precautions including emergency strategy; x) Mitigation proposals for the minimal disturbance of silt during the in-river works, including a risk assessment of alternative measures. xi) A scheme for the treatment and control of Japanese knotweed. xii) Timescales for all the above. The works shall be undertaken in accordance with the approved details unless otherwise agreed in writing in advance by the local planning authority. Reason: To ensure a satisfactory form of development in accordance with agreed principles, to ensure public safety during the operations, to ensure a design solution is sought to minimise archaeological disturbance, and to protect the amenity of the area in accordance with policies S1, S2, DR1, ARCH5, ARCH6, NC2 & NC3 and LA1 of the Herefordshire Unitary Development Plan 2007. Restoration Scheme 4 No development shall take place until a reinstatement and restoration scheme for the completion of the project has been submitted to ... view the full minutes text for item 154.