That authority be delegated to officers, in consultation with the Chair of the Committee, to approve the application, subject to the successful negotiation with the applicant of all outstanding matters and the conditions as set out in the report (to be amended as required following resolution of those outstanding matters and as set out in the update sheet); 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, authority be delegated to the Operations Manager – Development Services to do so in consultation with the Chair of the Development Control Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 23rd January 2017
Application HPK/2016/0488 No: Location Rear of Hallsteads, Buxton Proposal Application for approval of reserved matters pursuant to outline planning permissions relating to HPK/2013/0319 & HPK/2013/0625 for Phase two 83 dwellings Applicant Jalo Enterprises Co Ltd Agent [name removed]/ward Chapel-en-le-Frith Date registered 02/09/2016 If you have a question about this report please contact: Ben Haywood -Email [email protected]; Tel: 01538 395400 Ext: 4924
REFERRAL
The application is referred to committee as it is a major development and High Peak Borough Council has an ownership interest in the site.
1. SUMMARY OF RECOMMENDATION
APPROVE, subject to conditions
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application site comprises a roughly triangular shaped area of some 3.22 ha, located on the north –eastern side of Dove Holes to the rear of properties fronting Hallsteads. The site lies within the built-up area boundary as defined in the adopted Chapel-en-le-Frith Neighbourhood Plan. It is located within 300m of the A6 trunk road.
2.2The site is bordered by The Meadows residential development to the south and to the north by Black Brook. The site lies immediately adjacent to a designated local wildlife site (Ridgeclose Rocks) which is part of the site of a former quarry. A public footpath runs across the site.
2.3The site lies adjacent to the former line of the Peak Forest tramway which lies in a cutting to the east. This area is noted on the Historic Environment Record as one of historic importance.
2.4The application, the details attached to it including the plans, the comments made by residents and the responses of consultees can be found on the Council’s website at: http://planning.highpeak.gov.uk/portal/servlets/ApplicationSearchServlet?PKID=2104 33
3. DESCRIPTION OF THE PROPOSAL
3.1The application is a reserved matters submission providing the detail in relation to the outline planning permission HPK/2013/0319 granted on 10th September 2010 and HPK/2013/0625 allowed on appeal on 27th October 2014 for a variation of condition 18 to increase the number of dwellings from 58 to 120 from the original outline application HPK/2013/0319. The outline planning permission was subject to a S106 legal agreement and a number of planning conditions. The S106 secures 30% affordable housing to be provided on site for each and every reserved matters application, and off site contribution for open space and play space within the Dove Holes area. 3.2 The reserved matters are access, appearance, landscaping, layout and scale. The proposal is for Phase 2 of the development comprising 83 dwellings (phase 1 for 21 dwellings of which 6 will be affordable dwellings having been approved by the Committee in April 2016 – application HPK/2015/0563 refers). The Phase 2 development, which is the subject of this application proposes 46 open market houses on Jalo land, 11 market houses on High Peak Borough Council Land and 26 rented affordable houses on High Peak Borough Land. 3.3 The application proposes a good mix of house types and designs of a similar nature to the existing Meadows Estate and those approved on the Phase 1 development. The dwellings would be constructed of artificial split faced stone, grey tiled roofs, upvc windows and doors, timber black fascias and soffits and sectional up and over garage doors. 3.3 The site is reached by a road off Walker Brow, forming part of the Meadows Estate which is directly served from the junction with the A6 at Dove Holes. A new road which will serve the Phase 1 development will be extended into phase 2. 4. RELEVANT PLANNING HISTORY
HPK/2015/0563 Reserved matters for 21 Approved 18/04/2016 dwellings
HPK/2015/0284 Application for approval of Withdrawn. reserved matters following outline approval HPK/2013/0319.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.