MEETING: AUDIT AND GOVERNANCE COMMITTEE
DATE: 17 JANUARY 2011
TITLE OF REPORT: AGRESSO PROJECT UPDATE
PORTFOLIO AREA: RESOURCES CLASSIFICATION: Open Wards Affected None
Purpose To provide a briefing on the Agresso project, and the Audit implications as the system nears go- live.
Key Decision This is not a Key Decision.
Recommendation THAT the report be noted
Alternative Options This is an information report and therefore no alternative options are outlined.
Introduction 1. Agresso is an Enterprise Resource Planning (ERP) system. This integrated computer- based application can be used to manage internal and external resources, including tangible assets, financial resources, materials, and human resources. Its purpose is to facilitate the efficient flow of information between all business functions inside the boundaries of an organization and manage the connections to outside stakeholders.
2. A project is underway to implement Agresso within the Council, Hereford Hospitals the Primary Care Trusts. This report gives an overview of the project, and some detail specifically for the activities that have implications for Audit in the run-up to the 1st April 2011 initial go-live.
Project Background 3. Many Commercial and Public Sector organisations have sought to implement ERP systems to help streamline their businesses and consolidate information centrally, thus creating the opportunity to reduce the number of disparate computer and paper-based
Further information on the subject of this report is available from Simon Lind, Connects Programme Manager on (01432) 383187 systems.
4. For the three clients in Herefordshire, Agresso has been selected to be implemented and is a key enabler for the Shared Services. The table below details the elements of the Agresso system that each of the clients has opted to implement.
Main area of Financial functionality Ledger E- Sales to Procure to to be (Reporting, Payroll HR procurement Cash Pay implemented/ Financial (Proactis) (Debtors) (Creditors) Client Manage)
Herefordshire Yes Yes Yes Yes Yes Yes Council
Hereford Hospitals Yes No 1 No Yes Yes Yes Trust
Primary Care Yes No No Yes Yes Yes Trust
5. For the Council, Agresso provides the opportunity to consolidate previous disparate functions (e.g. bringing Payroll functions together) and streamline existing processes.
6. The new processes and ways of working will need to be reviewed again as further detail about Shared Services (and specifically the Target Operating Model) is agreed and becomes available. This will be post go-live.
7. There are no issues of concern with the Council’s existing Financial Ledger system (Cedar) but it does not support future business needs (e.g. Shared Services) as it is not designed as a fully integrated Finance, HR and Payroll system.
8. Cedar’s Supplier (COA Solutions) did form part of a competitive tendering process that was undertaken during 2009.
9. Agresso was selected as it offered similar functionality to other products, greater flexibility once installed, and for a lower total cost of ownership than its rivals.
10. For the Council alone the initial go-live will see around 200 users requiring to be trained. Eventually the majority of employees will use Agresso.
Unit4 (Agresso Supplier) 11. Agresso is an international product marketed by a company called Unit4 which has a
1 The NHS has a national HR (Electronic Staff Record) and Payroll system
_________________________________________________________________________________________
Page 2 of 10 range of financial and business system products, and operations in more than 20 Countries.
12. Under the contract with Unit4 the project receives support from the Supplier in a number of forms;
• Project Management – Unit4’s Project Manager is regularly on-site and is responsible (in conjunction with the local Project Manager) for driving the projects’ activities on a day to day basis.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AGRESSO PROJECT UPDATEReport | 200 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.