Whitfield Recreation Ground - Play Area Improvement Project
DecidedExecutive1 paper
The Executive - Individual Executive Decisions decided this item on Thursday 11 April 2019. Below is the council's own wording, with the papers it was decided on.
That Whitfield Recreation Ground Play Area.be refurbished; 2. That funds be utilised from the Council’s Capital Programme for Play Facilities to expedite the refurbishment of the Play Area. Any declaration of interest received None A note of any dispensation, if any None
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
Report to The Executive - Individual Executive Decisions
Recommendation
2.1It is recommended that approval is given to:
Refurbish Whitfield Recreation Ground Play Area. Funds to be utilised from the Council’s Capital Programme for Play Facilities to expedite the refurbishment of the Play Area.
Executive summary
3.1Whitfield Recreation Ground play area is a large open space with play facilities for both toddlers and juniors that are well used by the local community that it serves.
3.2All of the play equipment on the site has been installed for a considerable number of years. In May 2018 the predominant feature on the site, a large multi-activity unit was removed as a result of serious public safety concerns. The remaining equipment is deteriorating and has little play value. As a matter of urgency the site needs significant investment to refurbish the play area.
3.3In comparison with other sites that have recently been refurbished a cost of £45,000 is considered to be a realistic amount to improve the site. 3.4 Approximately £33,000 of S106 contribution is allocated for Whitfield Recreation Ground from a development at Charlestown Works, Glossop. The trigger point for the release of the funds has not yet been reached (10% occupancy) there is also currently some uncertainty as to when this point will be reached.
3.5It is therefore proposed that £45,000 funding for this project will be met from the Council’s Capital Programme for Play Facilities, this capital pot currently amounts to £76,805 with anticipated draw on the funds in 2020/21. Thus enabling the refurbishment works to commence as soon as possible. The S106 monies will then be used to replenish £33,000 of the total of funds used; meaning the Councils contribution to the project will amount to circa £12,000.
3.6Initial consultation with the People of Whitfield group and the wider community of Whitfield has already identified that there is an urgent need to refurbish the play area. The group are fully supportive of the project and will continue to work with us to achieve a new play area for the site. This may also include some local fund raising to support the project, although it is recognised that such activities will be limited resulting in councils funds being required.
4. How this report links to Corporate Priorities
4.1The refurbishment of the play area will contribute towards ensuring that the Council continues to protect and improve the environment through the provision of quality open spaces.
5. Options and Analysis
5.1There are two options available to the Council:
1. Install new play equipment replacing the current equipment which is of poor quality and nearing the end of its life. The installation will enable us to work closely with the local community and provide a facility to encourage children to play locally, ultimately raising the Council’s profile. Recommended.
2. To do nothing - the existing play equipment is old, has little play value and has reached the end of its serviceable life. If left and allowed to deteriorate further the play area will fall into decline preventing children from playing locally, which will have a negative impact on the Council’s commitment to protect and improve the environment and providing quality open spaces (not recommended).
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998) This project will actively involve the People of Whitfield community group and the wider local community. This positive contribution will create a sense of ownership which potentially reduces anti social behaviour activities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Executive - Individual Executive Decisions at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1...
Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.