RESOLVED THAT: (a) Herefordshire Connects be re-focused on implementing the three updated business cases and further developing these business cases jointly with the PCT as Herefordshire Public Services partners, as defined in section 5.3 of the report attached; (b) Cabinet note the critical risks to service continuity of key ICT system failures. This is due to the current large number of inadequately connected systems requiring upgrades that would not achieve the Council’s ambitions for improving customer services and satisfaction, provide poor value for money or that are no longer supported by providers due to their age; (c) the Council’s ICT system application portfolio be rationalised to achieve the minimum number of integrated applications by Joint Management Team and Deloitte conducting a two month evaluation of: (i) the four market proven system providers for an integrated ... view the full minutes text for item 35.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
HEREFORDSHIRE CONNECTS OPTION APPRAISAL PORTFOLIO RESPONSIBILITY: ICT EDUCATION AND ACHIEVEMENT / CORPORATE AND CUSTOMER SERVICES AND HUMAN RESOURCES CABINET 31 JULY 2008
Wards Affected County-wide
Purpose To seek approval of recommendations arising from an Options Appraisal of Herefordshire Connects to determine the future focus, purpose and outcomes for the Council’s development of Information and Communications Technology (ICT) systems required to achieve cost effective, service improvements for customers, in partnership with Herefordshire Primary Care Trust (PCT).
Key Decision This is a Key Decision because it is likely to be significant in terms of its effect on communities living or working in Herefordshire in an area comprising one or more wards.
It was included in the Forward Plan.
Recommendations THAT:
(a) Herefordshire Connects be re-focused on implementing the three updated business cases and further developing these business cases jointly with the PCT as Herefordshire Public Services partners, as defined in section 5.3 of the report attached;
(b) Cabinet note the critical risks to service continuity of key ICT system failures. This is due to the current large number of inadequately connected systems requiring upgrades that would not achieve the Council’s ambitions for improving customer services and satisfaction, provide poor value for money or that are no longer supported by providers due to their age;
(c) The Council’s ICT system application portfolio be rationalised to achieve the minimum number of integrated applications by Joint Management Team and Deloitte conducting a two month evaluation of:
a. the four market proven system providers for an integrated back office system and associated integration tools to enable
Further information on the subject of this report is available from Andrew Williams, Interim Deputy Chief Executive on (01432) 260037
FinalConnectscabinetreport2107080.doc integration between Council systems and where jointly approved, Council and PCT systems, as stated in Section 6.4 of the report attached;
b. the two market proven system providers for an integrated environment and planning system, as stated in Section 6.4 of the report attached;
c. market proven system providers for an integrated performance management system, as stated in Section 6.4 of the report attached;
(d) A report on the recommendations arising from (c) above be produced for the Cabinet in October 2008;
(e) The Customer Relationship Management System Upgrade should proceed to secure the significant increase in system efficiency and customer service standards. Deloitte advise this upgrade is already delivering these for other Council users of this system;
(f) The current Finance System Upgrade should proceed; which will address imminent service continuity risks
(g) The Joint Management Team implement Connects Programme Management arrangements based on Section 8 of the report attached to provide assurance to the Council, and where relevant PCT, of compliance with the applicable Procurement Policies and best practice in the Project Management risks, costs and the realisation of benefits for customers and staff.
Reasons 1 The Audit Commission has been maintaining an overview of the council’s progress with Herefordshire Connects, and in its Annual Audit & Inspection Letter recommended that before progressing further elements the council take the opportunity “.to re-focus and clarify the purpose, outcomes and actions of Herefordshire Connects. This should include formally considering in a short paper what other options are still open to the council including the costs, benefits and risks of each option. It should also set out how the programme fits with the new joint working arrangements with the Primary Care Trust.”
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.