It was agreed that: (a) Subject to securing planning consent, a grant of £2,300,900 be awarded to John Kyrle High School and Sixth Form to fund an extension to the John Kyrle High School & Sixth Form Centre to enable its permanent expansion from seven forms of entry (210 pupils per year group) to eight forms of entry (240 pupils per year group); and (b) The grant being made subject to a requirement that the build be designed and completed with the objective of obtaining a BREEAM excellent or Passivhaus certification. £260k of the grant being allocated is specifically for this purpose.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: John Kyrle High School and Sixth Form: new permanent accommodation
Report by: Sufficiency Planning and Capital Investment Manager, Head of Educational Development
Classification Open
Decision type Key
This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.
This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.
Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.
Wards affected Ross North; Ross East; Ross west;
Purpose To approve a new permanent building at John Kyrle High School & Sixth Form Centre to accommodate additional pupils admitted from September 2021 in response to rising numbers in Ross-on-Wye and to meet parental preference, and to agree the procurement approach to deliver the required works.
Further information on the subject of this report is available from Karen Knight, Quentin Mee, Tel: 01432 383042, 01432 383043, email: [email protected], [email protected] John Kyrle High School & Sixth Form Centre is rated Good with Outstanding features by Ofsted and has been consistently oversubscribed since 2009. In recent years additional permanent accommodation has been provided and funded by John Kyrle to enable additional children to attend.
Funding has been identified in the council’s capital programme, using basic need government grant, to enable John Kyrle High School & Sixth Form Centre to expand by one form of entry. A grant will be provided to John Kyrle High School & Sixth Form centre to deliver a new science block which will provide additional classrooms and associated support spaces. The project will be delivered and managed by John Kyrle.
Recommendation(s) That:
(a) Subject to securing planning consent, a grant of £2,300,900 be awarded to John Kyrle High School and Sixth Form to fund an extension to the John Kyrle High School & Sixth Form Centre to enable its permanent expansion from seven forms of entry (210 pupils per year group) to eight forms of entry (240 pupils per year group); and
(b) The grant being made subject to a requirement that the build be designed and completed with the objective of obtaining a BREEAM excellent or Passivhaus certification. £260k of the grant being allocated is specifically for this purpose.
Alternative options 1. The grant is not provided. This is not recommended. There is already a pressure on places in Ross-on-Wye. Failure to invest in John Kyrle means the additional places required for 30 children in year 7 could not be accommodated at John Kyrle in September 2021 or future years. As there is no alternative secondary school in Ross-on-Wye the children would have to travel out of Ross and be accommodated at another school in Herefordshire or in Gloucestershire.
2. Further mobiles could be installed to provide the additional classroom space required. This is not recommended as the siting of a mobile would not be considered best value as they are looked upon as temporary solutions, have a finite life in planning terms and do not have the life span that permanent build accommodation would have. The council’s School Capital Investment Strategy includes the objective that children are not taught in temporary classrooms.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.