That the application be approved as set out in the report; 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Operations Manager – Development Services be delegated authority to do so in consultation with the Chair of the Development Control Committee, provided that the changes do not exceed the substantive nature of the committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 16th July 2018
Application HPK/2018/0266 No: Location Fern Lea, Buxton Road, Chinley Proposal Variation of Conditions 2, 3, 4, 6, 7 and 11 to planning permission reference HPK/2017/0643 Applicant Messrs R Spicer and A Bains Agent [name removed], Emery Planning Partnership Ward/parish Blackbrook Ward / Chinley, Date registered 31st May 2018 Buxworth and Brownside Parish If you have a question about this report please contact: Mark Ollerenshaw [email protected] 01538 395400 ext. 4921
1. REFERRAL
The application is referred to the Development Control Committee because the previous application was determined by Committee.
SUMMARY OF RECOMMENDATION
APPROVE subject to conditions
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application site comprises a small detached bungalow, associated residential curtilage and ancillary buildings including a garage, situated on the south side of Buxton Road within the Green Belt and Open Countryside. The site is bordered by agricultural land to the east, south and west with the road immediately to the north. There are no immediate neighbours.
3. DESCRIPTION OF THE PROPOSAL
3.1This application seeks to vary a number of conditions attached to the previous approval for a replacement dwelling on the site, ref. HPK/2017/0643, which was granted permission in March 2018. A number of changes are proposed to the approved plans including the addition of a basement.
3.2As part of this submission the applicant is also seeking to vary and address a number of the conditions attached to the previous approval. The conditions proposed to be varied are 2, 3, 4, 6, 7 and 11 as set in more detail below.
3.3Condition 2 lists the approved plans. It is proposed to vary Condition 2 to reference updated plans which provide for the creation of a basement floor to the
1 property. The basement would contain a gym, media room, wine cellar, storage area and plant room and has a floor space of 123m2. It would be entirely below ground with the exception of two small light wells and would be constructed under and within the footprint of the approved dwelling. The additional basement would include engineering operations to remove approx. 320m3 of materials. Due to the existing and proposed site levels, some of this will not be able to be re-used within the development and would be removed from the site. The building would continue to meet the UK Passivhaus standard. The addition of the basement would improve the capability of the dwelling to meet this standard since there will be a greater surface area of the building walls that are buried, creating a more efficient insulation system.
3.4The applicant has submitted additional information/details with the intention that this can be assessed and agreed as part of this application, thus removing the need for pre-commencement conditions attached to the previous approval. The applicant has provided additional details of the proposed construction materials to address Condition 3 and further detail on boundary treatments to address Condition 6. An Asbestos Pre-refurbishment / Demolition Survey Report has been submitted which seeks to address Condition 11.
3.5In addition, it is proposed to vary Conditions 4 (hard and soft landscaping) and 7 (biodiversity enhancement strategy). Both of these are currently pre-commencement conditions which prevent the development being commenced until a scheme of hard and soft landscaping and a biodiversity enhancement strategy have been submitted to and approved by the Local Planning Authority. It is proposed to vary these conditions to allow the submission and agreement of details within 6 months of the commencement of development instead of prior to the commencement of development. This will enable both schemes to be drawn up whilst the initial groundworks and construction are underway.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.