That the monitoring report be noted and; the out come of the Riverside Primary School Performance Bond negotiations be communicated to Members; and A Member briefing note be provided clarifying the Riverside Primary School financing position, particularly in respect of financing the project, the land disposal and disposal of the portacabins
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
TITLE OF REPORT: CAPITAL BUDGET MONITORING REPORT 2009/2010
PORTFOLIO AREA: CHILDREN & YOUNG PEOPLE’S DIRECTORATE CLASSIFICATION: Open Wards Affected County-wide
Purpose To report the capital budget position for 2009/10 for the Children & Young People’s Directorate.
Recommendation THAT Committee note and comment on the report as part of its scrutiny function.
Key Points Summary • The report contains updates on all major funding streams and capital developments. All are broadly on budget and to timescales.
• Riverside Primary School is now open, and work is underway on phase 2 of the scheme to complete the external areas. In February 2007, Cabinet considered a funding shortfall on the schemes to replace Riverside Primary School and Sutton Primary School. Cabinet agreed that the funding shortfall on both schemes should be met from a combination of Government grant, available to the Local Authority for modernisation of school buildings; a reduction to the scope of both schemes; and the use of capital receipts. Officers are pursuing the disposal of part of the Riverside Primary School site to realise the required capital receipt. The school and community are aware of this planned disposal.
In addition, officers are negotiating with insurers over the release of funding from a Performance Bond which was put in place at the start of the scheme to mitigate against the potential costs of the developer being unable to deliver the scheme. Since the original contractor went into administration, officers are seeking to reclaim, from the Performance Bond insurers, the additional costs incurred by the Local Authority.
Further information on the subject of this report is available from Rob Reid, Head of Access & Capital Commissioning on (01432) 260920
CapitalBudgetReportMarch20100.doc 26Nov08 Alternative Options 1 This report is a monitoring report. There are alternatives in terms of the format if Scrutiny Committee wishes to have information presented in a different way.
Reasons for Recommendations 2 Monitoring report
Introduction and Background 3 This report provides a summary of the planned capital expenditure for the Children & Young People’s Directorate in 2009/2010.
Planned capital expenditure for 2009/10 is around £30 million.
Key Considerations 4. Update on capital schemes for 2009/10
4.1The Minster College – Building Schools for the Future One School Pathfinder - £21,000,000 (£12,201,349 to be spent in 2009/10)
This scheme continues to progress well and is on schedule to complete in the summer 2010. While the new school has been designed to accommodate the upper end of possible future student numbers within the catchment area and, in time, from new housing, the school will have significant spare capacity when it opens. The Local Authority continues to work with the headteacher and governors to mitigate this. An area of surplus capacity is being developed to accommodate a multi agency integrated children’s services team within the new building and other accommodation is being adapted to provide a facility for alternative provision (see paragraph 4.7).
4.2The Hereford Academy - £23,923,712 (£5,090,000 to be spent in 2009/10)
This scheme programme has experienced some slippage during the ground works stage due to snow and ice, but there has also been a 3 weeks delay as a result of the grounds work contractor, appointed by Willmott Dixon Construction, ceasing trading. A new grounds work contractor has been appointed and is now on site. Under the National Academies Framework, additional costs in respect of this are borne by the main contractor, Willmott Dixon Construction and not the Local Authority. Officers are working with The Academy Trustees and the contractor to mitigate the affect on the programme.
4.3Primary Capital Programme - £3,000,000 (2009/10) + £5,378,000 (2010/11)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
Performance Digest Quarter 3 2010/11That a) the performance indicated in the report and Performance Digest be noted and future reports to include progres...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.