Development Control Committee noted this item on Monday 21 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the update sheet be noted.
21st JUNE 2021
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATE REPORT
HPK/2021/0020 – Ferney Bottom Farm, Grinlow Road, Harpur Hill
Applicant:
Comments summarised as follows:
“1. Our ecologist has addressed all of the matters raised by DWT and it is they who have not yet substantiated their objection in light of this. 2. We have already supplied clarity in respect of the quantum of the red edged and blue edged site areas. It also states the site can be accessed from Ferney Bottom Farm itself and it cannot. Access will be solely via the stoned track to the North West of the existing substation. 3. para 2.7 states that the Ferney Bottom Local wildlife site was designated in 2019, I can find no evidence of this. It would seem that DWT were instrumental in the designation of this site and I therefore question their ability to act for the council as an independent consultant on this matter as there is clearly a conflict of interest and bias on this matter. 4. para 3.3 'a new access point would be formed north east and adjacent to the electricity sub station off the Harpur Hill Road'. It is not a new access point, it is an enhancement of an existing agricultural access point, next to the redundant electricity sub station, off Morland Way. So it is not new, and nowhere near Harpur Hill Road, Morland Way joins Grinlow Road. 5. para 3.5 states 'hours of operation are not given and are assumed to be 24/7'. The hours of operation are in fact 8am to 4pm Monday to Friday inclusive …”.
Applicant’s Landscape Consultant
“Having read the refusal recommendation my comments are as follows;
'....The proposed development would also result in ‘less than substantial harm’ to the setting of the Grade II Listed Grin Low Tower.'
The way this has been written suggests they have interpreted 'less than substantial harm' as significant. My interpretation is that effects are not significant. I have not had chance to read through the heritage report, but if effects are indeed not significant then the heritage consultant should in my opinion reinforce this with a statement of clarification of some sort.
'Furthermore, the applicant has not demonstrated that the identified harm to biodiversity as a result of the scheme could be adequately mitigated against.'
The applicant has submitted an Ecology Report, the Biodiversity Net Gain calculation and the Soft Landscape Mitigation Strategy. Regarding landscape...
'The proposed scheme, however, for a large industrial building and yard within open countryside would result in significant landscape harm from a number of high sensitivity receptor points whereby proposed tree planting would be deemed as inappropriate mitigation within the Limestone Moorland landscape context.'
Whilst the development is not within the defined development boundary of Harpur Hill, neither is the entirety of the Harpur Hill Employment Zone.
Firstly there is an impasse on 'significant landscape harm'. Under separate cover, I can detail our strategy for taking apart the landscape consultee's objections dated 250521, which would inform the process of taking the case to an independent higher authority- should you chose to pursue this avenue.
We would also suggest that the term 'open countryside' is questionable. As previously stated on many occasions the site lies within a landscape which has been heavily intervened by past and present industry and quarrying set within a moorland context. At the local scale the agricultural fields sit within an enclave between settlement, industry, quarried land and moorland- these fields are technically at odds with the prevailing local landscape character.
The site is far from being considered open countryside.
These fields are highly susceptibility to change to the type of development proposed given the Morland Way highway infrastructure, which effectively annexes them from the open countryside to the north. There is also a semblance of ribbon development along Morland Way presenting an urban fringe character.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 498 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.