Resolved
That the application be deferred in order to obtain further comments from Natural England in respect of the Applicant’s Assessment of Likely Significant Effects.
Development Control Committee deferred this item on Monday 15 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be deferred in order to obtain further comments from Natural England in respect of the Applicant’s Assessment of Likely Significant Effects.
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 15th July 2019
Application HPK/2019/0097 No: Location Rockhead Spring Pump Building, Bakewell Road, Buxton Proposal Installation of a pipe from Rockhead Spring Pump House to Waterswallows Lane along a route that includes Bakewwell Road, Redgap Lane, Daiseymere Lane and Waterswallows Lane. Applicant [name removed], Nestle Waters Agent [name removed], Cass Associates Parish/ward King Sterndale / Cote Date registered 21st March Heath 2019 If you have a question about this report please contact: Ben Haywood email: [email protected] Tel: 01538 395400 Ext: 4924
REFERRAL
The application has been referred to the Committee as it is a major development
1. SUMMARY OF RECOMMENDATION
Approve, subject to conditions
2. DESCRIPTION OF THE PROPOSAL
2.1Nestlé Waters UK bottles mineral and spring water at its bottling plant facility on Waterswallows Lane, Buxton. To supply growing customer demand, Nestlé Waters has acquired the Rockhead Spring along the A6 (Bakewell road) approx 2 miles to the SE of Buxton Town centre. The source is approximately 4km from the bottling plant and a new pipeline is required between the source and the plant to transport the water between the two locations.
2.2The works effectively consist of a single trench, 600m wide and 1.2m deep for the entire 4km. It is anticipated that trench-work will be via 4-man gang using 6-13T excavator or trenching machine.. Once excavated pipework will be placed within the trench, with site welds applied every 18m. The apparatus to be installed within, is summarized as follows;-
2 Off DN65 316L stainless steel production pipes, wrapped spirally bin Densoclad. 2 Off 150mm Cable ducts. The apparatus will be laid at a cover of 900mm with a 100mm sand bed and surround. The backfill material above the sand and warning tape will vary dependent on whether the trench is within (a) highway or (b) farm land/verge. All trench re-instatement will be carried out in accordance with the Specification for the reinstatement of openings in highways (3rd Edition)
3. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
3.1At present the Rockhead Source site comprises a small stone and slate building similar in size to a small detached garage, surrounded by a palisade fence which sits alongside the A6 road into Buxton. The site is well screened from the road by boundary trees and shrubs.
3.2Separate applications are also under consideration by the Council for monitoring boreholes at the site and a new pump building.
3.3The proposed pipeline would start from the Rockhead source and after leaving the Rockhead compound, the route will enter several different sections noted on the submitted plan with letters. In brief the sections involve;-
A – B 400m section in the A6, under a Network Rail Viaduct, followed by a river crossing and a short run across a rough hardstanding area used by local plant yard and quarry wagons. B- C 125m section through a Site of Scientific Interest (SSSI) C-D 900m section across farmland, farmyard and tracks ending in a crossing of Redgap Lane. D-E 900m section in wide verge parallel to Redgap Lane.. E-F 750m section in the narrower verge of Daisymere Lane. F-G Crossing of Waterswallows Lane adjacent junction. G-H Section in Nestlé owned land.
3.4The application and details attached to it - including the plans, supporting documents, representations and responses from consultees - can be found on the Council’s website at:-
http://planning.highpeak.gov.uk/portal/servlets/ApplicationSearchServlet?PKID=2311 32
4. RELEVANT PLANNING HISTORY
4.1No relevant history.
5. PLANNING POLICIES RELEVANT TO THE DECISION
Adopted High Peak Local Plan 2016
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HPK/2019/0097 Rockhead Spring Pump Building, Bakewell Road, Buxton: Installation of a pipe from Rockhead Spring Pump House to Waterswallows LaneReport | 518 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.