Audit and Governance Committee noted this item on Monday 17 January 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
MEETING: AUDIT AND GOVERNANCE COMMITTEE
DATE: 17 JANUARY 2011
TITLE OF REPORT: INTERIM AUDIT SERVICES ASSURANCE REPORT 2010/11 NO.3
PORTFOLIO AREA: RESOURCES CLASSIFICATION: Open Wards Affected County-wide
Purpose The purpose of the Interim Assurance Report is to update members on the current status of control issues and bring to their attention any key internal control issues.
Key Decision This is not a Key Decision.
Recommendation THAT the report be noted.
Key Points Summary • Seven key issues were identified in the Council’s Annual Governance Statement. Four have been closed. (Appendix 1 refers).
• Subject to Committee agreement there are currently four Committee Resolutions that are open (Appendix 2 refers);
• Of the audits completed two were given an unsatisfactory audit opinion and one a marginal opinion ( Appendix 3 refers)
Alternative Options 1 This report is for information therefore alternative options are not applicable.
Reasons for Recommendations 2 To ensure compliance with good practice as set out in the CIPFA Code of Practice for Internal Audit in Local Government in the United Kingdom.
Further information on the subject of this report is available from Tony Ford Chief Internal Auditor on (01432) 260425
$ymcoayw5.doc 26Nov08 Introduction and Background 3 To ensure that the Committee is informed of progress on the Audit Plan and any key internal control issues identified.
Key Considerations Key Issues Identified in 2009/10
4 The Audit and Governance Committee considered the Annual Assurance report for the year ending 31st March 2010 on 29th June 2009. In addition the Committee reviewed and adopted the Annual Governance Statement. The key issues identified for improvement are set out in Appendix 1 along with the comments of the lead officer regarding the current position. Four key issues have been closed.
Audit and Corporate Governance Committee Resolutions
5 Regarding resolutions made by the Committee to November 2010 (Appendix 2 refers) subject to committee approval there are five open and ongoing following the last meeting held on 12th November 2010. Replies received from relevant officers have been included in the updated version of the appendix.
Fundamental Systems
6 The Council’s target is for all fundamental systems to achieve at least a satisfactory audit opinion. Work in this area is well advanced with a final report issued for Education Transport, which was given a marginal audit opinion due to the need for improved risk management, income control and procedures, management checks and guidance to staff. As required under the Audit and Governance Code a copy of the report has been sent to the Chairman of the Audit and Governance Committee
Non Fundamental Systems
7 The report on Car Park Income has been finalised and an unsatisfactory audit opinion issued. This was due to the need for improved procedures and controls, managers have taken speedy action in relation to the recommendations made. The Service Manager has confirmed that all recommendations have been implemented. A follow up audit visit will be made to ensure that actions are embedded. As required under the Audit and Governance Code a copy of the report has been sent to the Chairman of the Audit and Governance Committee. Other work is at various stages of progress.
Governance and Anti-fraud
8 Preliminary work in relation to the National Fraud Initiative (NFI) 2010 is complete, relevant offices have been requested to submit relevant data to the Audit Commission. All relevant data has been submitted. The NFI Data Protection Compliance Return has been completed and submitted.
9 The Annual Governance Statement for 2009/10 was presented to the Audit and Governance Committee on 29th June and now forms part of the Council’s Statement of Accounts.
Other Key Systems
10 Member’s allowances and expenses were reviewed and given a satisfactory audit opinion. 11 CRB consultancy work to provide advice and guidance regarding the robustness of the new CRB system has now been completed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AGS Significant issues 2009-10: January 2011(f)Appendix 1 | 47 KB | Download |
PDF |
Open and ongoing resoulutions: January 2011 (f)Appendix 2 | 82 KB | Download |
PDF |
Audit Plan progress- January 2011(f)Appendix 3 | 54 KB | Download |
PDF |
INTERIM AUDIT SERVICES ASSURANCE REPORT 2010/11Report | 91 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.