Resolved
It was resolved that: Cabinet, having reviewed performance and financial forecast for year 2022/23, as set out the in appendices A-E, have not identified any additional actions to be considered to achieve future improvements.
Cabinet decided this item on Thursday 23 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
It was resolved that: Cabinet, having reviewed performance and financial forecast for year 2022/23, as set out the in appendices A-E, have not identified any additional actions to be considered to achieve future improvements.
(All Wards);
Purpose
To review performance for Quarter 3 2022/23 and the forecast budget outturn for the year.
To provide assurance that progress has been made towards delivery of the agreed revenue budget and service delivery targets, and that the reasons for major variances or potential under-performance are understood and are being addressed to the cabinet’s satisfaction.
The forecast 2022/23 outturn shows a net overspend of £9.1 million after the use of reserves and recovery plan actions.
The proportion of performance measures showing an improvement, or remaining the same compared to the same period last year is 66%. At the end of the quarter, 81% of actions from the delivery plan are identified as complete or are progressing within planned timescales.
Recommendation(s)
That:
a) Cabinet review performance and financial forecast for year 2022/23, as set out in the appendices A-E, and identifies any additional actions to be considered to achieve future improvements.
Further information on the subject of this report is available from Appy Reddy, Tel: 01432 383675, email: [email protected] Alternative options
1. Cabinet may choose to review financial, delivery and operational performance more or less frequently; or request alternative actions to address any identified areas of under-performance, including referral to the relevant scrutiny committee.
Key considerations
Revenue Budget
2. The latest outturn forecast for 2022/23 at the end of December 2022 is a potential cost pressure of £9.1 million after the use of reserves and recovery plan actions (£8.7 million at Quarter 2).
3. The table below sets out the cabinet portfolio position at the end of December 2022. Further service detail is available in appendix A.
4. The overall forecast indicates a potential cost pressure of £9.1 million (5.2% of budget). At this stage in the year, emerging costs pressures continue to be validated however the underlying costs and demographic pressures will need to be managed and mitigating actions put in place to achieve a balance budget at the end of the financial year.
5. The table above indicates where there are in year plans to recover the forecast overspend and which will be funded from earmarked reserves. The impact of these one-off actions will reduce the outturn forecast for 2022/23 by £0.4 million to £9.1 million and it is expected that continuing activity to identify savings through transformation will mitigate these cost pressures for future years.
6. The improved forecast overspend of £0.3 million, before recovery actions, in the Health and Adult Wellbeing Portfolio reflects the delivery of recovery plan activity identified at Quarter 2 and a reduction in client demand. The forecast overspend of £0.3 million comprises net pressures within care provision budgets of £0.2 million offset by £0.5 million of allocated Better Care Fund hospital discharge funding held within Commissioning and Operational Service Delivery.
7. Children’s and Family Services and Young People’s Attainment is forecasting an overspend of £9.1 million at 31 December 2022. The overspend is largely explained by variances in Looked After Children of £7.1 million, Additional Needs of £1.4 million and the impact of the pay award which has resulted in an additional pressure of £0.5 million for 2022/23.
8. The £1.9 million movement in forecast (£7.2 million overspend reported at Quarter 2) comprises additional costs for Residential Placements of £1.2 million and Agency Fostering of £0.5 million, £0.2 million to support the ongoing care needs of Unaccompanied Asylum Seeker Children (UASC) and £0.2 million in Supported Accommodation costs offset by smaller variations across the Directorate.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revenue forecastAppendix A | 461 KB | Download |
PDF |
Capital forecastAppendix B | 581 KB | Download |
PDF |
Treasury management forecastAppendix C | 271 KB | Download |
PDF |
Savings deliveryAppendix D | 278 KB | Download |
PDF |
Delivery plan dashboardsAppendix E | 817 KB | Download |
PDF |
Quarter 3 Budget and PerformanceReport | 441 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.