Resolved
DECISION : That the minutes of the meeting of the Cabinet held on 4 August 2020 be approved as a correct record.
Cabinet approved this item on Tuesday 6 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION : That the minutes of the meeting of the Cabinet held on 4 August 2020 be approved as a correct record.
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL
CABINET DECISIONS TUESDAY, 4 AUGUST 2020 PRESENT: Councillor S E Ralphs MBE (Chair)
Councillors M Bowen, M A Deaville, T Hall, J Porter, S Scalise and E Wain
IN ATTENDANCE: Councillors J Aberley, G Bentley, S Coleman, E Fallows, K Hoptroff, K Jackson, L Malyon, L Swindlehurst, R Ward and N Yates
61 MINUTES OF THE PREVIOUS MEETING (PREVIOUSLY CIRCULATED)
DECISION – That the minutes of the meeting of the Cabinet held on 16 June 2020 be APPROVED as a correct record.
62 DECLARATIONS OF INTEREST, IF ANY
The following declarations were made:
Member Declaring Agenda Item Nature of Interest Interest
Other Interest – Son-in-Law Cllr. T Hall Agenda Item 12 – is Director of MF Tyler Disposal of Plots 12 – 15 Victoria Business Park Lobbied – No response Cllr. S. Scalise given
63 FORWARD PLAN
DECISION:
That the Forward Plan be APPROVED for publication.
64 FOURTH QUARTER FINANCIAL, PROCUREMENT & PERFORMANCE REVIEW
The purpose of the report was to inform members of the Council’s overall performance and financial position for the period ended 31 March 2020 (Fourth Quarter 2019/20). The report was considered by the Resources Overview and Scrutiny Panel on 15 July 2020. The position was summarised as follows:
Subject Headline Finance Headlines for the Fourth quarter were: Performance against Budget At the fourth quarter stage the General Fund provisional outturn for 2019/20 was an underspend of £1,322,792. Efficiency Programme Cabinet - 4 August 2020
The 2019/20 general fund efficiency target of £842,000 had been exceeded with £1,025,000 of savings achieved. Capital Programme The revised Capital Programme budget for 2019/20 was £3.3 million. The outturn for the year was £2.7 million; a variance of £0.607 million – mostly in respect of underspend on Disabled Facilities Grant works. Treasury Management Cash investments held at 31 March 2020 totalled £9.7 million. The Ascent loan and debenture currently stood at £14 million. Council borrowing at 31 March 2020 totalled £10 million (related to the Ascent loan) The Council’s net interest income receipts were £73,110 surplus above budget. Revenue Collection 98.55% of Council Tax was collected by 31 March 2020 compared to 98.66% for the same period last year. 99.30% of Business Rates was collected by 31 March 2020 compared with 99.13% for the same period last year. Variances in payments plans are contributing to the above year-on- year difference At the end of the Fourth Quarter debt that was over 60 days old was £70,729 which compared with £70,434 at 31 March 2020. Procuremen Headlines for the Fourth Quarter were: t 11 procurement activities were completed The Procurement forward plan included 56 procurement activities for completion in 2020/21 (either SMDC only or joint) At the 31 March 2020, 67% of procurement activity undertaken was on the forward plan and the Council paid 97% of its invoices within 30 days during the year Performanc The headlines for the Fourth Quarter were: e 67% of the key performance indicators met target (43% of which were better than last year) The Council received 63 complaints and 65 compliments in the Fourth Quarter. 12 projects on track, 1 completed, 1 Red Rated and 6 Grey.
Members commented that the positive report reflected a tremendous effort on the part of all involved. DECIDED:
1. That the Fourth Quarter 2019/20 financial, procurement and performance position detailed in Appendices A, B and C and summarised in the report be NOTED.
2. That the allocation of the surplus on the General Fund Revenue Account to reserves as explained in Appendix A (paragraph 2.10) be APPROVED.
3. That the proposal to carry forward unspent revenue budget as described in Appendix A (paragraph 2.12) be APPROVED. Cabinet - 4 August 2020
4. That the proposals to carry forward unspent capital budget as set out in Appendix A (paragraph 5.6) be APPROVED.
65 FINANCIAL PLANNING PROCESS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the previous meeting (previously circulated)Minutes | 93 KB | DownloadRead as text |
Follow Cabinet at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Aug 2026 | Forward PlanDECISION: That the be approved for publication. | Approved | Open |
| 11 Aug 2026 | Climate and Nature Delivery Plan Update - Performance Report October 25 to April 26DECISION: That Cabinet approved the performance report set out in Appendix A. | Approved | Open |
| 11 Aug 2026 | Fourth Quarter - Finance, Procurement & Performance ReportsDECISION: 1. That the Fourth Quarter 2025/26 financial, procurement and performance position detailed in Appendices A... | Noted | Open |
| 11 Aug 2026 | Partial Review Staffordshire Moorlands Local PlanDECISION: 1. That the Staffordshire Moorlands Local Plan Partial Review be approved (attached at Appendix A) for a 6-... | Approved | Open |
| 11 Aug 2026 | Adoption of Market Guidance (Development Management)DECISION: That the Guidance attached at Appendix 1 of the report be approved for use by the Council’s Development Man... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.