Resolved
That the project update and the next steps proposed in order to progress the England Housing Infrastructure Fund Project (Fairfield Roundabout be noted.)
Economy and Growth Select Committee noted this item on Wednesday 29 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the project update and the next steps proposed in order to progress the England Housing Infrastructure Fund Project (Fairfield Roundabout be noted.)
2.1Members are requested to note the project update and the next steps proposed in order to progress the England Housing Infrastructure Fund Project (Fairfield Roundabout)
3.1An IED report was presented to the Executive in June 2020, providing an update of project progress and requesting authorisation for the appointment of consultants to provide commercial development expertise for delivery of the Housing Infrastructure Fund supported work at Fairfield (subject to confirmation of costs being met by Homes England).
3.2Since this time, the following actions have been progressed;
3.2.1 The application for golf course mitigation works was approved by the HPBC Development Control Committee at their meeting on 29th June. The planning application for the roundabout was approved by DCC on 6th July.
3.2.2 DCC is currently undertaking advance design works for the roundabout, to help determine a more accurate estimate of construction costs. This should be available in July.
3.2.3 A letter has been sent to Homes England to request a review of the Housing Infrastructure Fund (HIF) Grant Funding Agreement (GFA). The Council has suggested some changes based on advice received from Freeths (commissioned legal advisers). The letter to HE also requests a review of the project timetable in light of COVID-19 and seeks additional grant funding. This capacity support is required to enable the Council procure development consultancy expertise to help resolve the key issues identified above.
3.2.4 In addition, the Council has requested revising the HIF programme to include the HE Local Authority Accelerated Construction (LAAC) funded project for delivering Granby Road B. Should HE agree, it is expected that LAAC funding of around £385,000 would be added to the HIF
3.3It is proposed to bring a further report to Members for their consideration in August/September. The purpose of the report will be to present a project review, to consider progress on the issues of HE grant funding and the updated costs of the roundabout, with an assessment of whether remaining risks are within an acceptable tolerance that will enable the project to continue.
5. How this report links to Corporate Priorities
5.1The accelerated housing delivery programme contributes to the following aims of the Corporate Plan 2019 – 2023:
• Aim 2: A responsive, smart, financially resilient and forward thinking council.
• Aim 3: Protect and create jobs by supporting economic growth, development and regeneration.
5.1There are no options to consider at this stage
Neil Rodgers Executive Director (Place)
Web Links and Contact details Background Papers June 2020 Executive IED Accelerated Housing Delivery Joanna Bagnall Programme update (Housing Infrastructure Fund and Senior Regeneration Officer Local Authority Accelerated Construction) [email protected] Feb 2020 Executive report HIF project draw down and risks Aug 2019 Executive report HIF update report and approval to accept HE grant April 2018 Executive report AHDP update Sept 2016 Executive report AHDP approval
6. Detail
6.1Homes England (HE) has made a grant award to the Council of £2m towards the construction of the Fairfield roundabout and link roads. Delivery of this infrastructure will unlock sites allocated in the Local Plan at Hogshaw, Waterswallows and Granby Road, helping to bring forward around 570 new homes. The construction of the roundabout and link roads is key to securing housing delivery on all sites in the North Buxton cluster.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fairfield Roundabout UpdateReport | 72 KB | DownloadRead as text |
Follow Economy and Growth Select Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Aug 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 27 Apr 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 19 Mar 2026 | Exclusion of Press and PublicThat the press and public be excluded from the meeting during consideration of the following item of business as ther... | Decided | Open |
| 19 Mar 2026 | To approve the minutes of the previous meetingThat the minutes of the meeting held on 26 November 2025 be approved as a correct record. | Approved | Open |
| 19 Mar 2026 | Select Committee Work ProgrammeThat, subject to the above, the Select Committee Work Programme, be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.