THAT: (i) progress made in delivering the Comprehensive Area Assessment Preparation Programme over the first six months of 2008 be noted; and (ii) Cabinet agree the need for effective remedial action for the items marked amber listed in paragraph three of the report.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
COMPREHENSIVE AREA ASSESSMENT PREPARATION PROGRAMME PROGRESS REPORT PORTFOLIO RESPONSIBILITY: CORPORATE, CUSTOMER SERVICES AND HUMAN RESOURCES
CABINET 31 JULY 2008
Wards Affected County-wide
Purpose To report progress against the Comprehensive Area Assessment Preparation Programme.
Key Decision This is not a Key Decision
Recommendations THAT
i. progress made in delivering the Comprehensive Area Assessment Preparation Programme over the first 6 months of 2008 be noted; and
ii. Cabinet agrees the need for effective remedial action for the items marked Amber, which are listed in paragraph 3.
Reasons The Council’s current Corporate Plan sets out the Council’s objectives, priorities and targets for the three years 2007-10. The Annual Operating Plan (AOP) is the detailed action plan for the first of these years, 2007-08; it includes all the indicators in the Local Public Service Agreement (LPSA), the Local Area Agreement (LAA) and the Herefordshire Community Strategy (HCS), as well as the Council’s own indicators.
Considerations 1. The Comprehensive Area Assessment Preparation Programme (Appendix 1) is currently being implemented. Judgement has been made against those actions timetabled for completion during the first 6 months of the year on the following basis:
Further information on the subject of this report is available from Tony Geeson, Head of Policy and Performance on 01432 261855 • Green signifies that the action has been achieved; • Amber signifies that the action is delayed or there is other cause for concern; if remedial action is taken it should be achieved although not necessarily on the original timescale; and • Red signifies that the action has not been achieved or is not expected to be achieved
2. The majority of actions required to have been delivered thus far have either been achieved and marked Green, or are currently on track and marked Amber. There are no Reds.
3. Those actions currently marked Amber are:
• 1.3 Identify changes needed to data collection and analysis to provide reliable, regular data, e.g. single, shared client data-bases, setting a prioritised timetable for each element; • 3.2 Action plan for the Sustainable Community Strategy (SCS), including the new LAA; • 4.1 Integrated planning and performance improvement cycle between the Council, the PCT and the Herefordshire Partnership; • 4.10 Review ICT requirements to deliver this programme; • 4.12 Establish strengthened scrutiny arrangements that will make a major contribution to planning and performance management across the Council/PCT and the Herefordshire Partnership; • 4.14 Council and PCT workforce development strategy to deliver the programme; • 4.15 Annual training and development programme for the Council, PCT and partner organisations to help deliver the programme; • 4.16 Corporate, directorate and service induction to include the core objectives and themes of the programme, relating them to each individual’s role and responsibilities; • 4.17 Programme to develop understanding for the roll-out of the strategic risk identification and management process; • 5.1 Establish shared strategic risk identification and management process for the Council, the PCT and their partners, integrated with performance management systems and reporting; • 6.4 Action plan for prioritised improvements in partners’ indicator performance and other factors relevant to the Direction of Travel assessment to improve the rating in February 2010; • 7.5 Rationalisation of back-office accommodation; and • 8.1 Communications strategy and action plan designed and rolled out.
4. Confirmation of the new CAA framework will be published towards the end of July, together with consultation on its detailed operation. Whatever the details, the Council’s and Partnership’s success depends on their being able to evidence continuous improvement and the robustness of plans for further improvement.
Alternative Options None.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.