Whitfield Recreation Ground - Play Area Improvement Project

Approved Executive 1 paper

The Executive - Individual Executive Decisions approved this item on Tuesday 10 September 2019. Below is the council's own wording, with the papers it was decided on.

Item20/4

Resolved

That the revised project for the improvements to the play area at Whitfield Recreation Ground, be approved. Any declaration of interest None A note of any dispensation, if granted None
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to The Executive - Individual Executive Decisions

Recommendation

2.1It is recommended that the Executive Councillor approves the revised project for the improvements to the play area at Whitfield recreation ground

Executive summary

3.1Whitfield Recreation Ground play area is a large open space with play facilities for both toddlers and juniors that are well used by the local community that it serves. All of the play equipment on the site has been installed for a considerable number of years.

3.2In May 2018 the predominant feature on the site, a large multi activity unit was removed as a result of serious public safety concerns. The remaining equipment is deteriorating and has little play value. As a matter of urgency the site needs significant investment to refurbish the play area.

3.3In April 2019 the Council approved a project for the improvement of the facility, which committed £45,000 of funding towards the project including £33,000 of S106 contribution allocated from a development at Charlestown Works, Glossop.

3.4Initial consultation with the wider community of Whitfield has already identified that there is an urgent need to refurbish the play area. The group are fully supportive of the project and are continuing to work with the Council to achieve a new play area for the site.

3.5Given the level of support for the project, it is recommended to enhance the originally approved project to extend the scheme outwards to include the currently fenced toddler area. Initially this would have been explored at a later stage as funding became available. The additional cost of this is partially offset by a grant of £14,451 which has been allocated to the Council by government following the recent announcement of a parks improvement fund. The remaining funds will be provided from the Council’s Capital Programme for Play Facilities.

3.6Subject to approval of this play project our aspiration is for the new play area to be installed by Spring 2020.

4. How this report links to Corporate Priorities

4.1The refurbishment of the play area will contribute towards ensuring that the Council continues to protect and improve the environment through the provision of quality open spaces.

5. Options and Analysis

5.1There are three options available to the Council:

• Option 1 - Install a new play area to the value of £90,000, which will create a fully refurbished site with a wide range of play equipment for both toddlers and juniors. The installation will enable us to work closely with the local community and provide a facility to encourage children to play locally, ultimately raising the Council’s profile. – Recommended

• Option 2 - Install a core scheme of new play equipment to the value of £45,000 as per report IED 19/32 Whitfield Recreation Ground – Play Area Improvement Project – (not recommended).

• Option 3 - To do nothing - the existing play equipment is old, has little play value and has reached the end of its serviceable life. If left and allowed to deteriorate further the play area will fall into decline preventing children from playing locally, which will have a negative impact on the Council’s commitment to protect and improve the environment and providing quality open spaces (not recommended). 6. Implications

6.1Community Safety - (Crime and Disorder Act 1998) This project will actively involve the People of Whitfield community group and the wider local community. This positive contribution will create a sense of ownership which potentially reduces anti social behaviour activities.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Whitfield Recreation Ground: Play Area Improvement ProjectReport 42 KB DownloadRead as text

At this meeting

Whole meeting
20/4Whitfield Recreation Ground - Play Area Improvement ProjectThis decision

On this subject at High Peak

Search all
  1. Whitfield Recreation Ground - Play Area Improvement ProjectThis decision
  2. Whitfield Recreation Ground - Play Area Improvement ProjectDecided

More from High Peak The Executive - Individual Executive Decisions

All decisions
MeetingDecisionOutcome
18 Aug 2026 Asset of Community Value nomination - Hockerley Meadow, Whaley BridgeThat the nomination for land lying to the Northwest of Hockerley Lane, Whaley Bridge, High peak be declined for the r... Decided Open
4 Aug 2026 Request for additional capital Funds towards the Gamesley Play Improvement ProjectsThat the allocation of £100,000 from the Council’s capital funds to ensure that improvements at both play areas meet ... Approved Open
4 Aug 2026 Request for Capital Funding to Support Improvements to Manor Park CaféThat the allocation of £30,000 from the Council’s capital funds to undertake essential refurbishment and improvement ... Approved Open
4 Aug 2026 Visit Peak District & Derbyshire SLAThat the signing of the High Peak Visit Peak District & Derbyshire SLA 2026 – 2029 to allocate a total of £30,000 (£1... Approved Open
28 Jul 2026 Alliance MyActive Wellbeing LimitedRESOLVED 1. That the appointment of [name removed] as an Independent Director of Alliance MyActive Wellbeing Ltd. be ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies