That authority be delegated to the Operations Manager – Development Services, in consultation with the Chair of the Committee, to approve the application, subject to no substantive objections being raised in the outstanding consultation responses, any additional planning conditions required as mitigation by the EA and the conditions and informatives as set out in the report; 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Operations Manager be delegated authority to do so, in consultation with the Chair of Development Control Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 3rd July 2017
Application HPK/2017/0200 No: Location Headfall Outfall at Warm Brook, Brookside Road, Chapel-en- le-Frith Proposal Proposed repair to river bank erosion in 4 places identified along the river Applicant High Peak Borough Council Agent N/A Parish/ward Chapel-en-leFrith Date registered 04/05/2017 If you have a question about this report please contact: John Williamson - Email [email protected]; Tel: 01538 395400 Ext: 4922; Mob: [phone removed]
REFERRAL
The application is referred to committee as the applicant is the Borough Council.
1. SUMMARY OF RECOMMENDATION
DELEGATED AUTHORITY TO APPROVE, subject to outstanding consultations, conditions & informatives
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application site consists of 4 No. locations where the river bank is to be repaired, the access to these areas and location of the site compound.
2.2The areas to be repaired are located on a stretch of river located to the rear of numbers 19 to 45 Brookside Road.
2.3The site is located on the edge of the built up area boundary and countryside and lies within a high risk flood zone and ‘settled valley pastures’ landscape character area, as defined in the Local Plan.
3. DESCRIPTION OF THE PROPOSAL
3.1The application seeks full planning permission for proposal to repair river bank erosion in 4 places identified along the river.
3.4The applicant has submitted the following additional information, details of which can be read on file: • Environmental Risk Assessment • Method of Work • Proposal to deal with Japanese Knot Weed
3.6The application and all details associated with it can be found on the Council’s website at:
5. PLANNING POLICIES, GUIDANCE AND OTHER MATERIAL CONSIDERATIONS RELEVANT TO THE DECISION
High Peak Local Plan Adopted April 2016
S1 – Sustainable development principles S1a – Presumption in favour of sustainable development S6 – Central sub-area strategy EQ2 – Landscape character EQ3 – Rural development EQ5 - Biodiversity EQ6 – Design and place making EQ9 – Trees, woodland and hedgerows EQ11 – Flood risk management CF6 – Accessibility and transport
Chapel-en-le-Frith Parish Neighbourhood Development Plan 2013-2028
National Planning Policy Framework
• Ministerial foreword • Introduction (Inc. Achieving sustainable development, presumption in favour of sustainable development, core planning principles, delivering sustainable development) • 4 Promoting sustainable transport • 7 Requiring good design • 8 Promoting healthy communities • 10 Meeting the challenge of climate change, flooding and coastal change • 11 Conserving and enhancing the natural environment
National Planning Practice Guidance
6. CONSULTATIONS
Site notice Expiry date for comments: 16.06.2017 Press notice Expiry date for comments: N/A Neighbours Expiry date for comments: 09/06/2017
Neighbours
No comments received
Consultees
Consultee Comment Officer response Environment Initial comments 7.13-7.16 Agency (flooding) Environment Agency position AND We object to the proposed development as submitted because the assessment and mitigation of the risks to 7.25-7.26 nature conservation are inadequate. We therefore recommend that the planning application is refused. (Crayfish) We will maintain our objection until the applicant has supplied information to demonstrate that the risks posed by the development can be satisfactorily addressed.
We wish to be consulted on the results of any survey submitted in connection with this application, on any design changes, additional mitigation, compensation or enhancement measures that might subsequently be proposed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.