Executive Quarterly Review of EFS Limited

Noted Executive 1 paper

Executive noted this item on Wednesday 14 September 2016. Below is the council's own wording, with the papers it was decided on.

Item36.2

Resolved

Decision that the report be noted. Reasons for the Decision Under the Governance Agreement the Executive was required to undertake quarterly reviews of Elstree Film Studios (EFS) to enable the Executive to carry out its delegated authority on behalf of the Council. The report before Members provided the first of those quarterly updates for 2016/17 and covered analysis of the Studios’ financial performance and business projections including the proposed new stage and ancillary area, a condition survey of the EFS estate and the lease agreement between the Council and EFS. Alternative Options Considered and Rejected None as a quarterly update report, for review by the Executive, was a requirement placed on EFS under the Governance Agreement. Key Points Arising from the Discussion · Further to the report and its introduction by the Finance, Property and Economic Development Portfolio Holder, the Chief Executive was pleased to report a clean bill of health for the Studios. He pointed out that the granting of the lease was still outstanding as it was dependent on completion of the condition survey commissioned by the Council (report paragraph 4.5 refers). The Chief Executive said that this was proving to be a long drawn out process but emphasised its importance as the condition of the site was one of the key considerations for all users of the Studios. · The Chief Executive also highlighted for Members’ particular attention the need for non-Executive Directors to take up formal training when made available (report paragraph 6.3 refers). The Finance, Property and Economic Development Portfolio Holder concurred that, in view of the Council’s intention of establishing a development company, the need for formal training of this kind was of paramount importance. He added that Officers as well as Members serving as non-Executive Directors should be urged to engage in formal training. · The Chairman agreed that it was highly important to have the correct expertise in place and advised that a full update would be given at the Operations Review Committee meeting on 20 September which the Managing Director of Elstree Film Studios was due to attend.
Word for word from the decision Hertsmere published for this meeting. Source: hertsmere.moderngov.co.uk

Follow this further

Built from Hertsmere's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Executive Quarterly Review of EFS LimitedReport 110 KB Copy on its way

More from Hertsmere Executive

All decisions
MeetingDecisionOutcome
6 Jul 2022 Scrutiny Review on Implementation of Section 106 Monies and the Community Infrastructure Levy - Executive responseDecision that t he Executive’s response to the Scrutiny Review of the Implementation of Section 106 monies and the Co... Approved Open
6 Jul 2022 Adoption of Statement of Common Ground (SCI) for the SW Hertsmere Joint Strategic Plan (JSP)Decision that i. the responses to the draft Statement of Community Involvement as set out in Appendix 2 to the report... Agreed Open
6 Jul 2022 Approval for public consultation of the SW Herts Joint Strategic Plan 'Realising our Potential' Regulation 18 consultation document plus associated Sustainability Appraisal Scoping ReportDecision that i . the following documents be issued for consultation: a. South West Hertfordshire 2050 – ‘Realising o... Agreed Open
6 Jul 2022 Covid-19 additional relief fund policyDecision that i. the “ Covid Additional Relief Fund Policy ” attached as appendix A to the report be approved. ii. au... Approved Open
6 Jul 2022 Support for Energy Bills - The Council Tax Rebate Discretionary SchemeDecision that i. the proposed “Council Tax Rebate Discretionary Scheme Policy” attached as appendix A to the report b... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies