Resolved
That (a) the Committee noted the content of the Capital Monitoring report and approved the format of the information. (b) The Committee be informed by briefing note of the terms and intended location of schemes under the Playbuilder grant.
Children's Services Scrutiny Committee noted this item on Monday 28 September 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
That (a) the Committee noted the content of the Capital Monitoring report and approved the format of the information. (b) The Committee be informed by briefing note of the terms and intended location of schemes under the Playbuilder grant.
MEETING: CHILDREN’S SERVICES SCRUTINY COMMITTEE
DATE: 28 SEPTEMBER 2009
TITLE OF REPORT: CAPITAL BUDGET REPORT 2009/2010
PORTFOLIO AREA: CHILDREN’S SERVICES AND ICT, ACHIEVEMENT & EDUCATION CLASSIFICATION: Open – Wards Affected County-wide
Purpose To scrutinise the capital budget position for 2009/10 for the Children & Young People’s Directorate.
Key Decision This is not a Key Decision.
Recommendation(s) THAT Committee note and comment on the report as part of its scrutiny function.
Key Points Summary • With the exception of previously reported delays with the delivery of The Riverside School and the Holmer Flood Alleviation Scheme, the capital programme is being delivered on time and to budget.
Alternative Options 1 This report is a monitoring report. There are alternatives in terms of the format if Scrutiny Committee wishes to have information presented in a different way.
Reasons for Recommendations 2 Monitoring report
Introduction and Background 3 This report provides a summary of the planned capital expenditure for the Children & Young People’s Directorate in 2009/2010.
Further information on the subject of this report is available from Rob Reid, Head of Access & Capital Commissioning on (01432) 260920
CapitalBudgetReport0.doc Planned capital expenditure for 2009/10 is around £30 million.
Key Considerations 4. Update on capital schemes for 2009/10
4.1The Minster College – Building Schools for the Future One School Pathfinder - 21,000,000 (£7,201,349 to be spent in 2009/10)
This scheme continues to progress well and is on schedule to complete in the summer 2010. While the new school has been designed to accommodate the upper end of possible future student numbers within the catchment area and, in time, from new housing, the school will have significant spare capacity when it opens. The Local Authority continues to work with the headteacher and governors to mitigate this. An area of surplus capacity is being developed to accommodate a multi agency integrated children’s services team within the new building.
4.2The Hereford Academy - £23,000,000 (£9,066,000 to be spent in 2009/10)
Planning permission for the new build has been approved. At the time of writing this report, approval of the final business case by Partnerships for Schools is imminent. This will release the funding for the project and Willmott Dixon Construction will then commence work immediately. The scheme is within budget and the new buildings are due to complete in the spring of 2011. Students and staff will then move into the new buildings, allowing for the existing buildings to be demolished and the final external areas to be landscaped. The whole scheme is due to complete in the autumn of 2011.
4.3Primary Capital Programme - £3,000,000 (2009/10) + £5,378,000 (2010/11)
This is the national Government fourteen year funding programme for major investment in primary schools and primary age special schools. Herefordshire will receive its first year’s allocation of £3,000,000 this financial year and £5,378,000 in 2010/11, giving a total of £8,378,000 over the two financial years. Funding amounts beyond this have not yet been announced by Government.
Cabinet has committed £7,378,000 of the first two year’s funding to the building of a new all through primary school in Leominster, to replace the current Leominster Infant and Leominster Junior schools. A Project Team has been formed, comprising of the headteachers and governor representatives of the current schools and Local Authority Children’s Services, Property Services and Human Resources officers, to deliver the new build school and to carry out the statutory school reorganisation process to establish the new school. Amey will provide the consultant architect and design service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Report 2009/2010Report | 111 KB | DownloadRead as text |
Follow Children's Services Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2011 | MINUTESThat the Minutes of the meeting held on 10 December 2010 were approved as a correct record and signed by the Chairman. | Approved | Open |
| 11 Mar 2011 | Suggestions from members of the public on issues for future scrutinyThat Nursery Education Funding (NEF) and the Future of Peripatetic Music Teaching be logged in the work programme as ... | Decided | Open |
| 11 Mar 2011 | Report on the results on the consultation on priorities for the Children and Young People's Plan 2011 - 2014That the position set out in the report be noted and a further update report be logged for consideration as part of t... | Noted | Open |
| 11 Mar 2011 | Performance Digest Quarter 3 2010/11That a) the performance indicated in the report and Performance Digest be noted and future reports to include progres... | Noted | Open |
| 11 Mar 2011 | Children and Young People Directorate ReorganisationThat a) the report be noted and a further report be logged in the work programme so that progress with the Frameworki... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.