Herefordshire Council
Cabinet, Thursday 23 February 2023 at 5.30pm

Aylestone School Expansion

Agreed Executive 1 paper

Cabinet agreed this item on Thursday 23 February 2023. Below is the council's own wording, with the papers it was decided on.

Item210

Resolved

It was resolved that: a) Cabinet agree to progress with the permanent expansion of Aylestone High School; b) Subject to securing planning consent, Aylestone High School is expanded to enable its permanent expansion to five forms of entry (150 pupils per year group) at a cost of not more than £13.1m including fees and contingency; c) Delegated authority for award of procurement contract for the lifecycle of the project, is given to the Corporate Director, Children and Young People; and d) The Service Director, Education, Skills and Learning, be authorised to take all operational decisions necessary to implement the above in consultation with the S151 Officer and the Cabinet Members for Children and Families and Commissioning, Procurement and Assets; and e) The Service Director, Education, Skills and Learning present to Cabinet a draft strategic plan for the delivery of school places across the County for the period 2024 to 2034 for final approval by Cabinet within the next twelve months.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

Title of report: Aylestone School Expansion Meeting: Cabinet

Meeting date: Thursday 23 February 2023

Report by: Cabinet member children and families;

Classification Open

Decision type Key

Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

Wards affected Aylestone Hill;

Purpose To approve the expansion of Aylestone School to accommodate additional pupils admitted from September 2026 in response to rising numbers in Hereford City.

Recommendation(s) That: (a) Cabinet agree to progress with the permanent expansion of Aylestone High School;

(b) Subject to securing planning consent, Aylestone High School is expanded to enable its permanent expansion to five forms of entry (150 pupils per year group) at a cost of not more than £13.1m including fees and contingency;

(c) Delegated authority for award of procurement contracts for the lifecycle of the project, is given to the Corporate Director, Children and Young People; and

Further information on the subject of this report is available from Michael Griffin, Jennifer Hilton-Trout, Karen Knight, Quentin Mee, Tel: 01432 383400, Tel: 01432 383042, Tel: 01432 383043, email: [email protected], [email protected], [email protected], [email removed] (d) The Service Director, Education, Skills and Learning, be authorised to take all operational decisions necessary to implement the above in consultation with the S151 Officer and the Cabinet Members for Children and Families and Commissioning, Procurement and Assets.

Alternative options 1. Expand Whitecross High School – this would be our preferred option, as there is a significant shortage of capacity at the school. However, the school is part of a Private Finance Initiative (PFI) contract for which the Council pays a unitary charge to the PFI contractor. The council explored what the impact of an extension at Whitecross would have on the PFI contract. Although the landlord was agreeable for the school to expand, it was identified that there would be a significant uplift in the annual unitary charge which has meant that any expansion, at this time, would not be financially viable, and therefore this option is not recommended.

2. Expand Kingstone High School – this was explored in detail and remains an option for the future, but not recommended at this time. A decision to expand Kingstone by one form of entry (1FE = 150 pupils) was due to be heard by Cabinet in November 2022 (to be closely followed by a further 1FE expansion proposal for Aylestone High School), but was later withdrawn to allow for: additional options to be considered following feedback during pre-cabinet scrutiny; and, further analysis identified a greater need for places in the city. Despite a number of housing developments in its catchment, Kingstone High School has the physical capacity to serve all the children in its catchment, meet the demand of the developments and provide the majority of places requested by parental preference. Any expansion at Kingstone, at this time, would result in transporting learners from the city to the Golden Valley and therefore would not align with the council’s commitment to climate change.

Key considerations 3. Ensuring there are sufficient school places to meet parental demand is a statutory duty for councils. This means that councils must make population and pupil forecasts in order to anticipate changes in demand. Where additional places are required the council is responsible for securing them. This applies to maintained schools, voluntary controlled schools, voluntary aided schools, free schools and academies.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Aylestone School ExpansionReport 284 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 21 attended
DH
Councillor David HitchinerChairperson, present
EC
Councillor Ellie ChownsMember, present
PC
Councillor Pauline CrockettMember, apologies
GD
Councillor Gemma DaviesMember, present
JH
Councillor John HarringtonMember, present
LH
Councillor Liz HarveyVice-Chairperson, in attendance
DT
Councillor Diana ToynbeeMember, present
AT
Councillor Ange TylerMember, present
JH
Councillor John HardwickCabinet support, apologies
PJ
Councillor Peter JinmanCabinet support, present
TJ
Councillor Terry JamesGroup leader, apologies
BM
Councillor Bob MatthewsGroup leader, apologies

All 21 on the meeting page

On this subject at Herefordshire

Search all
  1. Aylestone School ExpansionThis decision
  2. 251073 - aylestone high school, broadlands lane, hereford, herefordshire, hr1 1hyApproved
  3. Capital support for the federation of aylestone businsess and enterprise college and broadlands primary school and children's centreApproved
  4. Capital support for the federation of Aylestone Business and Enterprise College (ABEC), Broadlands Primary school and Children's CentreNoted
  5. 151204 aylestone school business and enterprise college, broadlands lane, hereford, herefordshire, hr1 1hyApproved
  6. Capital support for federation of Aylestone Business and Enterprise College (ABEC) and Broadlands Primary School and Children's Centre.Approved

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies