Resolved
That the update sheet be noted.
Development Control Committee noted this item on Monday 18 January 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update sheet be noted.
18TH JANUARY 2021
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATES SHEET
HPK/2020/0201 – Land off Buxton Road, Furness Vale (Residential)
DCC (Derbyshire County Council): Landscape Architect Officer:
Further revisions have been made to the proposed layout in response to discussions, this has addressed some previous concerns and some key improvements have been made to the layout. A reduction in density has been accepted and this is key to making improvements possible in the context of a very constrained site.
The overall number of parking spaces has been reduced and the turning head to the proposed access road mirrored. These measures will reduce the dominance of parking and road areas and they will also allow a greater proportion of front gardens with planting and incorporate more tree planting. This will be beneficial to the street scene within the development as well as views from Buxton Road. The omission of parking to the front of block 8 is a particular improvement in this respect and allows the access road to be terminated by planting. Improvements to views to the open countryside have also been made by the reconfiguration of blocks.
Overall I consider that considerable progress has been made in the development of the layout and consideration has been given to include as much planting as possible to help mitigate the impacts of parking areas. Whilst it would be ideal to include a greener street scene with less parking areas, given the constraints of the site I consider that the proposals achieve a good balance and would support the revised proposal subject to a condition to ensure that the detailed landscape proposals are suitable and adequate.
DCC (Derbyshire County Council): Urban Design Officer: Awaited.
HPBC Environmental Health: I can confirm that the approved noise assessment, includes assessment and mitigation regarding rail traffic noise (Peak Acoustics, Noise & Vibration Assessment Report (ref: NM2708191NR Rev 1.0), dated 6th October 2020).
LLFA (Lead Local Flood Authority) (DCC):
Objection (insufficient information): Without clear confirmation from United Utilities that it would be safe for the developer to discharge into their combined sewer at the location intended and a discharge rate that it would be safe for them to do so the LLFA refer to their earlier comments. Network Rail
15.01.21 The applicant is proposing embankment works adjacent to the boundary in the amended details therefore Network Rail’s comments remain. This proposal must be reviewed and agreed by Network Rail.
Applicant:
15.01.21: Further commentary has been received as follows:
Car parking The revised site layout has been amended to highlight the distribution of grouped, unallocated parking as requested.
Flood The applicant’s engineers have provided confirmation from United Utilities that there is no alternative for this site but to connect into the existing drain on Buxton Road / A6.
Network Rail Delegated authority is sought to resolve final outstanding issues.
100% affordable home provision The proposal for 37 new homes on this site accords with HPBC housing allocation (Site C16) and therefore responds to a recognised housing need in the area.
Policy requirements are for the provision of 30% affordable homes (11No units) however the applicant is committing to providing 100% (37 units) with a mix of Affordable Rent and Shared Ownership units.
Commitment to build The applicant, The Guinness Partnership Ltd., is committed to delivering high quality affordable homes in High Peak, adding to the stock they already own and manage in the area. With Homes England grant funds committed to this development, the applicant is committed to commencing work on site within a matter of months of receiving planning approval. Discussions have already commenced with regards securing a suitable building contractor for the development via the Innovation Chain North framework.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 96 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.