Environment Scrutiny Committee noted this item on Monday 8 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
That the capital budget report be noted .
ENVIRONMENT SCRUTINY COMMITTEE 8 JUNE 2009
CAPITAL BUDGET MONITORING Report By: DIRECTOR OF RESOURCES
Wards Affected County-wide
Purpose 1. To advise Scrutiny Committee on the final outturn position for the 2008/09 Environment Capital Programme and the proposed Environment Capital Programme for 2009/10.
Summary 2. The final outturn for the 2008/09 Environment Capital Programme was £18.7 million and the current budget for 2009/10 is £16.8 million.
3. The Environment Capital Working Group meets regularly and keeps overall spending position under careful review.
Financial Implications Capital Outturn 2008/09
4. The final outturn position for the Environment Capital Programme is shown in Appendix 1, on scheme basis with funding arrangements indicated in overall terms.
5. The total of the Capital Programme reduced to £18,687,000 from the figure of £21,056,000 previously reported to this committee. This is a net underspend of £2,369,000 and the main variances were:
i) A net underspend of £277,000 on Local Transport Plan (LTP) schemes representing 2% of the total forecast spend of £13.2 million on LTP schemes for 2008/09.
ii) Hereford Transport Strategy scheme includes £248,000 underspend compared to the budget for the year on Rotherwas Access Road scheme in relation to compensation payments not yet finalised. Rotherwas Access Road opened to traffic at the beginning of June 2008 and became the main route into the Estate for vehicles over 7.5 tonnes following the introduction of the traffic order on Holme Lacy Road later in the year. Important cycle infrastructure schemes at Yazor Road and Holmer Road have been delivered this financial year with the remaining sections of the Holmer Road scheme (which links the north of Hereford City to the Great Western Way) planned over the next three financial years. A significant programme of disabled and pedestrian improvements was also implemented this year – notably disables access improvements on footways along Whitecross Road that have been welcomed by ‘Hereford Access for All’ group.
iii) Rural Herefordshire Transport Strategy schemes underspend includes slippage on the Shaw Cycleway scheme and Symonds Yat Boat maintenance scheme. The Shaw Cycleway scheme was delayed due to planning constraints whilst the Symonds Yat works were delayed by the requirement for further design work as a
Further information on the subject of this report is available from Cathy Stokes, Principal Accountant (Environment & Regeneration) on 01432 261849 ENVIRONMENT SCRUTINY COMMITTEE 8 JUNE 2009
result of the additional land slippage caused by the 2008 floods. Both of these schemes are programmed for delivery in 2009/10. A significant programme of disabled and pedestrian improvements was delivered in market towns and rural location whilst the design of Shaw cycleway and Symonds Yat maintenance schemes were completed ready for implementation in 09/10. The high priority rural footway scheme at Clehonger was also completed during the year.
iv) Venns Lane improvement scheme, funded through s106 agreement, included within the Road Safety Strategy schemes has been delayed to enable further consultation which is scheduled to take place in the summer of 2009.
v) Additional Highways maintenance schemes on roads and footways have been completed in the year resulting in additional spend of £220,000. This reflects the response to two flood events in the autumn of 2008 and a programme of repair works as a result of the damage caused by the floods and extreme weather.
vi) An underspend of £1.875 million against the 2008/09 forecast in relation to Ross Flood Alleviation Scheme. This reflects the pain/gain requirement against the contractor under the contract for the scheme. Costs to date total £10.5 million before the pain/gain claim and Environment Agency have currently agreed funding up to £11.04 million.
vii) Slippage in the closed landfill site schemes at Leominster of £106,000 and Strangford of £77,000 sites which will be completed in 2009/10.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget MonitoringReport | 67 KB | DownloadRead as text |
PDF |
Capital Report Jun 09 Appendix 1Appendix | 70 KB | Download |
PDF |
Capital Report Jun 09 Appendix 2Appendix | 62 KB | Download |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.