Capital Budget Monitoring Report 2010/1011

Noted Scrutiny 1 paper

Children's Services Scrutiny Committee noted this item on Friday 1 October 2010. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

that the position set out in the Capital Budget Monitoring report be noted.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Children's Services Scrutiny Committee

MEETING: CHILDREN’S SERVICES SCRUTINY COMMITTEE

DATE: 1 OCTOBER 2010

TITLE OF REPORT: CAPITAL BUDGET MONITORING REPORT 2010/2011

PORTFOLIO AREA: CHILDREN & YOUNG PEOPLE’S DIRECTORATE CLASSIFICATION: Open Wards Affected County-wide

Purpose To scrutinise the capital budget position for 2010/11 for the Children & Young People’s Directorate.

Key Decision This is not a Key Decision.

Recommendation THAT Committee note and comment on the report as part of its scrutiny function.

Key Points Summary • A reduction in some capital grants, following central Government announcements of funding cuts, has resulted in capital schemes and grants being halted or reduced in scope.

• Riverside Primary School – options to meet the funding gap caused by the original contractor going into liquidation.

• Other than for urgent health and safety work, the planned capital maintenance programme has been halted due to significant expenditure needing to be incurred on urgent and essential work to remove or clean up asbestos and also to replace pipe work to Low Propane Gas (LPG) tanks in response to Health & Safety Executive advice.

Alternative Options 1 This is a monitoring report. There are alternatives in terms of the format if Scrutiny Committee wishes to have information presented in a different way.

Further information on the subject of this report is available from Rob Reid, Head of Access & Capital Commissioning on (01432) 260920 Reasons for Recommendations 2 Monitoring report.

Introduction and Background

3 As requested at the meeting of the Children’s Services Scrutiny Committee on 14 June 2010, this is an exception report on the key areas of progress, achievement and challenge within the capital programme for 2010/11. Planned capital expenditure for 2010/11 is £31,739,000.

Key Considerations

4.1Reductions in grant income following central Government announcements of funding cuts:

• Schools’ Harnessing Technology grant has been reduced by 50% to £543k.

• SEN/14-19 Targeted Capital grant has been reduced by £660k to £7,340k

• Early Years grants for Children’s Centres and improvements to the quality of and access to private, voluntary and independent sector early years provision, has been reduced by £530k to £1,225k. This will result in rethinking how children’s centres services can be provided in the north Hereford City area and it will reduce the Local Authority’s ability to provide early years settings in the private, voluntary and independent sector with grants to improve quality and access to provision.

• Playbuilder –. This capital grant was unringfenced in June. The Local Authority was to receive £607k, but this is likely to be reduced and the Local Authority is waiting for the Government to confirm exactly what the 2010/11 grant will be. In July, the Local Authority submitted to the Government details of 11 play schemes that we have been developing with community groups across Herefordshire. All of these schemes are on hold until the exact amount of funding is announced by the Government. Even then, as whatever grant we get will be unringfenced, the Herefordshire Partnership will need to determine whether the funding should still be used for the Playbuilder schemes.

4.2Riverside Primary School

As reported to the Committee previously, the scheme has incurred extra costs, predominantly as a direct consequence of the original contractor going into liquidation and a new contractor having to be taken on to complete the scheme:

Direct additional contractor costs due to the original contractor going into £1,012,000 liquidation

Vacant site security £88,000

Remedial works required to original contractors work £117,000

Additional ICT costs £104,000 Additional professional fees connected with receivership work – re- £511,000 measuring work required for new contractor tender specifications, production of new tenders and variations to the scheme. It is therefore possible that this figure will reduce as Asset Management and Property Services is in discussion with AMEY Consulting..

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring Report 2010/1011Report 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 23 attended
MC
Councillor ME CooperVice-Chairperson, present
PE
Councillor PJ EdwardsMember, present as substitute
AJ
Councillor AW JohnsonMember, present
BP
Councillor Brig P Jones CBEMember, present
GL
Councillor G LucasMember, present
JP
Councillor JE PembertonMember, present
SR
Councillor SJ RobertsonMember, present
RS
Councillor RV StocktonMember, apologies, sent representative
AT
Councillor AM ToonMember, present
WW
Councillor WJ WallingMember, present
JW
Councillor JD WoodwardMember, present
PB
Mr PF BurbidgeMember, present

All 23 on the meeting page

On this subject at Herefordshire

Search all
  1. Capital Budget Monitoring Report 2010/1011This decision
  2. 2026/27 capital investment budget and capital strategy updateApproved
  3. 2025/26 capital investment budget and capital strategy updateApproved
  4. Addition of capital budget to deliver it capital programmeApproved
  5. Addition of capital budget to provide an acquisition fund for housing provisionApproved
  6. 2024/25 capital investment budget and capital strategy updateApproved

More from Herefordshire Children's Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2011 MINUTESThat the Minutes of the meeting held on 10 December 2010 were approved as a correct record and signed by the Chairman. Approved Open
11 Mar 2011 Suggestions from members of the public on issues for future scrutinyThat Nursery Education Funding (NEF) and the Future of Peripatetic Music Teaching be logged in the work programme as ... Decided Open
11 Mar 2011 Report on the results on the consultation on priorities for the Children and Young People's Plan 2011 - 2014That the position set out in the report be noted and a further update report be logged for consideration as part of t... Noted Open
11 Mar 2011 Performance Digest Quarter 3 2010/11That a) the performance indicated in the report and Performance Digest be noted and future reports to include progres... Noted Open
11 Mar 2011 Children and Young People Directorate ReorganisationThat a) the report be noted and a further report be logged in the work programme so that progress with the Frameworki... Noted Open