CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Herefordshire Council
Environment Scrutiny Committee, Monday 14 September 2009 at 9.30am

Capital Budget Monitoring

Noted Scrutiny 2 papers

Environment Scrutiny Committee noted this item on Monday 14 September 2009. Below is the council's own wording, with the papers it was decided on.

Item23

Resolved

That the Capital Budget report be noted.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Environment Scrutiny Committee

ENVIRONMENT SCRUTINY COMMITTEE 14th September 2009

CAPITAL BUDGET MONITORING Report By: DIRECTOR OF RESOURCES

Wards Affected County-wide

Purpose 1. To advise Scrutiny Committee on progress of the 2009/10 Environment Capital Programme within the overall context of the Council’s Capital Programme.

Summary 2. This report is largely based on the latest round of capital monitoring, which involved the examination of all schemes at the end of July 2009. The Environment Capital Working Group is keeping the overall spending position under careful review.

3. The total spent and committed at 31st July 2009 is £7.585 million or 45.3% of the Revised Forecast. The actual amount spent to date is £3.042 million.

Financial Implications 4. The Capital budgets for Environment for 2009/10 are shown in summary on Appendix 1, on scheme basis with funding arrangements indicated in overall terms.

5. The total of the Capital Programme reduced to £16,755,000 from the figure of £17,574,000 previously reported to this committee. This is a net reduction of £819,000 and the main variances are:

i) £1.46 million has been received in relation to Growth Point funding from central government as part of its commitment to increasing housing supply. This capital grant was awarded following a bid for expenditure to implement the Park & Ride scheme (North) but is not ring fenced. The Park & Ride scheme (North) is not expected to incur this expenditure in the current financial year so the 2009/10 Capital Programme has reduced to reflect this. This funding will be included in future years Capital Programmes.

ii) An additional £30,000 in relation to Hereford Crematorium scheme and relates to additional slippage in the 2008/09 Programme.

iii) There is an addition of £384,000 in relation to the Connect 2 scheme. This is due to realigning the total scheme budget to reflect the expected expenditure in 2009/10.

iv) Additional grant funding in relation to 2009/10 of £113,000 from Department of Transport to assist the Council in building up its highways asset inventory and analysis capability. This work is necessary to support changes in accounting guidelines for highways assets which will be incorporated into the 2011/12 accounts.

Further information on the subject of this report is available from Cathy Stokes, Principal Accountant (Environment & Regeneration) on 01432 261849 ENVIRONMENT SCRUTINY COMMITTEE 14th September 2009

v) There are two additional schemes in relation to Relocation of the Hereford Open Retail Market of £58,500 and Butter Market refurbishment consultation of £50,000. These schemes were approved through the annual capital bidding process and are funded through prudential borrowing.

vi) There is an addition of £44,000 in relation to capital grant funding from the Home Office to support the Safer and Stronger Communities initiative.

vii) A reduction of £39,000 in relation to align section 106 monies to schemes expected to be delivered in 2009/10.

RECOMMENDATION THAT subject to any comments the Committee may wish to make the report be noted.

BACKGROUND PAPERS • None identified

APPENDIX Appendix 1 – Summary Environment Capital Programme Budget 2009/10

Further information on the subject of this report is available from Cathy Stokes, Principal Accountant (Environment & Regeneration) on 01432 261849

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget MonitoringReport 62 KB DownloadRead as text
PDF
Environment Capital Report Sep 09 Appendix 1Appendix 70 KB Download

At this meeting

Whole meeting

Who was there

11 of 17 attended
PA
Councillor Polly AndrewsIn Attendance, in attendance
CB
Councillor CM BartrumMember, present
SB
Councillor Sebastian BowenMember, present
PE
Councillor PJ EdwardsIn Attendance, in attendance
DG
Councillor DW GreenowMember, present
KG
Councillor KG GrumbleyMember, present as substitute
JH
Councillor JW Hope MBEMember, present
MH
Councillor MAF HubbardMember, present
TH
Councillor TW HuntMember, present
PJ
Paul JamesSecretary, expected
JJ
Councillor JG JarvisIn Attendance, in attendance
BM
Cllr Bob MatthewsChairperson, present

All 17 on the meeting page

On this subject at Herefordshire

Search all
  1. Capital Budget MonitoringThis decision
  2. 2026/27 capital investment budget and capital strategy updateApproved
  3. 2025/26 capital investment budget and capital strategy updateApproved
  4. Addition of capital budget to deliver it capital programmeApproved
  5. Addition of capital budget to provide an acquisition fund for housing provisionApproved
  6. 2024/25 capital investment budget and capital strategy updateApproved

More from Herefordshire Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
28 Feb 2011 MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... Decided Open
28 Feb 2011 Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... Noted Open
28 Feb 2011 Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... Decided Open
28 Feb 2011 Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. Noted Open
28 Feb 2011 Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies