Resolved
that the position set out in the Capital Budget Monitoring report be noted.
Children's Services Scrutiny Committee noted this item on Friday 1 October 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
that the position set out in the Capital Budget Monitoring report be noted.
MEETING: CHILDREN’S SERVICES SCRUTINY COMMITTEE
DATE: 1 OCTOBER 2010
TITLE OF REPORT: CAPITAL BUDGET MONITORING REPORT 2010/2011
PORTFOLIO AREA: CHILDREN & YOUNG PEOPLE’S DIRECTORATE CLASSIFICATION: Open Wards Affected County-wide
Purpose To scrutinise the capital budget position for 2010/11 for the Children & Young People’s Directorate.
Key Decision This is not a Key Decision.
Recommendation THAT Committee note and comment on the report as part of its scrutiny function.
Key Points Summary • A reduction in some capital grants, following central Government announcements of funding cuts, has resulted in capital schemes and grants being halted or reduced in scope.
• Riverside Primary School – options to meet the funding gap caused by the original contractor going into liquidation.
• Other than for urgent health and safety work, the planned capital maintenance programme has been halted due to significant expenditure needing to be incurred on urgent and essential work to remove or clean up asbestos and also to replace pipe work to Low Propane Gas (LPG) tanks in response to Health & Safety Executive advice.
Alternative Options 1 This is a monitoring report. There are alternatives in terms of the format if Scrutiny Committee wishes to have information presented in a different way.
Further information on the subject of this report is available from Rob Reid, Head of Access & Capital Commissioning on (01432) 260920 Reasons for Recommendations 2 Monitoring report.
Introduction and Background
3 As requested at the meeting of the Children’s Services Scrutiny Committee on 14 June 2010, this is an exception report on the key areas of progress, achievement and challenge within the capital programme for 2010/11. Planned capital expenditure for 2010/11 is £31,739,000.
Key Considerations
4.1Reductions in grant income following central Government announcements of funding cuts:
• Schools’ Harnessing Technology grant has been reduced by 50% to £543k.
• SEN/14-19 Targeted Capital grant has been reduced by £660k to £7,340k
• Early Years grants for Children’s Centres and improvements to the quality of and access to private, voluntary and independent sector early years provision, has been reduced by £530k to £1,225k. This will result in rethinking how children’s centres services can be provided in the north Hereford City area and it will reduce the Local Authority’s ability to provide early years settings in the private, voluntary and independent sector with grants to improve quality and access to provision.
• Playbuilder –. This capital grant was unringfenced in June. The Local Authority was to receive £607k, but this is likely to be reduced and the Local Authority is waiting for the Government to confirm exactly what the 2010/11 grant will be. In July, the Local Authority submitted to the Government details of 11 play schemes that we have been developing with community groups across Herefordshire. All of these schemes are on hold until the exact amount of funding is announced by the Government. Even then, as whatever grant we get will be unringfenced, the Herefordshire Partnership will need to determine whether the funding should still be used for the Playbuilder schemes.
4.2Riverside Primary School
As reported to the Committee previously, the scheme has incurred extra costs, predominantly as a direct consequence of the original contractor going into liquidation and a new contractor having to be taken on to complete the scheme:
Direct additional contractor costs due to the original contractor going into £1,012,000 liquidation
Vacant site security £88,000
Remedial works required to original contractors work £117,000
Additional ICT costs £104,000 Additional professional fees connected with receivership work – re- £511,000 measuring work required for new contractor tender specifications, production of new tenders and variations to the scheme. It is therefore possible that this figure will reduce as Asset Management and Property Services is in discussion with AMEY Consulting..
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Budget Monitoring Report 2010/1011Report | 93 KB | DownloadRead as text |
Follow Children's Services Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2011 | MINUTESThat the Minutes of the meeting held on 10 December 2010 were approved as a correct record and signed by the Chairman. | Approved | Open |
| 11 Mar 2011 | Suggestions from members of the public on issues for future scrutinyThat Nursery Education Funding (NEF) and the Future of Peripatetic Music Teaching be logged in the work programme as ... | Decided | Open |
| 11 Mar 2011 | Report on the results on the consultation on priorities for the Children and Young People's Plan 2011 - 2014That the position set out in the report be noted and a further update report be logged for consideration as part of t... | Noted | Open |
| 11 Mar 2011 | Performance Digest Quarter 3 2010/11That a) the performance indicated in the report and Performance Digest be noted and future reports to include progres... | Noted | Open |
| 11 Mar 2011 | Children and Young People Directorate ReorganisationThat a) the report be noted and a further report be logged in the work programme so that progress with the Frameworki... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.