HPK/2026/0134 - The Natural Baths, The Crescent, Buxton
ApprovedPlanning1 paper
AI summaryHigh Peak Borough Council approves Listed Building Consent for internal works at the Grade II Natural Baths in Buxton to maintain mineral water extraction, subject to pre-commencement conditions on archaeology and vision panel design.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to amended DCC Archaeology condition
MoneyNot stated
What happens nextPre-commencement conditions to be dischargedWSI and vision panel details required first
Who it affectsThe Natural Baths, The Crescent, BuxtonGrade II Listed Building, Roman-era site
What was decided
The application was approved as set out in the officer report, subject to the amended condition from DCC Archaeology in the update sheet. Report P96
Delegated authority was given to the Head of Development Services, in consultation with the Chair, to make minor wording changes before the decision is issued, provided the substantive nature is not exceeded. Report P98
Why
Officers judged the works would cause less than substantial harm to the heritage asset by concealing 1920s decorative interiors, but this was outweighed by the public benefit of continued safe extraction of Buxton mineral water and preservation of the town's spa heritage. Report 8.25, 9.4, 9.5, 9.7, P87, P88, P89, P90
A nutrient neutrality screening found no likely significant effect on the Peak District Dales Special Area of Conservation, as the scheme does not increase overnight stays or surface water run-off. Report 8.36
What happens next
A Written Scheme of Investigation must be submitted and approved in writing before any works commence, and the development must then be carried out in accordance with the approved details. Report 8.33, 9.6, P97
Details of the proposed high-level horizontal vision panel and vertical vision panels, with scaled photographs showing the panels overlaid, must be submitted and approved before the internal wall system is produced or installed. Report P65, P97
Options considered
Chosen: Approve subject to conditions. Less than substantial heritage harm is outweighed by significant public benefits of continued safe water extraction and protection of Buxton's spa heritage status. Report 9.5, 9.7, P96
Implications
Legal: Section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 duty to have special regard to preserving the listed building was applied; less than substantial harm balanced against public benefits under Chapter 16 of the NPPF. Report 8.9, 8.11, 8.25
Other: The site is identified as the most probable location of the Roman baths, with two Historic Environment Records relating to it; the 1905 record places the bath 6 yards from the then 'Bathroom' near St Anne's Well. Report 8.29, 8.30
Other: The proposal was screened out of an Appropriate Assessment under the Habitats Regulations because it will not increase overnight stays or surface water run-off into the River Wye catchment. Report 8.36, P75
Who and where
The applicant, operating the water extraction from the Natural Mineral Baths Report 8.17, 8.22
Historic England and the Council's Conservation Officer, who negotiated a pre-commencement condition on vision panel design Report P1, 8.27, P65
The County Archaeologist, who requested a Written Scheme of Investigation before commencement Report 8.32, 8.33, 9.6
Buxton's tourism economy and the wider historic significance of the town as a spa destination Report 8.6, 8.23, 9.5, P89
Timeline
1850s: Original building constructed on the site of ancient Roman baths and later Georgian baths, subsequently altered in the early 20th century as a first class gentleman's bath. Report 8.12
2026-08-10: Development Control Committee approved Listed Building Consent subject to conditions and delegated authority for wording changes.
Plain English for the jargon
WSI: Written Scheme of Investigation: a document setting out how archaeological work will be carried out, agreed before development starts.
SAC: Special Area of Conservation: a European-protected wildlife site, in this case the Peak District Dales fed by the River Wye.
HRA: Habitats Regulations Assessment: a check on whether a plan or project is likely to harm a European-protected site.
Section 66(1): A legal duty requiring special regard to the desirability of preserving a listed building or its setting when deciding planning applications.
Less than substantial harm: An NPPF category of harm to a heritage asset that does not reach the threshold of substantial harm or total loss, but still weighs against the development in the planning balance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27/27
Resolved
That the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as set out in the update sheet: 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/ informatives /planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 10th August 2026
Application No: HPK/2026/0134 Location The Natural Baths, The Crescent, Buxton Proposal Listed Building Consent for Internal works to alter and extend the hygiene room system, removal of existing doors, removal of internal walls and below ground works to create 3 no. new drainage trenches Applicant Nestle Waters UK Ltd Agent DLP Planning Parish/ward Buxton Central Date registered 14th April 2026 If you have a question about this report please contact: James Stannard, Tel. 01298 28400 extension 4298, [email protected]
1. SUMMARY OF RECOMMENDATION
Approve with Conditions
1. REASON FOR COMMITTEE DETERMINATION
1.1This application has been brought before the Development Control Committee owing to the fact that High Peak Borough Council are landowners of the application site.
2. PROCEDURAL MATTERS
2.1The Application Form was submitted showing Certificate A completed, which submits that the applicant is the sole owner of all land within the application site, which is incorrect.
2.2After Officers identified this error, the applicant has submitted a completed Certificate B which correctly identifies that the Council have land interests in this site with notice being served and the required 21 day consultation period concluding prior to the application being assessed and presented before Committee.
2.3All procedural matters have now therefore been fully addressed.
3. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
3.1The application relates to the Grade II Listed Natural Mineral Baths which are directly associated with the Grade I Listed The Crescent, located in the heart of Buxton.
1 3.2 As indicated on the Existing and Proposed Elevation Plans, The Natural Baths are located at street level served by an entrance door, defined by three semi-circular windows which sit underneath the three floors serving the adjacent Old Hall Hotel.
3.3The Existing Floor Plan shows that the internal layout comprises an entrance lobby that provides access to the main pool room, beyond which is a store room. A corridor provides access via a flight of steps to a pool room extension, switch room and store room.
4. DESCRIPTION OF THE PROPOSAL
4.1The proposed development comprises the following works to improve hygiene standards at the Natural Mineral Baths:
• Removal of the existing hygiene room and steel staircase – stripping out works for which Listed Building Consent is not required;
• Installation of new hygiene surfaces in all rooms, corridors and service areas including installation of new hygiene doors and frames. Wall system to include vision panels through to preserved historic features and windows. The system is to be installed on a head and track system ensuring existing historic tiled walls remain undisturbed;
• Creation of a new reception/changing room;
• Demolition of existing wall between store room and pool room.
• Groundworks to fill old floor chambers, introduce new stainless steel drainage channels, excavate and lower existing drains. To include 3no. new outlet pipework routes for which ground works are required;
• Installation of new 6mm polyurethane flooring laid over the existing flooring throughout;
• Removal of existing floor drainage.
• Install new floor drainage;
• Removal of redundant pipework;
4.2No external alterations are proposed.
4.3Further to additional information being submitted during the consultation period, the full list of plans and documentation that is subject of assessment within this report is presented as follows:
2 - Existing Location & Floor Plan (Ref: D5660(3)-01-D) - Proposed Location & Floor Plan (Ref: D5660(3)-10-E) - Proposed Typical Details (Ref: D5660(3)-20-C) - Existing and Proposed Elevation (Ref: D5660(3)-30) - Design and Access Statement - Heritage Statement - Heritage Statement Addendum (24th June 2026) - Photograph (Vision Panel at Entrance – Vertical Tiling) - Photograph (Vision Panel in Back Room – Horizontal Tiling)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.