Resolved that (a) The Director for economy and place, following consultation with the Section 151 Officer, the Cabinet member for environment and economy and the Cabinet member for infrastructure and transport, be authorised to approve expenditure required to deliver the public realm projects which will be procured in line with the council’s contracts procedures rules; (b) The Director for economy and place, following consultation with Section 151 Officer, in consultation with the Cabinet member for environment and economy and Cabinet member for infrastructure and transport, be authorised take all operational decisions necessary to deliver the balance of the programme, including grant schemes and information and engagement projects within the total project budget of £3.6m; and (c) The Section 151 Officer be authorised to reduce the grant element of the overall budget to up to £1.8m from the £2m originally estimated and approved at Council so that the overall capital programme budget for this project is £3.6m.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Title of report: Leominster Heritage Action Zone Meeting: Cabinet
Meeting date: Thursday 23 September 2021
Report by: Cabinet member environment and economy;
Classification Open
Decision type
Key
This is a key decision because it is likely to result in the council incurring expenditure which is, or the making of savings which are, significant having regard to the council’s budget for the service or function concerned. A threshold of £500,000 is regarded as significant.
Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.
Wards affected Leominster East;
Purpose To approve expenditure and deliver activities as detailed in the Leominster Heritage Action Zone Delivery Plan.
Recommendation(s) That: a) The Director for economy and place, following consultation with the Section 151 Officer, the Cabinet member for environment and economy and the Cabinet member for infrastructure and transport, be authorised to approve expenditure required to deliver the public realm projects which will be procured in line with the council’s contracts procedures rules1;
1 Herefordshire Council Constitution; Part 4 – Procedure Rules Updated: 26 January 2021
Further information on the subject of this report is available from Robert Ewing, Tel: [phone removed], email: [email removed] b) The Director for economy and place, following consultation with Section 151 Officer, in consultation with the Cabinet member for environment and economy and Cabinet member for infrastructure and transport, be authorised take all operational decisions necessary to deliver the balance of the programme, including grant schemes and information and engagement projects within the total project budget of £3.6m; and c) The Section 151 Officer be authorised to reduce the grant element of the overall budget to up to £1.8m from the £2m originally estimated and approved at Council so that the overall capital programme budget for this project is £3.6m.
Alternative options 1. Do nothing – the council is not statutorily obliged to deliver this programme. Not delivering the programme would mean that the council would not have to incur up to £1.8m of capital expenditure to match fund the programme activities. This option has been discounted as the council would lose the grant funding and the ability to deliver the activities as detailed in Heritage Action Zone – Leominster decision taken on 23 July 2020.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.