Resolved
That the be NOTED .
Development Control Committee noted this item on Monday 11 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the be NOTED .
11th July 2022
HPBC DEVELOPMENT CONTROL COMMITTEE
UPDATES SHEET
HPK/2021/0081 Land at Longclough Drive, Glossop
Ecology
An updated Biodiversity Management Plan has been submitted confirming that the proposed management details are for a 10-year period, which reflects the previous advice from DWT.
Clarified advice has been received from Derbyshire Wildlife Trust regarding proposed details of ecological mitigation and enhancement. In light of these technical clarifications, the following additional condition is recommended in addition to those noted in the main report:
- 5-year review of biodiversity management plan
Public open space management
An updated Biodiversity Management Plan has been received providing additional details of maintenance and management of the public open space, as follows:
Close Mown Grassland 5.2.6 Close mown grassland as shown Landscape Proposals Plan within and around the residential development area will be maintained by regularly cuts, approximately every four weeks to between 30 to 50mm, this will maintain a neat and tide appearance while allowing flowering plants to grow in short grass and flower between cuts.
5.4.1 Litter picking and debris removal will ensure that a neat and tidy general appearance is sustained throughout the soft landscaped areas.
5.4.2 The surface of the paths will be checked every six months and if necessary repaired. Paths will be kept clear of undergrowth and overhanging tree branches.
It is considered that the indicated details of litter clearance are still not sufficiently specific and that further clarification should be secured, either prior to final approval or by imposing a further condition to allow for later approval of these details.
Updated plans, landscaping, trees
An updated site layout plan reflecting a change the layout of the footpath in the open space (avoiding a protected tree) has now been received and is available on the website. It is considered that approval should be granted on the basis of this amended layout plan.
An updated tree protection plan has been received reflecting the final proposed layout. It is suggested that the previously suggested condition relating to tree protection can instead be reworded to relate to this updated plan, rather than requiring further approval by condition. An updated landscaping details plan, amended to be consistent with the final proposed layout has also been received. The modified details reflecting the change in layout at plots 1- 4 and the simplification of the footpaths are considered to be acceptable.
AMENDED RECOMMENDATION:
A. That the application be delegated to the Chair of the Development Control Committee and the Head of Development Services for APPROVAL, subject to the conditions listed in the main report, the additional condition noted above and following receipt of clarified details of open space maintenance.
B. In the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/informatives/planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Development Services has delegated authority to do so in consultation with the Chairman of the Development Control Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
HPK/2020/0219- Land adjacent 80 New Mills Road, Hayfield
ERRATUM
Paragraph 8.6 of the report should read:
Section 5 of the NPPF relates to delivering a sufficient supply of homes. Paragraph 68 requires planning policies to identify a sufficient supply and mix of sites, taking into account their availability, suitability and likely economic viability. The Council does not currently have a five year housing land supply and therefore housing supply policies are not up-to-date and the presumption in favour of sustainable development is engaged unless specific policies as referred to in footnote 9 of the Framework indicate otherwise. This matter will be returned to below.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update SheetReport | 103 KB | DownloadRead as text |
Follow Development Control Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Aug 2026 | Minutes of the previous meetingThat the minutes of the meeting held on 13 July 2026 be approved as a correct record. | Approved | Open |
| 10 Aug 2026 | Update SheetThat the update sheet be noted. | Noted | Open |
| 10 Aug 2026 | Planning ApplicationsThat the report be noted. | Noted | Open |
| 10 Aug 2026 | HPK/2026/0134 - The Natural Baths, The Crescent, BuxtonThat the application be approved as set out in the report, subject to the amended condition from DCC Archaeology as s... | Approved | Open |
| 10 Aug 2026 | HPK/2026/0184 - Buxton Opera House, Water Street, Buxton, DerbyshireThat Listed Building Consent be granted as set out in the report: 2. That in the event of any changes being needed to... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.