That the Late Representation report be noted; That contrary to officers’ recommendation, the application be REFUSED for the following reasons: a. Contrary to Policies SS1, SD1, SD2, DC3; b. No special circumstances which sufficiently outweigh the harm to the greenbelt; c. Landscape and visual impact due to potential light pollution; d. Cumulative impact of the proposal to the greenbelt; e. Concern in relation to the possibility of explosions and proximity to residential properties; f. Distance from the substation. 3. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Development Services be given delegated authority to do so in consultation with the Chair of the Planning Applications Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision. (Proposed by Councillor Roberts and seconded by Holmes)
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL PLANNING APPLICATIONS COMMITTEE
8th June 2023
Application SMD/2022/0574 No: Location Land adjacent to Armshead Farm, Armshead Road, Werrington, Staffordshire Proposal Erection of storage containers, support infrastructure and security fencing for battery energy storage facility along with landscaping and all associated works. Applicant Conrad Energy (Developments) Limited Agent Alder King Planning Consultant Parish/ward Cheddleton Date registered 21/11/2022 If you have a question about this report please contact: John Copestake [email protected]
REFERRAL
The proposal is for major development in the Green Belt..
1. SUMMARY OF RECOMMENDATION
Approve with conditions.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The site comprises 4.07ha of agricultural land within the Green Belt, approximately 800m to the southwest of Cellarhead Substation and 420m to the northern extent of the main area of housing development in Werrington. The site is accessed via a track running east from Armshead Road which also comprises a public footpath (Public Footpath No.49 Cheddleton Parish). The site is generally flat, with the wider landscape generally featuring flat agricultural fields to the north, east and southeast with no large settlements within 5km, rising slightly across fields and up to Abbey Hulton 2.2km to the west.
2.2The application site includes five adjacent fields, three to the north of the existing farm track and footpath, and two to the south. The main compound will be located within the southeast corner of the wider site, with a new track running parallel and to the south of the existing track providing access. The remainder of the site, which comprises approximately 90% of the total area, is to be used for extensive hard and soft landscaping.
3. DESCRIPTION OF THE PROPOSAL
3.1The proposed development is for a battery energy storage facility, with access and landscaping. Notably, the application seeks permission for 35 years, after which time the battery energy storage infrastructure will be removed from the site.
3.2The battery storage infrastructure comprises: 64 battery units – metal box form structures with external fastenings, 2.9m high, 6.1m long and 2.4m wide; 32 inverter units – metal box form structures with external machinery and panels, 2.9m high, 6.1m long and 2.4m wide; One auxiliary transformer – metal machinery with a maximum height of 1.9m and a footprint of 2.2m by 2.1m; One switch room – a simple metal box building, finished in ‘holly green’ and 2.9m high, 14.9m long and 3.3m wide; One DNO substation – a series of metal frames with insulators, wires and machinery, up to 6m in height; Two welfare/storage/comms cabins – simple metal box buildings, both finished in ‘holly green’ and 2.6m high, 6.1m long and 2.4m wide; Perimeter fencing and gates – palisade metal up to 2.4m high; CCTV and lighting columns – simple vertical poles up to 4m high; One fire hydrant; Access track – a new track within southern fields running parallel to existing track/footpath, in order to allow existing track to retain its character; and, Hard and soft landscaping – details below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.