It was agreed that: (a) The council enters into a funding agreement with The Historic Buildings and Monuments Commission for England (HBMCE) to deliver the Heritage Action Zone Programme in Leominster as per the Delivery Plan with an anticipated total budget of £3.6m from the capital programme (£1.8 of which is match funded) and £1.8m from HBMCE; (b) The Director of Economy and Place, in consultation with Section 151 Officer, be authorised to take all operational decisions necessary to secure the funding agreement between the Herefordshire Council and The Historic Buildings and Monuments Commission for England; (c) The Director of Economy and Place be authorised to sign all sub grant agreements (for the building grants) to grant recipients and take day to day operational decisions, including any variations to any sub grant agreements; (d) The Director for Economy and Place, in consultation with Section 151 Officer, and approved by Cabinet Member for Economy, Environment and skills and Cabinet Member for Infrastructure and Transport, be authorised to sign any programme changes which may include identifying new projects in light of Covid19; (e) Section 151 Officer agrees that the Council provide forward funding grant payments to grant recipients up to a cumulative maximum of £500k over any quarterly period, pending drawn down of funds from the Historic Buildings and Monuments Commission for England.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Heritage Action Zone - Leominster
Report by: Cabinet member environment, economy and skills
Classification Open
Decision type Key
This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.
This is a key decision because it is likely to be significant having regard to: the strategic nature of the decision; and / or whether the outcome will have an impact, for better or worse, on the amenity of the community or quality of service provided by the authority to a significant number of people living or working in the locality (two or more wards) affected.
Purpose To approve expenditure and deliver activities as detailed in the Leominster Heritage Action Zone Delivery Plan.
Recommendation(s) That:
(a) The council enters into a funding agreement with The Historic Buildings and Monuments Commission for England (HBMCE) to deliver the Heritage Action Zone Programme in Leominster as per the Delivery Plan with an anticipated total budget of
Further information on the subject of this report is available from Nadine Kinsey, email: [email protected] £3.6m from the capital programme (£1.8 of which is match funded) and £1.8m from HBMCE;
(b) The Director of Economy and Place, in consultation with Section 151 Officer, be authorised to take all operational decisions necessary to secure the funding agreement between the Herefordshire Council and The Historic Buildings and Monuments Commission for England;
(c) The Director of Economy and Place be authorised to sign all sub grant agreements (for the building grants) to grant recipients and take day to day operational decisions, including any variations to any sub grant agreements;
(d) The Director for Economy and Place, in consultation with Section 151 Officer, and approved by Cabinet Member for Economy, Environment and skills and Cabinet Member for Infrastructure and Transport, be authorised to sign any programme changes which may include identifying new projects in light of Covid19;
(e) Section 151 Officer agrees that the Council provide forward funding grant payments to grant recipients up to a cumulative maximum of £500k over any quarterly period, pending drawn down of funds from the Historic Buildings and Monuments Commission for England.
Alternative options 1. Do nothing – the council is not statutorily obliged to deliver this programme. Not delivering the programme would mean that the council would not have to incur up to £1.8m of capital expenditure to match fund the programme activities. This option has been discounted as it would mean the council would not receive £1.8m of external funding to deliver regeneration activity within the county that will bring economic benefit and investment. There are no alternative sources of funding to deliver this programme and deliver this activity.
2. Reject the grant off from HBMCE and operate the scheme using only the Herefordshire Council match funding allocation. A capital funding budget allocation was approved at Council to use £1.8m council match should a successful Delivery Plan be agreed. £1.65m of this match is to be used for public realm and road improvements in Leominster town centre, including Corn Square, which are complementary to the other projects within the Heritage Action Zone Delivery Plan.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.