Resolved
That the Capital Budget monitoring report be noted.
Environment Scrutiny Committee noted this item on Monday 28 June 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Capital Budget monitoring report be noted.
MEETING: ENVIRONMENT SCRUTINY COMMITTEE
DATE: 28 JUNE 2010
TITLE OF REPORT: CAPITAL BUDGET MONITORING
REPORT BY: DIRECTOR OF RESOURCES
Wards Affected County-wide
Purpose To advise members on the Scrutiny Committee of the final outturn position for the 2009/10 Environment Capital Programme within the overall context of the Council’s Capital Programme and the proposed Environment Capital Programme for 2010/11.
Recommendation THAT the report be noted. Introduction and Background 1 The final outturn for the 2009/10 Environment Programme was £17.4 million and the current budget for 2010/11 is £18.5 million.
2 The Environment Capital Working Group meets regularly and keeps overall spending position under careful review.
Key Considerations Capital Budget 2009/10
3 The final outturn position for the Environment Capital Programme is shown in Appendix 1, on scheme basis with funding arrangements indicated in overall terms.
4 The total of the Environment Capital Programme increased to £17,387k from the figure of £15,764k previously reported to this committee. This is a net increase of £1,623k relates to the following main variances:
a. There is a net underspend of £273k on Local Transport Plan (LTP) schemes representing 2% of the total forecast spend of £12,043k on LTP Schemes for 2009/10.
Further information on the subject of this report is available from Cathy Stokes, Principal Accountant on (01432) 261849 b. The main underspend on LTP schemes relates Herefordshire Council’s contribution to Network Rail towards the replacement costs of the Colwall Green Railway Bridge. Works carried out by the end of 2009/10 were initially estimated at £750k however the final provision for payment on account received in March 2010 was only £500k.
c. A final outturn valuation of £2,320k has been added to the Capital Programme for the Ross Flood Alleviation Scheme, this reflects the costs incurred in 2009/10 and are fully funded by the Environment Agency.
d. There was an increase in spend of £101k on the Rotherwas Access Road scheme relating to the settlement of compensation payments. This is funded through prudential borrowing.
e. A reduction of £243k due to slippage in the Closed Landfill Site at Leominster, we are awaiting guidance on the approach from the Environment Agency. Proposed work to install the remainder of the leachate perimeter drain will be carried out in 2010/11 subject to this agreement.
f. A reduction of £205k in relation to schemes funded from s106 contributions, which will now be delivered in future years.
Capital Budget 2010/11
5 The proposed Capital Programme for 2010/11 is attached in Appendix 2. This has been increased to £18,476k from the original budget included in the Medium Term Financial Management Strategy of £14,844. This increase of £3,632k relates to:
a. A reduction of £92k in relation to Rotherwas Access Road. This reflects accelerated payment in relation to compensation events made in 2009/10.
b. In March 2010, Department of Transport announced that a budget of £100m was being made available to assist local authorities repair damage to their roads caused by the severe weather conditions in January 2010. Herefordshire Council expect to receive £1,017k grant for Emergency Fund Winter Damage in 2010/11. This has been added to the 2010/11 Capital Programme for roads maintenance, meaning an annual budget of £11.6 million.
c. An increase of £1m in relation Growth Point funding from central government as part of its commitment to increasing housing supply. This capital grant was awarded following a bid for expenditure on Hereford Transport Infrastructure schemes.
d. An increase of £891k in relation to the Widemarsh Street Refurbishment scheme. This reflects the works expected to be completed in 2010/11. Works commenced at the end of February and are expected to be complete in November 2010. Total scheme cost is estimated at £1.4million.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget MonitoringReport | 88 KB | DownloadRead as text |
PDF |
Capital Report Appendix 2Appendix | 58 KB | Download |
PDF |
Envt Capital Report Appendix 1Appendix | 60 KB | Download |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.