Item91
Resolved
Decision that: 1. funding of £25,000 be approved to complete feasibility works, progress a design to planning application stage and commission preliminary legal work to negotiate the terms of agreement for the proposed affordable housing scheme at St John’s Church in Radlett, subject to the proposal meeting the Council’s affordable social housing policy criteria; 2. it be noted that, should the scheme progress, a proportion of these costs may be recoverable from Section 106 funding; and 3. further reports to be brought to the Executive and the Council to seek approval of the final scheme and project funding based on the final design and costing and evaluation process, including a robust financial appraisal to establish whether an acceptable financial return on investment is achievable. Reasons for the Decision It was considered that the scheme would result in much needed affordable housing in the area to be taken from unallocated Section 106 funding and in addition provide a new church hall facility for the benefit of the local community. Alternative Options Considered and Rejected The alternative option was to do nothing and not proceed with the project. However, as this would not provide the advantages stated above, this option was not supported. Key Points Arising from the Discussion · The Housing Portfolio Holder presented the report. She informed Members that the Church Council had approached this authority about a mutually beneficial scheme involving the provision of three 3-bedroom houses and three 2-bedroonm flats for the purpose of equity share affordable housing as well as the provision of a new church facility. · The Chief Executive advised the Executive that, as part of the move towards maximising Council assets, the Council had reached out to its local partners with the result that a rare opportunity had arisen which he recommended should be seized. He envisaged working with a positive, constructive partner in this matter by first carrying out a feasibility study and engaging the services of a Government-nominated administrator (Help to Buy) in view of the current fluctuating housing market. · The Chairman emphasised that the Council strongly favoured the practice of undertaking feasibility studies to assess the feasibility and viability of any scheme before a large amount of taxpayers’ money was committed. He cited a recent example determined by the Executive on 14 December 2016 involving the redevelopment of land in Allum Lane, Elstree for temporary accommodation purposes, the feasibility study for which he said was currently underway. (Action: Engineering Services and Asset Manager)
Word for word from the decision Hertsmere published for this meeting.
Source: hertsmere.moderngov.co.uk